How to Size Factory Solar From a Punjab Electricity Bill
Short answer: on a Punjab factory, solar sizing starts from the electricity bill, not the roof. Work out three capacities — what your consumption can absorb, what your sanctioned load allows and what your daytime load can use — and build the smallest. Then check which bill components solar actually avoids: the energy charge, not the fixed charge.
Three numbers, and you build the smallest
Monthly units divided by what one kilowatt generates in a month is the first number, not the answer. Our calculators plan with 120 kWh per kW per month, a North India annual average that is an assumption, not site data; the December–January fog months run below it. Use kWh for this — the kWh register if your bill shows one, or kVAh multiplied by the average power factor. PSPCL bills industrial energy in kVAh, and dividing kVAh by a kWh yield overstates the plant.
- Consumption capacity = monthly kWh ÷ 120 — the size whose output your factory would use.
- Sanction cap = sanctioned load in kW, or contract demand in kVA × 0.9, measured as the inverter's AC rating — the size PSPCL can connect.
- Daytime capacity = the plant whose generation your daytime load can use, block by block — the size that is self-consumed rather than credited at a lower value.
Where load has grown faster than the sanction, the second number can be a fraction of the first — which is why a proposal sized from units alone stalls at the application.
Bill components versus avoided charges
A PSPCL industrial bill is several charges, and rooftop solar touches only some of them. The components below are those of the FY 2026-27 tariff order (1 April 2026 to 31 March 2027); keep the table next to your own bill.
| Bill component | How it is charged | Does rooftop solar avoid it? | What to check |
|---|---|---|---|
| Energy charge | Per kVAh for small power, medium supply and large supply industrial categories | Yes, for units displaced on site or offset under net metering; where the tariff is kVAh-based, generation and consumption are settled in kVAh (PSERC regulation 12.3(f)) | Your category, its rate, and the kWh and kVAh readings |
| Time-of-day tariff | Peak and off-peak adjustments under condition 15 of the General Conditions of Tariff | Only within the same block or a cheaper one: surplus generation in a block is treated as if it occurred in the next lower-priced block (regulation 12.3(c)) | Consumption in each block; use in a higher-priced block is not offset by surplus from a cheaper one |
| Fuel and power purchase adjustment surcharge | Applied in addition to energy charges under condition 8 | Check how your bill applies it to net billed units | The surcharge line on each bill |
| Fixed charge | Per kVA per month on 80% of sanctioned load or contract demand (actual if higher, restricted to the sanctioned demand) | No — payable regardless of solar credits (regulation 12.3(g)) | Contract demand against recorded demand |
| Demand above contract demand | Any charge or notice on your bills for exceeding the sanctioned contract demand | Not reliably — the peak can fall at night, on a cloudy day or in the fog months | Twelve months of maximum demand |
| Voltage surcharge or rebate | A percentage of energy charges where supply is not at the specified voltage (condition 13) | Only in proportion to the energy charge | Supply voltage against the specified voltage |
| Power factor | Built into kVAh billing: a lower power factor raises billed kVAh for the same kWh | No — solar can lower the power factor of what is still drawn from the grid | Capacitor bank (APFC) settings after solar is added |
| Duty and other levies | Electricity duty and other levies on the bill | The regulation keeps them payable regardless of credits (regulation 12.3(g)) | How each line is computed |
Before anyone models a saving, work out what share of the bill is addressable at all. With heavy fixed charges and a night shift it is smaller, and so is the right plant. If the bill shows a poor power factor, fix that first; it can be cheaper than generating around it.
Sanctioned load or contract demand: the ceiling
This is the figure PSPCL has agreed to supply, in kW or kVA, and it is on the bill. It is not your connected load, the sum of everything you could switch on at once — PSPCL's own definitions keep the two apart. The PSERC regulation sets the plant's maximum against the sanctioned figure, measured as the inverter's AC rating; the DC module capacity can be higher, and a proposal should state both figures. Compare twelve months of recorded maximum demand with the sanctioned figure as well. If the factory routinely exceeds its sanction, the first question is whether to apply for a load extension, because that changes both the demand charges and the capacity solar is allowed to be. Load extensions for industrial connections are applied for through the state's industry portal, as PSPCL's FAQ sets out.
Interval daytime use: when you consume decides what solar is worth
A single-shift unit and a three-shift unit with the same monthly consumption are different propositions: the first uses nearly all of a correctly sized plant's output as it is made, the second sends more to the grid, where it is worth less. Monthly totals hide this. The bill's time-of-day split is a rough proxy; interval data from the meter's load survey, or a week of logging on the main incomer, is the real input. Look for:
- Midday base load on a working day — the floor the plant can feed without exporting.
- Weekly offs and holidays — a Sunday shutdown exports almost everything the plant makes that day.
- Seasonal shutdowns and the fog months — generation and load both move with the calendar.
- Load in higher-priced blocks — under the block-netting rule, midday surplus cannot offset consumption in a block priced above the one it was generated in.
Running a knitting or textile floor on two or three shifts changes the answer; see solar for a Ludhiana hosiery or textile unit.
Current PSPCL settlement rules
How surplus generation is settled depends on the arrangement you apply under. All figures below are from the PSERC rooftop solar regulations as amended on 7 April 2026; the settlement period runs from 1 October to 30 September (1 April to 31 March for the seasonal industries the regulation lists, such as rice shellers and cotton ginning units).
| Arrangement | Capacity (inverter AC rating) | What happens to surplus | Sizing logic |
|---|---|---|---|
| Net metering | 1 kWp up to 100% of sanctioned load or contract demand (kVA × 0.9), maximum 500 kWp | Carried forward within the settlement period under the time-of-day rules; credits left at the end are paid at 75% of the Commission's feed-in tariff for that year (regulation 12.3(d)) | Size to consumption the plant can offset within the settlement period |
| Net billing | 1 kWp up to the same 100%; no 500 kWp ceiling | Exports valued at the feed-in tariff, imports at the retail tariff; the billing credit carries forward and is paid at the end of the settlement period | Size to daytime self-use; exports earn only the feed-in tariff |
| Gross metering | 5 kWp up to the same 100% | All generation billed at the feed-in tariff, all consumption at the retail tariff | Compare the feed-in tariff with your energy rate before choosing it |
| Behind the meter | Up to 100% of sanctioned load or contract demand, with PSPCL's prior approval | No export: any injection is inadvertent and neither paid for nor settled | Size to the lowest daytime load, or add export-limiting control |
| Group net metering | 5 kWp up to the sum of the connections' sanctioned loads, maximum 500 kWp | Surplus at one premises offsets other connections of the same category, in a set priority and ratio | For owners with several units in the same supply area |
In every arrangement an exported unit is worth less than one used on site, so capacity beyond what the factory can use earns less per kW. PSERC sets the feed-in tariff each year; check the current figure.
Roof and interconnection constraints
- Transformer and feeder headroom. All rooftop solar on one distribution transformer or feeder may not exceed 80% of its rated capacity, and PSPCL must publish the capacity available and update it each year by 30 April (regulations 5.1–5.2).
- Roof structure. Whether purlins and sheeting can carry the added dead and wind load is a structural engineer's decision, not something a bill or a calculator can answer.
- Usable area. Skylights, vents, tanks and parapet shadows reduce the paper figure, and the CEA safety regulations require clear pathways at least 75 cm wide, with handrails, for roof access and emergency exit (regulation 121).
- Protection. The plant must detect an unintended island and stop feeding the grid when supply fails (PSERC regulation 6.6; CEA connectivity regulations for distributed generation, regulation 11). A grid-tied plant is therefore not backup power; what a battery or DG integration changes is covered in solar with battery backup for a Punjab factory.
- DG changeover. The changeover wiring decides how solar and the DG are interlocked; solar back-feeding a running DG set damages equipment.
A worked example — illustrative, not a quotation
The figures below are constructed for this article. They are not a customer's bill and not an offer.
- Contract demand: 300 kVA; twelve-month peak recorded demand 268 kVA
- Monthly consumption: about 95,000 kVAh billed, about 90,000 kWh on the kWh register (average power factor near 0.95)
- Shift pattern: single shift, roughly 9 am to 6 pm, six days a week
Consumption capacity: 90,000 ÷ 120 = 750 kW. Sanction cap: 300 kVA × 0.9 = 270 kW AC — inside the 500 kWp net-metering ceiling. Daytime capacity: at 120 kWh per kW, a 270 kW plant makes about 32,400 kWh a month, well below what a single-shift factory of this size draws in working hours, so it does not bind. The plant is about 270 kW AC — just over a third of what the units suggest — if the roof, the structure and the transformer headroom allow it. For an indicative budget at this size, the 250 kW plant cost page states its band and tax basis; the solar calculator runs the financials on your own numbers. No central subsidy reduces that figure: MNRE's PM Surya Ghar guidelines give no central financial assistance to commercial or industrial connections.
The bill gets you to a capacity range and the constraint that binds, not to a design. Send twelve months of bills, any interval data and the roof layout for a scope review; delivery is under Solar EPC, and more guides are in Insights.
Sources and how to verify
- PSERC (Grid Interactive Rooftop Solar Photo Voltaic Systems) Regulations, 2021, consolidated up to the third amendment — PSERC, amendment notified 7 April 2026 and published 11 April 2026; PSPCL consolidated copy of 8 July 2026. Regulations 2(za), 4.2, 5.1–5.2, 6.6, 12.3, 13 and 14.
- Existing and new tariff for FY 2026-27 — PSERC tariff order for PSPCL, applicable 1 April 2026 to 31 March 2027 (energy charges per kVAh, fixed charges per kVA, fixed-charge basis).
- PSPCL FAQ on new connection and extension of load — definitions of connected load, sanctioned load and contract demand, and the application route.
- CEA (Measures relating to Safety and Electric Supply) Regulations, 2023 — Central Electricity Authority, notified 8 June 2023; regulation 121 on solar installations.
- CEA technical standards for connectivity of distributed generation resources, 2013 (amended 2019) — regulation 11, anti-islanding and synchronisation.
- Guidelines for PM Surya Ghar: Muft Bijli Yojana — MNRE, 16 April 2024; no central financial assistance for commercial and industrial consumers. Other schemes: MNRE solar schemes.
Confirm locally: the regulation and tariff order in force on the day you apply, the feed-in tariff for the year, the capacity PSPCL shows as available on your transformer, and how your own bill computes each surcharge.
Frequently asked
What do I need from my Punjab electricity bills before sizing factory solar?
Twelve months of bills, all pages. From them: the sanctioned load or contract demand; the kWh and kVAh consumption for each month (industrial energy charges are billed per kVAh, but solar yield is estimated in kWh); the maximum demand recorded each month; the consumption in each time-of-day block if your connection is on time-of-day tariff; the tariff category and supply voltage; and the fixed-charge, surcharge and levy lines. Add anything the bill does not show: shift pattern, weekly offs, seasonal shutdowns and planned load additions.
Which site conditions can change the solar size or budget on a Punjab factory?
The capacity left on your distribution transformer or feeder, because all rooftop solar on it may not exceed 80% of its rating; the roof structure, which a structural engineer has to assess; shading, skylights and obstructions; the walkways the CEA safety regulations require on a rooftop plant; how the DG changeover is wired; the supply voltage and metering point; and loads that run after dark. A plant can also be held below its sanctioned-load figure by any one of these.
What should I send an engineer for a solar sizing review of my factory?
Twelve months of electricity bills, interval or load-survey data if you can get it (or a week of logging on the main incomer), the roof layout with photographs, the single-line diagram including the DG changeover, the shift pattern, and any load you plan to add. With those an engineer can give a capacity range your connection supports and say which constraint binds. A design still needs a site survey.
What percentage of sanctioned load can a rooftop solar plant be in Punjab?
Up to 100% of your sanctioned or contracted load, or of your sanctioned contract demand converted to kW at a power factor of 0.9, measured as the inverter's AC rating — under regulation 4.2 of the PSERC rooftop solar regulations as amended on 7 April 2026. Net metering is capped at 500 kWp; net billing and behind-the-meter arrangements go up to the same 100% without that ceiling; gross metering starts at 5 kWp. Separately, all rooftop solar on one distribution transformer or feeder may not exceed 80% of its rated capacity (regulation 5.1), so a site on a busy transformer can be held below its own figure.
Will solar remove my entire factory electricity bill?
No. Solar reduces the energy charge for the units it displaces or offsets. The PSERC regulation keeps fixed or demand charges and government levies payable whatever credits the plant earns (regulation 12.3(g)), and PSPCL's fixed charge for industrial consumers is levied per kVA on 80% of the sanctioned contract demand, or on the recorded demand if that is higher, up to the sanctioned figure. Demand overshoot is rarely solved by a rooftop plant, because the factory's peak need not fall when the sun is strong. Any proposal that shows the whole bill going to zero has not read the bill.
Does my connected load decide how much solar I can install?
No. Connected load is the sum of the rated capacities of everything that can be switched on at once; the sanctioned load or contract demand is what PSPCL has agreed to supply, and it is printed on your bill. The PSERC regulation caps rooftop capacity against the sanctioned figure. A plant sized against connected load can fail at the application stage, after the money has been committed.
Related services
Guides that reference this page
- Solar for Printing Presses: Sizing, Roof, Approvals and Payback (50 kW+)
- Time-of-Day Tariffs and Solar: How ToD Changes the Payback for HT Consumers
- Solar for Dairy Plants: Sizing, Roof, Approvals and Payback (50 kW+)
- Solar for Chemical Plants: Sizing, Roof, Approvals and Payback (50 kW+)
- Solar for a Ludhiana hosiery or textile unit — sized to how the floor actually runs
- Your solar plant switches off in a power cut. Here's what a battery changes in Punjab.
Related on this site
- termSolar Payback Period
- termCAPEX vs OPEX Solar
- termOpen Access (Solar)
- serviceSolar mounting structures and BOS
- serviceSolar plant O&M and performance
- calculatorSolar Roof Load Calculator
- calculatorSolar Amc Cost Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guidePESO licence for diesel storage
- guideFactory licence and DISH approval
More on Solar & Renewables · all insights