Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCDesign & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Calculator · Renovation · Programme risk

Project Delay Carrying-Cost Calculator

When a fit-out, a renovation or an occupancy certificate runs late, the cost is not one number. Put in the site costs that run only because the job runs longer, the money that carries interest while you wait and, if you want, the contribution you lose by opening later — the calculator keeps each one on its own line.

What this tool estimates

What a delay costs you while it lasts — avoidable site overhead, interest on the money tied up and any lost contribution you enter — each shown separately, with the cost per day of delay.

What it cannot decide

  • How long the delay will be — you enter it.
  • Whether any of it can be recovered from a contractor, landlord or anyone else. That depends on the contract and on who caused the delay; this is not a claim value.
  • Whether your overhead figure already contains interest, or your lost contribution already contains overhead — you must keep them apart.
  • Compounding, rate resets or further loan drawdowns during the delay.

Your inputs

Delay and site cost
calendar days

Costs that continue only because the job runs longer: site staff, security, hired plant, temporary power, site office, insurance extension. No interest here — it has its own line. Enter 0 if none.

Financing

The drawn balance or capital actually tied up during the delay — not the sanctioned limit or the whole project cost. Enter 0 if nothing is financed.

% a year

Enter 12 for 12% a year.

However your loan agreement counts interest.

Optional

Rent or margin you lose because the space opens or the plant produces later — net of costs you also avoid. Leave blank to leave it out; it must not include overhead or interest.

Your inputs stay in this browser. Nothing is sent anywhere unless you choose to send a review request further down this page — and that shows you exactly what it would send first.

Result

Cost of the delay —
Site overhead—
Financing (simple interest)—
Lost contribution—
Per day of delay — Overhead plus interest for each extra day.
Calculation steps
StepValue

Sensitivity: overhead + financing as the delay and the rate move (lost contribution excluded)
DelayRateOverhead + financing

Method version 6 October 2026. A screening estimate, not a design: see the limits below.

Method

How this calculator works — and where it stops

What it calculates

What a delay costs while it lasts: the site overhead that runs only because the job runs longer, the interest on the money tied up and — if entered — the contribution lost by opening or producing later, each shown on its own line, with the cost per day of delay.

Inputs

  • Delay in calendar days.
  • Avoidable site overhead per day, ₹ — costs that continue only because the job runs longer, with no interest in them.
  • Amount carrying interest, ₹ — the drawn balance or capital actually tied up during the delay.
  • Annual interest rate, % a year.
  • Day basis, 365 or 360 — as the loan agreement counts interest; the tool does not assume one.
  • Optional: contribution lost over the whole delay, ₹ — blank leaves it out.

Method

  1. Site overhead = delay days × avoidable site overhead per day.
  2. Financing = amount carrying interest × annual rate × delay days ÷ day basis — simple interest.
  3. Carrying cost = site overhead + financing.
  4. Cost of the delay = carrying cost + the lost contribution, when one is entered; when it is not, the result says so rather than counting it as ₹0.
  5. Per day of delay = overhead per day + amount × rate ÷ day basis.
  6. Sensitivity: overhead + financing at half and one-and-a-half times the delay and at the rate 2 points lower and higher, plus the financing on the other day basis.

Assumptions

  • The overhead figure contains no interest, and the lost contribution contains neither overhead nor interest. The tool cannot check this: counting one cost in two lines overstates the delay.
  • The amount is the balance that really carries interest through the delay — not the sanctioned limit or the project cost.
  • Simple interest at a fixed rate; no compounding, rate resets or further drawdowns during the delay.
  • Overhead and interest are both counted in calendar days.

Limitations

  • Not a claim value. Whether any of it can be recovered from a contractor, landlord or anyone else depends on the contract terms and on who caused the delay — a legal question this tool does not answer.
  • Does not estimate how long the delay will be.
  • The lost contribution is the user's figure; rent, sales and production are not modelled.
  • Excludes escalation of the remaining work, penalties under other contracts and tax effects.

Worked example

Produced by running this calculator with the inputs below.

Inputs

  • Delay 30 calendar days
  • Avoidable site overhead ₹5,000 a day
  • Amount carrying interest ₹1,00,00,000 (₹1 crore)
  • Annual interest rate 12%
  • Day basis 365
  • Lost contribution not entered

Working

  1. Site overhead = 30 × ₹5,000 = ₹1,50,000.
  2. Financing = ₹1,00,00,000 × 12% × 30 ÷ 365 = ₹98,630.14.
  3. Carrying cost = ₹1,50,000 + ₹98,630.14 = ₹2,48,630.14.
  4. Per day of delay = ₹5,000 + ₹1,00,00,000 × 12% ÷ 365 = ₹8,287.67.

Result. ₹2,48,630.14 (₹2.49 lakh) for a 30-day delay, excluding lost contribution.

Sensitivity — what moves the answer

  • The length of the delay drives everything: at 12% the carrying cost is ₹1,24,315.07 for 15 days and ₹3,72,945.21 for 45 days.
  • Two points on the rate moves the 30-day figure by about ₹16,438: ₹2,32,191.78 at 10% and ₹2,65,068.49 at 14%.
  • On a 360-day basis the same interest is ₹1,00,000 — ₹1,369.86 more than on 365 days.

How engineers use the result

To put a daily figure on a delay when deciding whether to spend money to avoid it — extra shifts, a temporary supply, an earlier inspection booking — with overhead, interest and lost contribution kept visible as separate lines.

When a professional design must replace it

Before the figure goes into a negotiation, a claim or a board paper: finance should confirm the drawn balance, the rate and the day basis from the loan agreement, the site team which costs really stop when the job finishes, and a lawyer what, if anything, is recoverable.

Sources

  • Simple interest: amount × annual rate × days ÷ day-count basis (actual/365 or actual/360) — standard day-count arithmetic; use the basis in your loan agreement
A site engineer in a hard hat holds a tablet on an office floor where renovation works continue behind barrier tape and cones on the left and a finished, occupied office sits on the right, with floating icons of a clock and schedule, a rising bar chart, a document and a closed barrier.
Concept illustration made for this page with an AI image tool — not a photograph of a Secured Engineers project.

Questions people ask before using it

What do I need before calculating the cost of a delay?

The expected delay in calendar days; the site costs that continue only because the job runs longer (site staff, security, hired plant, temporary power and water, site office, insurance extension), taken from your site budget rather than the project total; the balance that carries interest through the delay with its annual rate and the day basis in the loan agreement; and, separately, any rent, margin or other contribution you lose by opening or producing later.

Which site conditions could change the delay cost?

Anything that changes the length of the delay or the daily cost: a further query on an approval or an inspection, hired equipment and temporary supplies that have to stay longer, more of the loan being drawn while you wait, a floating rate that resets, and a tenant or production start that moves with the delay. Some overhead stops when the site demobilises, so on a long wait the daily figure can fall — rerun it for each stage.

What should I send an engineer for a project-specific review?

The existing layout, the landlord's provisions (the power, water, fire and HVAC capacity available to you), the renovation scope and the programme showing which activity is late and why. An engineer can then check which MEP tasks drive the delay and whether any can be re-sequenced or run in parallel to shorten it.

Optional: ask an engineer to look at it

The result above is yours with no form. If you want an engineer to check it against your drawings, schedules or bills, send a request. Nothing is sent until you press the button.

Exactly what this request will send
{}

Added automatically: this page's address, the tool name, the time, a reference number, the pages you opened on this site in this visit, how you arrived (landing page, referring site and any campaign tags) and your device type (touch or pointer, narrow or wide screen). Nothing else.

Prefer to talk? WhatsApp or the contact form.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Verify my numbers