Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Costing & Procurement

How to compare MEP contractor quotations: one set of quantities, one scope, one basis for tax and payment

Updated 6 Oct 2026 · 9 min read · by

Two engineers in hard hats and high-visibility vests mark up printed drawings side by side at a long table in an industrial hall, with a laptop beside them and electrical panels, cable trays, ducts and red fire mains behind.
Concept illustration made for this page with an AI image tool — not a photograph of a Secured Engineers project.

Three quotations for the same MEP package rarely price the same package. One bidder has measured the cable from the drawings and another has estimated it from floor area; one names its chiller and another writes "reputed make"; one is silent on testing and as-built drawings; one asks for a large advance. Award on the lowest total and you award on whichever bid left out the most.

The fix is to compare in a fixed order — the same quantities, then the same scope, then the same makes, then the same tax and payment basis — and only then the totals. Start with each bid's priced BOQ line by line, its exclusions sheet and its commercial terms, all priced on the same drawing revision; if two bidders priced different revisions, re-issue and re-price, because no adjustment fixes that. The MEP quotation comparison calculator does the arithmetic of the first two steps.

1. Price every bid against common quantities

A quotation is rates multiplied by quantities. If the quantities differ between bids, the totals differ for a reason that has nothing to do with price. Fix one quantity per line — from your own BOQ, or measured from the drawings — and multiply each bidder's rate by it. Where a bidder's own quantity differs materially, ask how it was measured: a short quantity in an item-rate bid is a future variation, and a long one may be padding inside a lump sum. These are the lines where the differences hide:

LineCompare inCommon quantity fromWhat a different bidder quantity usually means
LT power and control cablesm, by size and coresCable schedule measured along the routes on the drawingsRoutes estimated from area, or vertical drops and terminations counted differently
Cable trays and racewaysm, by width and typeTray layout drawingsBends, tees and supports in the rate for one bidder, measured separately by another
EarthingPits by number; strip or conductor in m, by sizeEarthing layoutA different pit construction or conductor material behind the same count
Panels and distribution boardsNumber, each against its feeder scheduleSingle-line diagramA "panel" priced without the same feeders, metering or protection
Lighting and power pointsNumber, by typeLayouts and point scheduleA different definition of what one point includes
Ductworkm² of sheet, by thicknessDuct layout on coordinated drawingsFittings measured as area by one bidder and as numbers by another; floor-area estimates
Duct and pipe insulationm² or m, by thicknessDrawings and insulation specificationThinner insulation, or exposed runs left out
Chilled-water, condenser-water and fire mainsm, by diameter and pipe classPiping layoutsFittings, supports and valves inside the pipe rate or counted separately
Sprinklers, hydrants and hose reelsNumber, by typeFire layout drawn to your fire schemeCoverage designed by the bidder rather than to your scheme
Plumbing pipework and fixturesm by diameter; fixtures by numberPlumbing layouts and fixture scheduleOwner-supplied sanitaryware assumed by one bidder, priced by another

On an item-rate bid, also read the rates against each other. High rates on early items and low rates on late ones, or high rates on items whose quantity is likely to grow, leave the total unchanged while moving money earlier or into the variations.

2. Put a price on the scope each bid leaves out

Build a matrix with every element of the work as a row and each bidder as a column, and mark each cell included, excluded or silent. Silent is the state that matters: a quotation that does not mention testing has not priced it, and the bidder will say so after award. For each excluded or silent item, add an allowance before comparing totals — the rate another bidder quoted for it or, where nobody priced it, your own estimate, marked as one. Provisional sums must be the same figure in every bid, or they are not comparable.

A worked example, with illustrative figures: Bid A totals ₹10 lakh but omits scope that Bid B prices at ₹2 lakh, so on the common scope Bid A is ₹12 lakh. Bid B is ₹11.5 lakh all-in — ₹50,000 lower on the same defined scope, although its headline was higher.

The rows bidders commonly treat differently:

  • Design responsibility — full design, or installation to someone else's drawings
  • Statutory applications — who prepares the files for the Fire NOC, the electrical inspection and the DISCOM connection, and who pays the fees. The decisions belong to the authorities, so price the work, never an outcome.
  • Owner-supplied items — DG set, transformer, lifts, light fittings, sanitaryware, BMS
  • Testing, adjusting and balancing, and integrated commissioning
  • As-built drawings, O&M manuals and training
  • Civil interfaces — plinths, trenches, core cutting, fire-stopping
  • Site facilities — construction power and water, storage, scaffolding

3. Check that "equivalent" makes really are equivalent

A lower price on a different make is a saving only if the alternative meets the same specification:

  • The same rating at the same conditions. A chiller's capacity and efficiency mean nothing without the water temperatures or ambient they were rated at; an AHU's airflow means nothing without its external static pressure. Keep tonnes of refrigeration and kW of cooling, which are thermal capacity, apart from the kW the machine draws.
  • The same standard and certification. Several common MEP items are on the Bureau of Indian Standards' compulsory-certification list: PVC-insulated cables up to and including 1,100 V (IS 694), switches (IS 3854), residual current circuit breakers (IS 12640) and circuit breakers for overcurrent protection (IS/IEC 60898) under the Electrical Wires, Cables, Appliances and Protection Devices and Accessories (Quality Control) Order, 2003, and outdoor oil-immersed distribution transformers up to 2,500 kVA and 33 kV (IS 1180 Part 1) under the Electrical Transformers (Quality Control) Order, 2015. An alternative make of a listed item needs a valid BIS licence for that standard; BIS's Know Your Standards portal lists the licences issued against each one.
  • The same tests and support. Routine and type test certificates to the same standard, factory acceptance tests where specified, and comparable warranty terms, service presence and spares.

Where a bidder offers a lower-tier alternative, ask for the specified make to be priced as well. The comparison then runs like for like, and the alternative becomes a separate decision with its own saving attached.

4. Bring taxes onto one basis

Compare the totals before GST, and deal with the tax line separately. Ask every bidder to show GST as its own line, with the rate and classification applied — one rate on a single works-contract price, or separate rates on supply and on installation. If two bids treat the same scope differently, resolve it with the bidders and your tax adviser before award; a smaller tax line is not a lower price if it is wrong.

What the GST finally costs you also depends on input tax credit. Section 17(5)(c) of the CGST Act, 2017 blocks credit on works contract services supplied for construction of an immovable property, other than plant and machinery, except where they are an input service for a further supply of works contract service; the Act's explanation counts renovation, additions and alterations as construction to the extent they are capitalised. Which side of that line your package falls on is a question for your tax adviser, not something to infer from a quotation.

5. Put the payment terms into the price

Two bids with the same total are not the same price if one asks for its money earlier. Write each payment schedule out as amounts against milestones: the advance and its security (a bank guarantee, or nothing); material and running payments, and whether they follow joint measurement; retention and when it is released; price validity and the escalation basis — copper and steel escalation clauses deserve their own reading; and the defect-liability period, including whether it covers parts.

Money paid earlier has a cost: the amount, multiplied by your own cost of funds, for the months it is paid ahead of the work. Where bids are close, that cost — and the risk of an unsecured advance — can decide the order. The retention and final-bill terms decide how the last part of the money moves.

The decision table: what to do with each difference

Difference foundTreatment before comparing totalsQuestion for the bidder
Different quantity on a measured linePrice the common quantity at the bidder's rateHow did you measure it, and from which drawing revision?
Item excluded, or silentAdd an allowance at another bidder's rate, or at your own estimateWill you price it now, at the same rates as the rest of your bid?
Provisional sums differReplace them with one common figure in every bidWhat is your figure based on?
Lower-tier or unnamed makeCompare on the specified make, priced by the bidderDoes the alternative meet the specification at the same rating and standard?
Rating stated at different conditionsRestate at the specified conditions before comparingAt what conditions are your capacity and efficiency rated?
GST shown differentlyCompare before tax; settle the tax treatment separatelyWhich rate and classification did you apply, and why?
Larger or unsecured advanceAdd the cost of money for the months it is paid earlyWill you take a smaller advance, or one against a bank guarantee?
Short validity or open escalationPrice the exposure, or ask for a firm priceAgainst which index, from which base date, and with what cap?
Shorter or labour-only defect liabilityTreat the difference as a cost of that bidWill you match the specified period and cover parts?

Then ask the low bidder to explain the number

Once the bids are on one basis, any remaining gap is margin, efficiency or method. Ask the lowest bidder to walk through the price against the BOQ: a leaner but compliant design or a make that meets the specification is a good answer; silence on the lines where they are cheapest is not. The L1 award that backfires is usually the one where nobody asked.

Most of this work disappears if the tender goes out with one measured BOQ, named makes and a mandatory exclusions sheet — the tender BOQ checklist covers how — and why per-square-foot MEP costs vary gives a sense check before bids arrive. The one-page checklist condenses this method, and more planning guides are on the Insights page. The work itself is delivered under turnkey EPC; to have bids lined up against one scope, share the project layout and equipment schedule for a scope and BOQ review.

Sources and how to verify

Confirm locally: the GST treatment and your input-tax-credit position for this contract with your own tax adviser, and that the BIS licence of any alternative make is valid on the date of supply.

Frequently asked

What do I need in hand before comparing MEP contractor quotations?

The BOQ or drawings every bidder priced, with revision numbers; each bid’s priced BOQ line by line rather than a summary; each bid’s exclusions and assumptions sheet; the make list for major plant; and the commercial terms — validity, escalation, payment schedule, retention, defect liability and the tax line. If two bidders priced different drawing revisions, re-issue the documents and ask for revised prices; no adjustment fixes that.

Which site conditions make MEP quotations hard to compare?

Conditions that change labour or quantities and that each bidder may have assumed differently: working hours and shutdown windows on a live site, access and lifting for heavy plant, the distance from the point of supply to the main panels, existing services to be retained or diverted, storage space, and construction power and water. State them in the enquiry, and check that every bid assumed the same ones before comparing prices.

What should I send an engineer to review competing MEP quotations?

All the quotations in full, the drawings and BOQ the bidders priced with their revision numbers, the scope split between the MEP package, civil works and owner-supplied items, any pre-bid clarifications, and your target dates. A useful review returns a scope matrix across the bids, the gaps priced at the rates the bids themselves contain, and the questions to put to each bidder before award.

Why do MEP quotations for the same building differ so much?

Usually because they are not quoting the same building. Differences in scope (who prepares the approval files, who supplies the DG set), in makes (a named chiller against an unnamed one), in quantities (a cable schedule measured from drawings against one estimated from area) and in exclusions (testing, as-built drawings, site facilities) account for much of the spread before any difference in margin appears.

Should the lowest MEP quotation be rejected automatically?

No — it should be explained. Once the bids are on one basis, ask the lowest bidder to walk through the price against the BOQ. A low price with a clear basis — a leaner but compliant design, a make that meets the specification, a genuine efficiency — is a good price. A low price whose basis is scope missing from the quote is a variation order waiting to happen.

Related services

Send the BOQ, the quotations you are comparing or the drawings the budget is for — the review starts from your documents, not a rate card.

Comparing quotes or building a budget?

Tell us about your project and what you can send — an engineer reviews it and uses the number you give.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Speak to a Lead Engineer