Does ALMM apply to a behind-the-meter captive solar plant?

18 October 2026 · 3 min read · by

Summary card: DCR, ALMM List-I and ALMM List-II are three separate rules; a private captive plant behind the meter is outside both ALMM lists

For a private consumer, no. MNRE's clarification of 4 August 2026 (O.M. No. 283/54/2026-GRID SOLAR), para (e), says ALMM List-I and List-II shall not apply to behind-the-meter solar power plants solely used for captive consumption by a consumer or group of consumers, other than Government entities or Public Sector Enterprises. A private factory running a plant behind its own meter, for its own load, is outside both lists: modules and cells.

Why the connection decides it, not the owner

The exemption rests on two words in the order: behind-the-meter and solely. The same O.M. defines "net-metering" to cover Gross Metering, Net Billing, Net Feed In, Virtual Net Metering, Group Net Metering, etc. but excluding Behind-The-Meter connections. So the test is how the plant is wired and settled:

How the plant connectsALMM List-I (modules)ALMM List-II (cells)
Private consumer, behind the meter, solely captiveDoes not applyDoes not apply
Net-metered, net-billed, gross-metered or open accessAppliesExempt if commissioned by 31 December 2026; applies after
Government entity or PSU, behind the meterAppliesExempt if commissioned by 31 December 2026; applies after

A plant described as captive whose output is in fact exported or settled through the DISCOM is a net-metering project for this purpose, whatever the proposal calls it. That is the failure we see: a module choice made on the "captive" label, then a connection application that says otherwise.

What this does not settle

  • DCR. Para (f) of the same O.M. says the ALMM orders have no effect on Domestic Content Requirement. If a subsidy or scheme imposes DCR, it still applies to a behind-the-meter plant. See DCR vs non-DCR for a commercial plant.
  • The DISCOM's own process. Whether your utility asks for anything beyond MNRE's position is a separate check.
  • Later orders. Check the MNRE ALMM page for anything issued after 4 August 2026 before you buy modules.

We will not suggest changing a connection to escape a module rule. Export, settlement and what the plant is worth to you are engineering and commercial choices; choose the connection for those, then apply the rule that follows. The full reading of both 2026 orders, the commissioning trigger and our pre-advice checklist are in the 2026 ALMM and DCR commissioning guide.

Frequently asked

Is a private factory's behind-the-meter solar plant exempt from ALMM?

Yes, if it is genuinely behind the meter and used solely for the factory's own consumption. Para (e) of MNRE's 4 August 2026 clarification states that ALMM List-I (modules) and List-II (cells) do not apply to behind-the-meter solar plants used solely for captive consumption by a consumer or group of consumers, other than government entities or public-sector enterprises.

Does a zero-export or net-metered plant count as behind the meter?

A net-metered plant does not. The same clarification defines net-metering to cover gross metering, net billing, net feed-in, virtual and group net metering "but excluding Behind-The-Meter connections", so any plant whose output is settled through the DISCOM is a net-metering project and is reached by List-I, and by List-II if it commissions after 31 December 2026. Whether a particular zero-export arrangement qualifies depends on how it is connected and metered; confirm it against the DISCOM's connection approval, not the label on the proposal.

Do government or PSU behind-the-meter plants need ALMM modules?

Yes. Para (e) excludes government entities and public-sector enterprises from the behind-the-meter exemption. Their behind-the-meter plants must use ALMM List-I modules, and List-II cells as well if they are commissioned after 31 December 2026.

Related services

Which rules likely apply to your project?

A preliminary reading from MNRE's O.M.s of 18 July and 4 August 2026. It runs in your browser and stores nothing. It is not an exemption certificate — exact module model, cell eligibility, scheme or tender terms, utility acceptance and commissioning evidence all have to be verified before any project advice.

Who is the consumer?
How will the plant connect?
Realistic commissioning date?
Is a subsidy, government scheme or tender involved?

Request an ALMM/DCR project review

Three details to start. Everything else is optional — leave what you do not know.

Either a phone number or an email is enough.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it