Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCDesign & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & CommissioningIndustrial Audits
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 29 calculators Solar Savings Calculator Fire Water Tank Calculator Fire Pump Room Calculator AC Tonnage Calculator DG Set Sizing Calculator MEPF Cost Estimator
Projects Work With Us Get a Free Quote
Solar

Net Metering

Net metering is the grid-interconnection settlement in which a bidirectional meter nets your solar exports against your imports — an exported unit offsets a consumed unit — under capacity caps and settlement rules set by your state's regulations.

Why it matters on an MEPF project

Net metering is what makes daytime-heavy rooftop solar bankable for consumers whose usage and generation do not perfectly overlap: surplus flows out, credits flow back. Because an exported unit is effectively valued at your retail tariff, the regime materially shapes plant sizing — often more than roof area does.

It is also entirely a creature of state regulation: eligibility caps (absolute kW and/or a percentage of sanctioned load), settlement periodicity, treatment of unadjusted credits, and the alternative regimes (gross metering, net billing) all vary and get revised. The application itself — feasibility, agreement, meter installation, synchronisation — is a DISCOM process with its own queue, which is why we run it as part of EPC scope rather than leaving it to the customer.

How it's specified in practice

Regime mechanics — Net Metering
ParameterTypical / working positionGoverning reference
MeteringBidirectional (net) meter at the interconnectionDISCOM metering spec
Eligibility capskW limits and/or % of sanctioned load — state-specificstate net-metering regulations
SettlementBilling-cycle netting; year-end treatment per regulationstate regulations
AlternativesGross metering / net billing where mandated or chosenstate regulations

Common mistakes

  • Sizing the plant past the state cap, then redesigning mid-application.
  • Assuming credits roll over forever — year-end rules differ.
  • Ignoring sanctioned-load linkage before applying.
  • Treating DISCOM timelines as EPC timelines in the project plan.

Related on this site

Frequently asked

Net metering vs gross metering — the difference?

Net metering offsets exports against imports at retail value; gross metering sells all generation at a feed-in tariff while you buy all consumption at retail. Which applies (and when you may choose) is your state regulation's call.

How much solar can I install under net metering?

Up to your state's cap — commonly expressed against sanctioned load and/or an absolute limit. Our solar-vs-sanctioned-load calculator shows your headroom before the application.

Standards referenced: state net-metering regulations · DISCOM procedures

Ready to start your project?

Get a free consultation and quote. We design, take all approvals, and execute — you stay stress-free.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Chat / Get Quote