Check Riser and Shaft Capacity Before an Office Expansion

Updated 6 Oct 2026 · 9 min read · by

Two engineers in hard hats inspect an open service riser packed with pipes, ducts and cable trays between a finished open-plan office and a floor stripped for renovation.

An office expansion (more seats, a new meeting floor, a server room, a bigger pantry) is planned on the floor plate, but it is limited by the building's vertical capacity: what the risers and shafts can still deliver to your floor. In a multi-tenant building that capacity is shared and finite, and earlier fit-outs have already used some of it. The tenant who expands last is often the one who finds the shaft full or the allocation spent, usually after the lease or the design has been signed.

Four checks, done before the design is committed, avoid most of that.

Survey usable riser space

A shaft on the base-build drawing is not the same as usable space inside it. Over years of fit-outs, shafts collect abandoned cables, redundant pipes and penetrations sealed with whatever was at hand. Survey what is actually there, floor by floor, and ask the landlord for the base-build provisions and the rules for using them.

The CEA (Measures relating to Safety and Electric Supply) Regulations, 2023 set some of those rules for multi-storeyed buildings above 15 m and the other premises they list. No other service pipes or cables may run in ducts provided for power cables; every duct for power cables and other services needs a fire barrier at each floor crossing; power is distributed to the floors by bus bar trunking; and in buildings above 15 m the power cables must be fire-retardant, low-smoke and low-halogen (Regulation 38). A tenant's new cable or pipe therefore has to go in the shaft meant for it, and every new penetration has to be sealed.

Riser or shaftWhat to record on siteWhat to ask the landlord for
Electrical riserBusbar rating and tap-off rating at your floor, spare tap-off positions, free tray space, abandoned cables, condition of the fire barriers at each slabPower allocation per floor or unit, measured demand at your tap-off, DG back-up allocation, metering arrangement
HVAC: chilled water or refrigerantPipe sizes and valves at your floor, spare branch connections, space for new refrigerant pipesCooling allocation (flow or capacity) at your floor, chiller operating hours, rules for outdoor units
Fresh air and exhaust shaftsDuct sizes, dampers, free cross-section, access doorsFresh-air quantity allocated to your floor, toilet and pantry exhaust capacity
Plumbing and drainageStack sizes and positions, spare connections, vent stacks, access to clean-outsWater supply and drainage connections available, any limit on new wet areas
Fire servicesSprinkler and hydrant risers, the floor control valve, zone extentApproved fire drawings for your floor, sprinkler zone limits, the landlord's fire consultant's requirements
ELV and dataTray space for data, fire alarm and access-control cables, segregation from powerRules for telecom risers and for connecting to the building's fire alarm

Power, cooling, fresh air and water allocations

For each service, compare what the expansion needs with what the building allocates to your floor and what you already use:

  • Power. List the new loads (workstations, lighting, pantry equipment, any tenant air-conditioning, and a server room with its UPS and cooling) and estimate the demand, keeping kW and kVA distinct. Compare it with the floor allocation and with the measured demand at your tap-off, not with the sum of nameplates. The electrical spare-capacity calculator works from a single-line diagram and demand records, and the same method applies to an office floor. Check what share of your load the landlord's DG supports.
  • Cooling. Central chilled water is allocated by flow or capacity at the floor valve. A denser floor or a server room may exceed it, and may need cooling outside the building's operating hours. Supplementary units need outdoor-unit space and a refrigerant route the landlord accepts.
  • Fresh air and exhaust. More people need more outside air; NBC 2016 Part 8, Section 3 covers minimum ventilation rates in the breathing zone. New toilets and pantries need exhaust, routed to a shaft with capacity to take it.
  • Water and drainage. New wet areas load stacks sized for the original fixtures. Keeping them close to existing stacks is often the difference between a connection and a new riser.
If this is shortOptions, roughly from least to most disruptiveWho has to agree
PowerReduce or reschedule loads; use any landlord reserve; a higher-rated tap-off; a riser upgrade, which means a building-wide shutdownLandlord; the DISCOM if the building's sanctioned load must rise
CoolingRebalance within the floor; release unused allocation; supplementary units for the dense areasLandlord, for the plant, outdoor-unit space and pipe routes
Fresh airRebalance the existing air; a dedicated fresh-air unitLandlord, for facade or shaft openings
Water and drainageMove wet areas next to existing stacks; pumped drainage only as a last resortLandlord, with a plumbing design review
Riser spaceRemove abandoned services; re-route earlier installations; a secondary riser where the structure allowsLandlord and a structural engineer; the fire consultant for new openings
Fire zonesExtend within the zone limits; add a zone or valve setLandlord's fire consultant; the fire authority if the approved scheme changes

Firestopping interfaces

Every new cable, pipe or duct through a shaft wall or floor slab opens a hole in the building's fire compartmentation. NBC 2016 Part 4 treats shafts and other vertical openings as part of that compartmentation: openings must not compromise it, and shafts carrying building services need fire-resistance-rated inspection doors, depending on their location. The CEA regulations add a fire barrier at each floor crossing in ducts that carry power cables and other services.

In practice, survey the existing seals before you start, because earlier fit-outs often leave them disturbed. Use a tested firestop system suited to the fire rating of the wall or slab and to what passes through it, install it as its manufacturer requires, photograph and label each penetration, and have it inspected before the ceilings close. Any change that alters the approved fire scheme, such as new zones, relocated risers or new openings, goes to the landlord's fire consultant and, through them, to the fire authority where needed.

The landlord review package

Most landlords review tenant MEP changes against a fit-out manual. A complete package gets a quicker and clearer answer:

  • a scope narrative and drawings of the expansion;
  • a load schedule with the demand estimate, and the single-line diagram of the tenant distribution board and tap-off;
  • cooling and fresh-air requirements, and any supplementary units with their outdoor-unit locations;
  • plumbing connections to the stacks, and exhaust routes;
  • fire alarm and sprinkler changes with the fire consultant's view;
  • a penetration schedule with the firestop system for each penetration;
  • structural loads for heavy items such as UPS batteries and server racks, checked by a structural engineer;
  • method statements and working hours, especially for any riser shutdown that affects other tenants;
  • the electrical licence of the contractor doing the work: additions and alterations must be carried out by a contractor licensed by the State Government for electrical work (Regulation 31 of the CEA regulations).

If you are the landlord, the same package is how you protect the next tenant. Keep a live register of what each riser and allocation still has, and approve fit-outs against it, so that capacity becomes a leasing conversation rather than a construction problem. Shaft sizing for new buildings is covered in MEP shaft sizing, and spare capacity in cable containment in cable tray sizing.

Under our turnkey EPC scope we survey the risers and allocations first, then design the expansion to fit them or set out clearly what has to change. For a review of your floor, share the existing layout, the landlord's provisions and the renovation scope. Other renovation guides are on Insights.

Sources and how to verify

Confirm locally: the landlord's fit-out manual and base-build allocations, the approved fire drawings for your floor, and the fire authority's position whenever the approved fire scheme changes.

Frequently asked

What information do I need before planning MEP for an office expansion?

The landlord's fit-out manual and base-build provisions (the power, cooling and fresh air allocated to your floor), the current single-line diagram of your distribution and the measured demand at your tap-off, the headcount and equipment the expansion adds, any server or IT room with its UPS and cooling, new pantries or toilets, and the hours you will operate. With those, each riser can be checked against the new load before the layout is fixed.

Which building conditions can change the scope or cost of an office expansion?

A full or congested riser that needs abandoned services removed or a new route; a busbar tap-off rated below the new demand; no spare chilled-water or fresh-air capacity on the floor; no space for outdoor units; firestopping damaged by earlier fit-outs; sprinkler zones already at their limit; structural limits for battery or rack loads; and landlord rules on working hours and riser shutdowns. Any of these can add a landlord-side upgrade to a tenant project.

What should I send an engineer for a riser and shaft capacity review?

The existing layout, the landlord's provisions and fit-out manual, the renovation scope, base-build riser drawings if you have them, photographs of the shafts and distribution boards, recent sub-meter or electricity bill readings, and the list of loads the expansion adds. An engineer can then say which allocations hold, which are short and what the landlord will need to approve.

Can a tenant route new cables or pipes through any shaft in the building?

No. Follow the landlord's rules for each shaft. In multi-storeyed buildings above 15 m, Regulation 38 of the CEA 2023 regulations does not allow other service pipes and cables in ducts provided for power cables, and requires a fire barrier at each floor crossing. Every new penetration also has to be firestopped, to keep the compartmentation the fire scheme relies on.

Related services

Share the base-build capacity schedule, the fit-out layout and the lease's services clauses — the review starts from your documents.

Fit-out, renovation or a landlord–tenant scope question?

Tell us about your project and what you can send — an engineer reviews it and uses the number you give.

  • ★ 4.7 (239 Google reviews)
  • 535+ projects
  • Reply in 1 business day

Tells us which channels bring real projects. “I don’t remember” is a fine answer.

Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Speak to a Lead Engineer