Solar, DG and Battery Integration for a Factory: Outages, Protection and Control
Short answer: a grid-tied solar plant is not backup power. It shuts down when grid supply fails, and running it alongside a DG set safely needs a control layer designed for that purpose. To use solar during outages — or to add batteries — design the architecture deliberately: separate the critical loads, decide which source serves them, add the controller that keeps solar within the DG's limits or the battery system that forms its own supply, and prove it all in testing.
Grid-tied outage limitations
Every distributed generator connected to the grid must protect the grid. The CEA technical standards for connectivity below 33 kV require it to trip on voltage and frequency outside set limits, to cease energising an unintended island within two seconds, and to reconnect only after supply has been stable for at least sixty seconds (regulation 11(6)). State regulations repeat the point: Punjab's rooftop solar regulations require anti-islanding protection, and where batteries are fitted, an arrangement that stops battery power flowing into the grid when it fails, plus a manual isolation switch (regulations 6.4 and 6.6). Before changing anything, record what happens on your site today.
| Check | What to find out | Why it matters |
|---|---|---|
| Solar behaviour in an outage | Does the plant trip, and does it restart when the DG starts? | If it restarts onto the DG without control, the DG can be back-fed |
| Changeover | Manual, automatic mains failure or synchronising panel; interlocks between grid and DG | Decides where solar can connect and when |
| DG data | Rating, number of sets, the manufacturer's minimum-loading guidance, reverse-power protection | Solar must not push the DG below its minimum load or into reverse power |
| Inverter capability | Can the inverters be curtailed by an external command? | A DG controller works only through that capability |
| Critical loads | Which loads must run in an outage, their kW, and how long | Sizes everything that follows |
| Outage pattern | Frequency, duration and time of day | Daytime outages are where solar can help; night outages are battery or DG territory |
| Earthing | Neutral and earthing arrangement when the site runs without the grid | An islanded supply needs a defined neutral reference |
| Approvals | Which additions need the DISCOM's consent or the Electrical Inspector's approval | Changes to sources and protection are changes to the installation |
Critical-load architecture
Start with the loads, not the equipment. Rank them by what an interruption costs — scrap, restart time, lost batches, safety — and segregate the ones that justify backup onto their own panel or bus. That single step can show that the backup needed is smaller than the whole plant, and it decides the size of every source that follows. Keep the units straight: a battery's energy is in kWh and its power in kW, and backup duration is roughly the usable energy divided by the critical load in kW, after losses. The battery storage calculator works through those numbers.
| What the factory needs | Architecture | What it requires |
|---|---|---|
| Cut diesel use during daytime outages; DG already carries the critical load | DG controller that limits solar output while the DG runs | Inverter control, DG data, metering at the DG, settings for minimum load and reverse power |
| Ride through seconds-to-minutes interruptions on sensitive equipment | UPS on those loads | UPS sizing to the load; solar plays no part |
| Run critical loads on solar and battery through short outages, with no DG start | Battery system that forms an isolated supply for a segregated critical bus | Battery inverter able to form the supply, transfer switching, anti-islanding interlocks, battery-room safety |
| Reduce recorded demand or shift energy between tariff blocks | Battery cycling under a control strategy | Tariff analysis first — see battery storage and peak shaving |
| Long outages and large loads | DG as the main backup, solar through a controller, battery optional | DG capacity for the critical load; controller as above |
| Rare outages | Grid-tied solar only | Accept that solar is off during cuts |
Protection and control interfaces
Adding sources changes the fault current the installation can see and the direction power can flow. Protection settings worked out for a single grid infeed may no longer discriminate correctly once inverters, a DG and a battery can all contribute, so revisit the protection study when the architecture changes. On installations above 650 V, the CEA safety regulations require supplies that are not meant to run in parallel to be interlocked against inadvertent paralleling or back-feed (regulation 47). The control layer then has to decide, without an operator's judgement at 2 am: which source serves which bus, when solar may run alongside the DG and how far it is curtailed, when loads are shed, when a battery charges or discharges, and how the site re-synchronises when the grid returns. Write those decisions down as a sequence of operation before any equipment is ordered.
Specialist integration and testing
Integration fails at the interfaces between suppliers — the inverter maker, the DG panel builder, the battery supplier and the electrical contractor each test their own box. Assign one party to own the sequence of operation and the tests that prove it: a simulated grid failure with solar running, a DG start with solar curtailed and the DG held above its minimum load, a battery transfer onto the critical bus, and re-synchronisation on grid return, with the protection trips checked at each step. Battery rooms bring their own fire and ventilation requirements; see lithium-ion battery room fire safety.
Approvals follow the installation. Under regulation 45 of the CEA safety regulations, installations above the voltage the state notifies are inspected by the Electrical Inspector before supply starts, those at or below it are self-certified, and generating units above the capacity the state notifies are inspected before commissioning (regulation 34). Changes to the solar connection or a battery also need the DISCOM's terms. Our Solar EPC and electrical infrastructure teams design and execute these interfaces, and CEIG approval consultancy prepares the inspectorate file; send the SLD, outage log and critical-load list through the scope review form. More guides are in Insights, including solar with battery backup for a Punjab factory.
Sources and how to verify
- CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations, 2013 — Central Electricity Authority, notified 30 September 2013, amended 2019; regulation 11.
- CEA (Measures relating to Safety and Electric Supply) Regulations, 2023 — notified 8 June 2023; regulations 34, 45 and 47.
- PSERC (Grid Interactive Rooftop Solar Photo Voltaic Systems) Regulations, 2021, consolidated up to the third amendment — Punjab State Electricity Regulatory Commission; regulations 6.4 and 6.6, as a state example.
- MNRE solar schemes — scheme overview; interconnection terms come from the state regulator and DISCOM.
Confirm locally: your DISCOM's interconnection terms for solar and storage, the voltage and generating capacity your state has notified for inspection, and the DG manufacturer's minimum-loading guidance for your sets.
Frequently asked
What information do I need before integrating solar with a DG or battery at my factory?
The single-line diagram with the grid incomer, DG changeover and solar connection points; the DG sets' ratings and the manufacturer's minimum-loading guidance; the solar inverters' make, rating and control capability; a list of loads ranked by how much an interruption costs; the outage record (how often, how long, at what time of day); and the load you plan to add. Without the critical-load list, every later decision is a guess.
Which site conditions can change the scope or budget of a solar, DG and battery integration?
Whether critical loads already sit on their own panel or are mixed across the plant; the type of changeover (manual, automatic, or synchronising panels); the DG's size relative to the solar plant; space and ventilation for a battery room, and its fire-safety requirements; the earthing arrangement when the site runs islanded; supply voltage and whether additions need the Electrical Inspector's approval; and how often the DG runs today.
What should I send an engineer to design solar, DG and battery integration?
The single-line diagram, DG and inverter data sheets, twelve months of electricity bills, interval load data or a week of logging, the outage log, the critical-load list with the interruption each load can tolerate, and the roof layout if solar capacity will change. That lets an engineer propose an architecture, size the controller or battery to the loads that matter, and set out the protection and testing it needs.
Why does my solar plant switch off during a power cut?
Because it is required to. A grid-connected plant must stop energising the network when the grid fails, so that it does not feed a line that utility staff believe is dead; the CEA connectivity standards require it to cease within two seconds of an unintended island forming and to reconnect only after voltage and frequency have been stable for at least sixty seconds. Solar can keep running during a cut only behind a DG controller or a battery system designed to form its own isolated supply, with interlocks that keep it from feeding the grid.
Related services
Guides that reference this page
- Solar for Bottling Plants and Breweries: Sizing, Roof, Approvals and Payback (50 kW+)
- Solar for Paper and Packaging Plants: Sizing, Roof, Approvals and Payback (50 kW+)
- Solar for Dairy Plants: Sizing, Roof, Approvals and Payback (50 kW+)
- Solar DG Synchronisation in a Factory: Minimum DG Loading and What Goes Wrong
- Your solar plant switches off in a power cut. Here's what a battery changes in Punjab.
- Size Rooftop Solar Against Your Factory's Daytime Load, Not the Roof
Related on this site
- termDCR Modules
- termSolar Payback Period
- termOpen Access (Solar)
- serviceSolar net-metering and monitoring
- serviceSolar PV module selection
- calculatorMEP Maintenance Budget Calculator
- calculatorSolar Water Pump Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guideFactory licence and DISH approval
- guideCTE/CTO pollution consent
More on Solar & Renewables · all insights