Who Owns What: The Landlord and Tenant MEP Responsibility Matrix
Most leases say something like "the landlord maintains the base-building systems and the tenant maintains the systems within the demised premises". The trouble starts where those two zones meet: the AHU that serves one tenant but sits on another floor, the riser that feeds a tenant's own distribution board, the chilled-water pipe crossing one tenant's ceiling on its way to the next. A prose clause describes zones. Disputes happen at interfaces.
The fix is a component-by-component responsibility matrix, agreed before the next fault rather than argued during it. This guide covers the four questions it has to answer separately, fit-out permissions, common-plant billing, and an example matrix to negotiate from. It describes engineering boundaries and practical options; it does not draw legal conclusions, which belong to the lease and the parties' lawyers.
Ownership versus operating duty
"Base-build or tenant-installed" tells you who built a system. It does not tell you who runs it, who maintains it or who pays for it, and those can be four different answers for one component:
- Owns: whose asset register it is on, and who replaces it at the end of its life.
- Operates: who may start and stop it, change setpoints and isolate it.
- Maintains: whose maintenance contract covers it, and to what standard.
- Pays: energy and consumables, routine maintenance, breakdown repairs and replacement may each sit with a different party.
Some duties are also set outside the lease. The National Building Code of India 2016 (BIS) gives asset and facility management its own part, Part 12, covering the responsibilities of facility managers and of occupants for maintaining facilities. For electrical installations, the Central Electricity Authority's safety regulations of 2023 make the owner of an installation responsible for keeping it free from danger, and require additions or alterations to be approved by the Electrical Inspector or self-certified before they are connected. The matrix should therefore name, for each electrical installation, which party is treated as its owner for those duties (a point to confirm with your lawyer), and who holds and renews each statutory approval for the building.
Answer these questions for every component, with a drawing reference for each boundary:
| Question for each component | Why it matters | Evidence to hold |
|---|---|---|
| Who owns it, and whose asset register is it on? | Decides who replaces it and who insures it | Asset register; handover documents |
| Where exactly is the physical boundary: valve, isolator, flange or incomer? | Disputes start where nobody can point to the line | Marked-up as-built drawing |
| Who may operate it: start, stop, setpoints, isolation? | Prevents one party changing conditions for another | Operating procedure; BMS access rights |
| Who maintains it, under which contract and to what standard? | Stops the gap where each side assumes the other's contract covers it | Maintenance contracts and service reports |
| Who pays for energy, routine maintenance, breakdown repairs and replacement? | The four costs often follow different rules | Lease schedule; metering records |
| Who keeps the statutory records: inspection reports, test certificates, approvals? | Records are what an inspector or insurer asks for | Compliance file with a named custodian |
| Who may modify it, and with whose written approval? | Unapproved changes are how base-build systems lose their design basis | Fit-out approval records |
| Who pays when one party damages the other's system? | Cost should follow the cause, which needs evidence | Joint condition survey; fault log |
| Who may isolate it in an emergency, regardless of ownership? | Seconds matter in a leak, fire or electrical fault | Emergency protocol with named roles |
| How is the matrix updated after a fit-out change? | A matrix that describes the original fit-out stops matching the building | Change log attached to the schedule |
Fit-out permissions
Tenant fit-outs touch base-build systems: sprinkler heads moved for a new ceiling, detectors relocated, FCUs connected to the landlord's chilled water, new distribution boards fed from the riser, pantry drains tied into the stack. The matrix needs a fit-out section that says, system by system:
- What needs prior approval and what drawings the tenant submits: layouts, single-line diagrams, load schedules, sprinkler and detector relocations, drainage connections.
- Who may work on life-safety systems. Changes to sprinklers, detection or fire alarm can affect the building's fire approval, so the matrix should say who may work on them and how changes are tested and recorded.
- Capacity limits. The electrical capacity allocated to the space (in kVA), chilled-water capacity (in TR or kW thermal) and riser or shaft space; our guide to riser and shaft capacity disputes covers that clash.
- Testing and sign-off, including the electrical self-certification or inspection that new tenant installations need before connection.
- As-built handover and reinstatement: updated drawings for every change, and what must be restored at the end of the lease.
The engineering line between base-build and fit-out is set out in more detail in where base-build MEP ends and fit-out begins.
Common-plant billing
Central chillers, cooling towers, shared AHUs, DG sets, lifts, pumps, sewage treatment and fire systems serve everyone, so their cost has to be shared by an agreed rule. Keep units distinct: electricity in kWh (or kVAh where the tariff bills kVAh), chilled water as thermal energy (kWh thermal or TR-hours) measured by BTU meters, and capacity in kVA or TR. Whether electricity costs may be recovered from tenants through sub-meters, and on what basis, depends on the state's electricity regulations and the building's supply arrangement; confirm it with the DISCOM and your lawyer before writing it into the lease.
| Billing method | Fits when | Watch-outs | Metering needed |
|---|---|---|---|
| Share by area | Similar tenants with similar hours | Low users subsidise high users; disputes grow as uses diverge | Main meters only |
| Metered electricity (kWh sub-meters) | Tenants with different loads or hours | Meter accuracy, calibration and access; the regulatory position on recovery | A sub-meter per tenant, read and calibrated on a schedule |
| Metered chilled water (BTU meters) | Central chilled water serving several tenants | Installation quality of flow and temperature sensors; maintenance | A BTU meter on each tenant branch |
| Allocated capacity plus usage | Tenants reserving capacity, such as server rooms | Reserved but unused capacity still costs; define the allocation | Capacity register plus meters |
| Extended-hours charge | HVAC or DG supply outside agreed hours | Agree the hourly basis and how hours are logged | BMS run logs or plant run-hour meters |
| DG backup allocation | Shared DG supply during outages | Fuel cost, running hours, and priority during a shortfall | A kWh meter on each backed-up feeder |
For metering design and disputes, see tenant sub-metering and energy billing; for backup power, DG backup allocation between tenants.
Example matrix to negotiate from
The table below shows one way the split can be drawn in a multi-tenant building. It is an example to negotiate from, not a recommended or standard allocation; every cell is open to agreement, and the lease decides.
| Component | Owns | Operates | Maintains | Pays (example) | Boundary point |
|---|---|---|---|---|---|
| Incoming supply, transformer, main LT panel | Landlord | Landlord | Landlord | Common charges | Up to the outgoing feeder for the tenant |
| Rising mains or busbar riser | Landlord | Landlord | Landlord | Common charges | Tap-off or isolator at the tenant's floor |
| Tenant distribution board and final circuits | Tenant | Tenant | Tenant | Tenant, by sub-meter | From the distribution board incomer outward |
| Central chiller plant and primary pumps | Landlord | Landlord | Landlord | BTU meter or area share | Isolation valves on the tenant branch |
| AHU or FCU serving one tenant | Negotiable | Tenant for setpoints; landlord for the plant | Negotiable | Negotiable | Unit isolation valves and electrical isolator |
| Sprinkler mains, risers and floor control valve | Landlord | Landlord | Landlord | Common charges | Floor control valve |
| Sprinkler heads and branch lines in tenant space | Landlord | Landlord | Landlord | Tenant pays for relocations and damage it causes | Downstream of the floor control valve |
| Fire alarm panel and detectors | Landlord | Landlord | Landlord | Tenant pays for relocations | Agreed device list per floor |
| Plumbing risers and stacks | Landlord | Landlord | Landlord | Common; blockages charged to the cause where proven | Branch connection to the stack |
| Tenant toilets and pantry fittings | Tenant | Tenant | Tenant | Tenant | Downstream of the tenant's isolation valve |
| DG set and changeover | Landlord | Landlord | Landlord | Allocation policy | Tenant's backed-up feeder |
| BMS head-end and tenant points | Landlord | Landlord; tenant views agreed points | Landlord | Common charges | Agreed point list |
Keep the matrix live: a joint condition survey with photographs at handover, one shared fault log, an update after every fit-out change, and a pre-agreed emergency isolation protocol. When the renovation or fit-out comes, compare contractor quotations on the same scope with the MEP quotation comparison calculator, and plan the works under a turnkey EPC scope so the boundaries are drawn once, in the design. To start, share the existing layout, the landlord provisions and the renovation scope through a scope request; more planning guides are in Insights.
Sources and how to verify
- Bureau of Indian Standards, National Building Code of India 2016 (SP 7:2016): Part 12 Asset and Facility Management, as summarised in the BIS Guide for Using NBC 2016 (responsibilities of facility managers and occupants for maintenance; hard services including HVAC, electrical, plumbing, lifts and fire fighting).
- Central Electricity Authority, Measures relating to Safety and Electric Supply Regulations, 2023: regulation 32(8) on the owner's responsibility to keep installations free from danger, and regulation 45(6) on additions and alterations.
Confirm locally: the legal effect of the lease and any schedule with your lawyer, the basis for recovering electricity costs with your DISCOM, and who must hold and renew the building's fire approval with the fire authority.
Frequently asked
What do I need before drafting an MEP responsibility matrix for a lease?
The as-built MEP drawings and single-line diagram, the asset register, the landlord's fit-out manual, current maintenance contracts, the metering arrangement for electricity, chilled water and DG power, the statutory approvals for the building and who holds and renews each one, a list of installations the tenant has added, and the draft lease. Without drawings the boundary points cannot be fixed, and the matrix becomes another paragraph of prose.
Which building conditions make the landlord–tenant MEP split harder to agree?
Shared plant serving several tenants with no sub-metering, AHUs or risers that serve one tenant but sit in another's space, missing as-built drawings, base-build equipment near the end of its life, tenant loads above their allocated capacity, and tenants with very different operating hours. Each one needs an explicit decision in the matrix, and some, such as adding meters or upgrading a riser, need engineering work before they can be settled.
What should I send an engineer to map MEP boundaries for a fit-out or renovation?
The existing layout, the landlord's provisions for the space (allocated electrical capacity in kVA, chilled-water connections, fire and drainage provisions), the renovation scope, any as-built drawings, photographs of plant rooms, risers and distribution boards, and the details of existing meters. From those an engineer can mark each physical boundary on the drawings and list what the renovation changes.
Who maintains an AHU that serves only one tenant?
There is no default answer; it is a negotiated point. One arrangement keeps the landlord responsible for the plant and its maintenance while the tenant handles filters, grilles and setpoints within its space, with costs recovered by metering or an agreed share. Whatever is agreed, write it against the specific unit and its isolation points rather than leaving it to a general clause.
Should the responsibility matrix sit in the lease or in a separate document?
A practical arrangement is a schedule referenced in the lease and maintained as a technical document that is updated whenever a fit-out changes the systems, because leases are hard to amend and buildings change. How the schedule binds the parties is a question for the lawyers drafting the lease.
Related services
Guides that reference this page
- The Building Stays Open. The Chiller Still Has to Come Out.
- Office Fit-Out MEP Scope: Base-Build and Tenant Boundaries
- How to Retrofit a BMS Without Losing Control of Your Building
- The Future of MEP Engineering: 5 Technologies to Watch
- The MSME Act Just Changed. Here Is What It Means for a Factory Owner.
- MEP Design for a Hospital: NABH, Medical Gases, Isolation and Power Redundancy
Related on this site
- termTurnkey EPC
- termModule Mounting Structure
- termOpen Access (Solar)
- serviceCCTV & IP Video Surveillance (Low Voltage / ELV)
- serviceBattery / Hybrid Storage (Solar EPC)
- calculatorMEP Renovation Budget Calculator
- calculatorFire Noc Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guideNBC 2016 fire and life safety for factories
- guideFire NOC for factories
More on Project Delivery & Commercial · all insights