Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Costing & Procurement

Documents your EPC contractor should deliver — design basis, test records, asset register and as-builts

Updated 6 Oct 2026 · 9 min read · by

Two engineers in hard hats review drawings next to a stack of bound document folders and a laptop at a workbench in a new factory hall, with switchgear, fire mains and ducts behind.
Concept illustration made for this page with an AI image tool — not a photograph of a Secured Engineers project.

Every MEP or EPC contract produces two things: an installation and a paper trail. The installation is what you inspect at handover. The paper trail is what you open for the next electrical inspection, the Fire NOC renewal, the insurer, the next expansion and the day something fails — long after the contractor has left. Without it, nobody can describe what was built.

The way to get it is to write the documents into the contract as deliverables, each with a due date, a format and the payment it unlocks. This page lists them in the order a project produces them, with a checklist you can attach to the contract and a table of what to do when something is missing.

Before award: the documents that qualify the contractor

These say nothing about engineering quality; they establish that you are contracting with a registered entity that is allowed to do the work. Ask for the company registration and a GSTIN that match the proposal, EPF and ESI registrations for the site workforce, completion certificates for comparable work with a client contact you can call (how to verify them is its own subject), and accounts or a banker's reference adequate for the contract value.

Above all, ask for the electrical contractor licence. Under regulation 31 of the CEA (Measures relating to Safety and Electric Supply) Regulations, 2023, electrical installation work — including additions, alterations and repairs — must be carried out by an electrical contractor licensed by the State Government, under the direct supervision of a person holding a certificate of competency, and work done otherwise must not be energised or connected to the supplier's works. Check that the licence and the supervisor's certificate are current in your state.

1. Design basis and approved drawings

The design basis is the document that says what the building was designed to do: the loads, the design conditions, the occupancy and hazard assumptions, the redundancy, and the codes and editions the design follows. Without it, nobody can later say whether a system is undersized or simply being asked to do more than it was designed for — the first question every expansion raises. The drawings then record what was approved, by whom and at which revision.

Ask for the documents below in your format, with a drawing register that shows every revision and its status: issued for comment, approved, or good for construction.

DocumentWhat it must containApproved byDue before
Design basis reportLoads, design conditions, occupancy and hazard assumptions, redundancy, the codes and their editions, and every assumption the owner must confirmOwner, or the owner's consultantDetailed design starts
Electrical load list and single-line diagramConnected load and maximum demand in kW and kVA; transformer, DG and panel ratings; the basis for protection settingsOwner; the Electrical Inspectorate too, where your state approves drawingsLong-lead electrical orders
Fire scheme drawingsOccupancy and hazard classification, the systems provided, pump and water-storage capacitiesOwner; the fire authority too, where it approves the schemeFire works start
HVAC design basis and heat-load calculationIndoor and outdoor conditions and their source, fresh-air basis, process loads, operating hoursOwnerPlant selection and ordering
Plumbing and drainage basisWater demand, storage, treatment and discharge basisOwnerTank and plant-room civil works
Drawing registerEvery drawing with its revision, date and statusContractor maintains; owner checksEvery drawing issue
Coordinated services and shop drawingsRoutes and levels resolved between trades and against the structure; plant-room layoutsOwner or consultantInstallation in that area
Material submittalsMake, model, data sheet and compliance with the specification for each itemOwner or consultantOrdering that item

2. Inspection and test records

Ask for an inspection and test plan at the start: every inspection and test, the standard it follows, the acceptance value, who witnesses it and the record it produces. Then insist on the records as the work proceeds — tests on concealed work cannot be repeated once the slab is poured or the ceiling closed.

  • Manufacturers' test certificates, filed against the BOQ line as material arrives. For apparatus above 650 V, regulation 48(1) of the CEA regulations allows the Electrical Inspector to require the type, acceptance and routine test certificates before approving the installation.
  • Stage inspections before concealment — cables tested before walls close, pipework pressure-tested before it is insulated or buried, ducts leak-tested before the ceiling.
  • Site tests with values, not ticks — insulation resistance by circuit, earth resistance by pit, test pressures and durations, pump duty points, air and water quantities after balancing. Regulation 48(2) requires new apparatus, cables and supply lines above 650 V to be site-tested to the relevant standards before commissioning.
  • The energisation file. An installation above the voltage your state has notified is inspected and approved in writing by the Electrical Inspector before supply starts; one at or below it is self-certified by the owner, with the report submitted to the Electrical Inspector (regulation 45). The distribution company either tests the installation or accepts test results signed by the licensed electrical contractor (regulation 33). The contractor produces the results and forms; the owner signs what is the owner's to sign.
  • Commissioning and integrated test reports — the fire alarm's cause-and-effect with dampers, fans and AHU shutdowns; mains, DG and UPS changeover; plant run at design duty — with calibration certificates for the instruments used.

For what an electrical commissioning file should hold, test by test, see what to check during electrical testing and commissioning.

3. Asset register and warranties

The asset register is the list your maintenance team, or your next AMC contractor, works from. Ask for it as a spreadsheet in the format your maintenance team uses, one row per asset:

  • Tag number and location, matching the as-built drawings
  • System, make, model and serial number
  • Rating with its unit — kVA for a transformer, kW for a motor, TR for a chiller, flow and head for a pump
  • Supplier, date of supply and date of commissioning
  • Warranty start, end and conditions, including any condition that servicing be done by the manufacturer or its authorised agent
  • Commissioning test values — the baseline every later reading is compared with
  • Recommended spares, with part numbers

Warranty certificates should be in the owner's name, not the contractor's. The defect-liability schedule — when it starts, when it ends, how a defect is reported and what the contractor must then do — belongs with the register; defect-liability disputes usually begin where that schedule was vague.

4. As-built drawings and O&M deliverables

  • As-built drawings for every discipline — routes, sizes, levels and positions as installed, marked as built, dated and signed, in editable format as well as PDF. Not the tender drawings with a new stamp.
  • Operation and maintenance manuals — a description of each system, its operating and shutdown procedures, the maintenance schedule from the manufacturers' manuals, data sheets and spares lists.
  • Training records — who was trained, on what, and by whom.
  • The approvals file — each approval, inspection report or self-certification, with its conditions and its renewal or re-inspection date written down.
  • The start of the records you must keep. For installations above 650 V, the CEA regulations require records of all tests, trippings, maintenance work and repairs to be kept so they can be compared with past records (regulation 48(6)), and, in the regulation on earthing for apparatus above 650 V, every earthing system to be tested for earth resistance on a dry day at least once a year, with the records kept (regulation 50(8)). The handover file is where those records begin.

What goes wrong when this set is missing is covered separately.

When a document is missing: the decision table

Tie each document to the payment that should wait for it. Late paperwork is a cost the owner carries for the life of the building, so the contract should make it the contractor's cost first.

Missing documentWhat it costs you laterTie it to
Design basis reportNo way to tell whether a system is undersized or overloaded; every expansion starts with a surveyThe design-stage payment
Approved drawings and the registerDisputes over which revision was approved and pricedStart of work in each area
Manufacturers' test certificatesThe Electrical Inspector may ask for them; warranty claims are harder to makeThe material bill for that item
Site test records with valuesNo baseline, and concealed work cannot be retestedThe stage bill for that work
Energisation fileSupply cannot startThe energisation milestone
Asset registerThe AMC cannot be scoped or priced; warranties lapse unnoticedThe final bill
Warranty certificates in the owner's nameClaims refused, or routed through a contractor who has moved onThe final bill
As-built drawingsThe next modification works blindThe final bill or retention release
O&M manuals and training recordsOperating errors and avoidable breakdownsHandover
Approvals file with renewal datesRenewals and re-inspections missedHandover

Writing it into the contract

List the deliverables with due dates and formats, and make each stage payment depend on that stage's records. A contractor who produces these as routine will not object; the objection is itself information.

The turnkey EPC page lists what the client receives at each of its fourteen stages, and testing and commissioning is the service that produces most of the records above. The project estimator lays out the phases these documents belong to; the tender BOQ checklist is the companion page for a tender, and more planning guides are on the Insights page. For a document list fitted to your project, share the project layout and equipment schedule for a scope and BOQ review.

Sources and how to verify

  • Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023 — Central Electricity Authority, notified 8 June 2023. Regulations 31 (licensed electrical contractors), 33 (testing of a consumer's installation), 45 (Electrical Inspector's approval and self-certification), 48 (testing, operation and maintenance above 650 V) and 50(8) (annual earth-resistance tests), as cited above. CEA's regulations page also lists an amendment notified in 2026; check it, and any later one, before relying on a provision.
  • National Building Code of India 2016 (SP 7:2016) — Bureau of Indian Standards. The model code for fire and life safety (Part 4), building services (Part 8) and plumbing services (Part 9) that design bases commonly cite; how it is adopted varies by authority.

Confirm locally: the voltage your state has notified for self-certification, whether your state's Electrical Inspectorate approves drawings before work starts, and which documents your fire authority asks for at inspection and at renewal.

Frequently asked

Which documents should an EPC contractor provide before the contract is awarded?

Proof of who you are contracting with and that they may do the work: company registration and a GSTIN that match the entity on the proposal, the electrical contractor licence issued by the State Government with the supervisor’s certificate of competency, EPF and ESI registrations for the workforce on your site, completion certificates for comparable work with a client contact you can call, and audited accounts or a banker’s reference adequate for the contract value.

What should be agreed before an EPC contractor starts producing project documents?

The deliverables list itself, with a due date and a format for each item; the drawing numbering and revision system; the design standards and the editions to be cited; the asset-register template your maintenance team uses; which approvals and inspections the project needs and who prepares each file; and which payment each set of documents unlocks. Agreeing this at the start costs nothing. Reconstructing it at handover is slow and never complete.

Which site conditions change the documents an EPC contractor has to deliver?

The supply voltage first: an installation above the voltage your state has notified is inspected and approved by the Electrical Inspector before supply starts, with test records to match. Generating units such as DG sets and solar above the capacity your state has notified need inspection before commissioning. An installation of more than 250 kW connected load, including a registered factory, needs a designated Electrical Safety Officer who keeps annual inspection records. Brownfield sites add surveys of retained services; live sites add shutdown method statements.

What should I send an engineer to check a contractor’s handover documents?

The contract’s list of deliverables, the drawing register and the as-built drawings received, the test and commissioning reports, the energisation and approvals file, the asset register and warranty certificates, and a note of anything the contractor says is still to come. The check compares what was delivered against the contract and against the installation, and lists what is missing or inconsistent before the final bill is paid.

Is an ISO 9001 certificate proof of a contractor’s quality?

It is proof that the contractor has a documented quality system that an auditor has checked. It is not proof of the outcome on your site. Treat it as one of several qualification documents, and weigh it below completion certificates from comparable projects and the quality of the drawings and test records the contractor actually produces.

Related services

Send the BOQ, the quotations you are comparing or the drawings the budget is for — the review starts from your documents, not a rate card.

Comparing quotes or building a budget?

Tell us about your project and what you can send — an engineer reviews it and uses the number you give.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Speak to a Lead Engineer