Size Rooftop Solar Against Your Factory's Daytime Load, Not the Roof
Short answer: size the plant to the daytime load that can use its output, measured from interval data — not to the roof area or to annual consumption. A unit used on site saves the energy charge you would otherwise pay; a unit exported is worth whatever the state's settlement rule pays, and a unit curtailed is worth nothing. The overlap between the load curve and the generation curve, across weekdays, weekly offs and seasons, sets the right size.
Interval load and generation overlap
Generation follows the sun: zero at night, rising through the morning, peaking around midday and falling in the afternoon. The factory's load follows the shift. Overlay the two on a typical working day, a weekly off and a shutdown day, for a summer and a winter month. Where load sits above generation, every unit is used on site; where generation sits above load, the surplus is exported or curtailed. Monthly bills average this away, so start from interval readings.
| Item | What to collect | Why it matters |
|---|---|---|
| Interval data | 15- or 30-minute consumption for representative weeks, summer and winter | Shows the midday base load the plant can feed |
| Shift pattern | Start and end times, number of shifts, lunch breaks | Decides how much of the generation window is covered |
| Weekly offs and holidays | Days the plant stops or runs reduced | On those days most generation becomes surplus |
| Shutdowns | Annual maintenance and seasonal stoppages | Long stoppages during sunny months change the annual picture |
| Large intermittent loads | Compressors, furnaces, chillers, process batches | Their timing moves the midday floor up or down |
| Cooling load | Air-conditioning and process cooling by hour | Cooling peaks in sunny hours, so it overlaps generation well |
| DG operation | Hours the DG runs and its minimum loading | A grid-tied plant stops in an outage, and with a DG it must be held within the DG's limits |
| Tariff and settlement | Time-of-day blocks, export arrangement, settlement period | Decides what a surplus unit is worth |
| Growth | Machines or shifts to be added, and when | Supports a phased plant rather than an oversized first phase |
On air-conditioned floors, cooling can be the daytime load that overlaps generation most closely, because both peak on hot, sunny afternoons. That coincidence is valuable, but it is also an argument for cutting cooling waste first: fixing duct leakage, air balance or solar gain through glazing can cost less than the panels needed to power the waste, and shrinks the plant you then need — see duct leakage and the performance gap and glazing and cooling load.
Weekdays, shutdowns and seasonality
A size that matches a Tuesday in May can be far too large for a Sunday in March. Three calendars matter:
- The week. A six-day factory has one day in seven when the midday load collapses. Unless the surplus earns something under the settlement rule, the plant should be sized so that weekday use carries the economics.
- The shutdown calendar. Annual maintenance, festival breaks and seasonal stoppages each remove load while generation continues.
- The climate. Generation varies through the year. Our calculators plan North India at an annual average of 120 kWh per kW per month, with December and January below it because of fog — a planning assumption, not site data. Cooling load is highest in the summer months, when generation is also strong, and lowest in winter.
Exports and curtailment
What happens to surplus depends on the arrangement the state regulator allows and you apply under. Under Punjab's rooftop solar regulations, for example, net-metered surplus is carried forward within a settlement period and any credits left at its end are paid at 75% of the Commission's feed-in tariff; under net billing, exports are valued at the feed-in tariff; behind the meter, export is not allowed and any injection is neither paid for nor settled. Other states set their own rules, so check your regulator's current regulation before treating a surplus unit as worth anything. Where export is not allowed or not worth much, the inverters have to curtail, and the plant's nominal size overstates what it delivers.
Outages are a separate limit. A grid-tied plant must stop feeding when the grid fails — the CEA connectivity standards require distributed generation to cease energising an unintended island within two seconds — so it produces nothing during a cut unless a DG controller or battery system is designed in. That integration is covered in solar, DG and battery integration.
Phased capacity choices
A load-matched first phase with the next phase prepared can be a better decision than one large plant. Plan the second phase into the first: structure and walkways for the full array, inverter space, cable routes and breaker space, and the sanctioned-load position that the larger plant will need.
| Factory situation | Size the first phase to | Why |
|---|---|---|
| Single shift, six days, steady load | The weekday midday base load, up to the cap your state's regulation sets against sanctioned load | Nearly all output is used on site on working days |
| Two or three shifts | The daytime base load only | Night load stays on the grid; storage is a separate decision |
| Long weekly or seasonal shutdowns | Slightly below the weekday base load | Surplus on off days earns little or nothing |
| Load growing, sanction revision pending | Today's daytime load, with phase two prepared | Capacity follows the sanction and the new machines |
| Export not allowed (behind the meter) | The lowest daytime load, with export-limiting control | Anything above it is curtailed |
| DG runs most days during outages | As above, plus a DG controller | Solar must be held within the DG's limits while it runs |
Run the numbers for your own site in the solar calculator. Design and delivery are under Solar EPC; for a load-matched sizing, send twelve months of bills, interval data and the roof layout through the scope review form. More guides are in Insights, including how a Punjab factory bill is read for solar sizing.
Sources and how to verify
- PSERC (Grid Interactive Rooftop Solar Photo Voltaic Systems) Regulations, 2021, consolidated up to the third amendment — Punjab State Electricity Regulatory Commission, amendment of 7 April 2026; regulations 4.2, 12, 13 and 14C, used here as a worked example of state settlement rules.
- CEA technical standards for connectivity of distributed generation resources, 2013 (amended 2019) — Central Electricity Authority; regulation 11 on protection and unintended islanding.
- MNRE solar schemes — Ministry of New and Renewable Energy; scheme overview. Metering, tariffs and export settlement are set by each state regulator.
Confirm locally: your state regulator's current rooftop regulation and settlement rule, the feed-in tariff for the year, your DISCOM's transformer capacity, and the roof's structural capacity from a structural engineer.
Frequently asked
What load data do I need before sizing rooftop solar against my factory's daytime use?
Interval consumption — 15- or 30-minute readings — for at least a few representative weeks, ideally across a summer and a winter month, from the meter's load survey or a logger on the main incomer. Add twelve months of bills, the shift pattern, weekly offs, holidays and planned shutdowns, the DG running hours, and any load you expect to add. Monthly bills alone cannot show what happens at midday on a Sunday, which is where surplus generation appears.
Which site conditions can change the solar size or budget for a factory roof?
Usable shadow-free roof area after skylights, vents and walkways; the roof structure, which a structural engineer must assess; the sanctioned load and the capacity left on the distribution transformer; the export arrangement your state and DISCOM allow; how often the DG runs, because the plant must stay within the DG's limits; and whether the roof will be extended or re-sheeted soon, which affects phasing.
What should I send an engineer for a load-matched solar sizing?
Twelve months of electricity bills, interval load data (or permission to log for a week), the roof layout with photographs, the single-line diagram including the DG changeover, the shift and shutdown calendar, and any expansion plan. With these an engineer can build the load and generation overlap, show how much would be exported or curtailed at different sizes, and recommend a first phase.
Should I size solar to cover my whole annual consumption?
Only if the surplus is worth what you pay for grid power, which it rarely is. A plant sized to annual consumption generates more than the factory uses at midday, on weekly offs and in the spring months, and that surplus is either credited under the state's settlement rules, at whatever value they set, or curtailed if export is not allowed. Size to the energy the factory can use, then add capacity only where the settlement rule makes the surplus worth having.
Related services
Guides that reference this page
- Solar for Printing Presses: Sizing, Roof, Approvals and Payback (50 kW+)
- Solar for Shopping Malls: Sizing, Roof, Approvals and Payback (50 kW+)
- East-West vs South-Facing Layout on a Flat Roof: Capacity vs Yield Trade-Off
- Solar for Pharma Plants: Sizing, Roof, Approvals and Payback (50 kW+)
- Perovskite Cells Promise 30%+ Efficiency. Your Roof Doesn't Have Ten Years to Wait and See.
- What an 80 kW Solar Plant Costs and Needs: Roof, Connection, Approvals
Related on this site
- termString Inverter vs Central Inverter
- termALMM
- termOpen Access (Solar)
- serviceSolar battery storage and hybrid systems
- serviceSolar net-metering and monitoring
- calculatorMEP Maintenance Budget Calculator
- calculatorSolar Sanctioned Load Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guideEnvironmental clearance (EIA 2006)
- guideNBC 2016 fire and life safety for factories
More on Solar & Renewables · all insights