Does ALMM apply to a behind-the-meter captive solar plant?
For a private consumer, no. MNRE's clarification of 4 August 2026 (O.M. No. 283/54/2026-GRID SOLAR), para (e), says ALMM List-I and List-II shall not apply to behind-the-meter solar power plants solely used for captive consumption by a consumer or group of consumers, other than Government entities or Public Sector Enterprises.
A private factory running a plant behind its own meter, for its own load, is outside both lists: modules and cells.
Why the connection decides it, not the owner
The exemption rests on two words in the order: behind-the-meter and solely. The same O.M. defines "net-metering" to cover Gross Metering, Net Billing, Net Feed In, Virtual Net Metering, Group Net Metering, etc. but excluding Behind-The-Meter connections.
So the test is how the plant is wired and settled:
| How the plant connects | ALMM List-I (modules) | ALMM List-II (cells) |
|---|---|---|
| Private consumer, behind the meter, solely captive | Does not apply | Does not apply |
| Net-metered, net-billed, gross-metered or open access | Applies | Exempt if commissioned by 31 December 2026; applies after |
| Government entity or PSU, behind the meter | Applies | Exempt if commissioned by 31 December 2026; applies after |
A plant described as captive whose output is in fact exported or settled through the DISCOM is a net-metering project for this purpose, whatever the proposal calls it. That is the failure we see: a module choice made on the "captive" label, then a connection application that says otherwise.
What this does not settle
- DCR. Para (f) of the same O.M. says the ALMM orders have no effect on Domestic Content Requirement. If a subsidy or scheme imposes DCR, it still applies to a behind-the-meter plant. See DCR vs non-DCR for a commercial plant.
- The DISCOM's own process. Whether your utility asks for anything beyond MNRE's position is a separate check.
- Later orders. Check the MNRE ALMM page for anything issued after 4 August 2026 before you buy modules.
We will not suggest changing a connection to escape a module rule. Export, settlement and what the plant is worth to you are engineering and commercial choices; choose the connection for those, then apply the rule that follows. The full reading of both 2026 orders, the commissioning trigger and our pre-advice checklist are in the 2026 ALMM and DCR commissioning guide.
Frequently asked
Is a private factory's behind-the-meter solar plant exempt from ALMM?
Yes, if it is genuinely behind the meter and used solely for the factory's own consumption. Para (e) of MNRE's 4 August 2026 clarification states that ALMM List-I (modules) and List-II (cells) do not apply to behind-the-meter solar plants used solely for captive consumption by a consumer or group of consumers, other than government entities or public-sector enterprises.
Does a zero-export or net-metered plant count as behind the meter?
A net-metered plant does not. The same clarification defines net-metering to cover gross metering, net billing, net feed-in, virtual and group net metering "but excluding Behind-The-Meter connections", so any plant whose output is settled through the DISCOM is a net-metering project and is reached by List-I, and by List-II if it commissions after 31 December 2026. Whether a particular zero-export arrangement qualifies depends on how it is connected and metered; confirm it against the DISCOM's connection approval, not the label on the proposal.
Do government or PSU behind-the-meter plants need ALMM modules?
Yes. Para (e) excludes government entities and public-sector enterprises from the behind-the-meter exemption. Their behind-the-meter plants must use ALMM List-I modules, and List-II cells as well if they are commissioned after 31 December 2026.
Related services
Guides that reference this page
- Solar EPC RFQ Template for an Industrial Plant Commissioning in 2027 (Copy and Issue)
- DCR vs non-DCR solar panels: which does a commercial plant need?
- DCR vs non-DCR solar panels, and ALMM List-II: the 2026 commissioning guide
- A Plant Down 8% Looks Exactly Like a Plant Working Fine.
- Three Vendors, One Roof, Three Different Generation Figures.
- Solar Module Cleaning for a 1 MW Plant: Water, Frequency, Robots and the Soiling Loss Maths
Related on this site
- termShadow-Free Area
- termGross Metering
- termOpen Access (Solar)
- serviceSolar plant O&M and performance
- serviceSolar battery storage and hybrid systems
- calculatorSolar Roof Load Calculator
- calculatorSolar Panel Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guideFactory licence and DISH approval
- guideCTE/CTO pollution consent
More on Solar & Renewables · all insights