Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

Solar EPC Company for Factories in Kerala: KSEB Rules, Approvals and Cost

22 October 2026 · 6 min read · by

Title card reading Solar EPC for Factories in Kerala, with a factory roof covered in solar modules drawn in outline.
Title card. Not a photograph of a Secured Engineers site.

A factory in Kerala can put 50 kW or more of solar on its roof under KSEB's rules. The 2025 KSERC regulations let industrial consumers net-meter 1 to 500 kW, but new plants above 25 kW must include storage. Larger plants use net billing, gross metering or open access. Turnkey cost sits in ₹24,000–32,000 per kW excluding GST.

Which metering route can a Kerala factory use?

The governing text is the Kerala State Electricity Regulatory Commission (Renewable Energy and Related Matters) Regulations, 2025, notified on 5 November 2025 under notification no. 3228/Con.Engg/2023/KSERC. They replace the older net metering regulations of 2020 and come into force on gazette publication, so ask KSEB for the gazette date. Early-2025 press coverage of the draft described much lower capacity caps; those were proposals, and the notified limits for industry are higher. Check the notified text, not the headlines.

RouteCapacity for an industrial consumerHow export is treatedCondition to note
Net metering1 to 500 kW, within connected load or contract demandImport and export netted by time zone; surplus for new plants above 25 kW is paid at the Commission's feed-in rate25 to 100 kW needs a hybrid inverter with storage of at least 10% of generation potential; 100 to 500 kW needs at least 20%
Net billingLower of connected load or contract demand, and 1,000 kW; up to 3,000 kW with at least 30% storageImport and export valued at different tariffs and netted on the billMinimum plant size 1 kW
Gross metering1 to 3,000 kW, can be at a separate siteAll generation sold to the licensee at the feed-in tariffNetwork upgrade cost can fall on the owner where the plant is larger than the load or sits elsewhere
Behind the meterUp to connected load or contract demandNo export; a reverse power relay is requiredPrior intimation to KSEB in the prescribed form
Captive or open accessOpen access rules apply where the power to be wheeled exceeds 100 kWWheeling, loss and other charges applyPlants of 1 MW and above need a special energy meter reporting every 15 minutes

Group net metering lets a net-metering-eligible consumer use surplus at its other premises in the same licensee's area. Virtual net metering in the notified text is aimed at residential, low-income, government, agricultural and very small consumers, so a typical factory will not use it. Existing net-metered plants stay on the old terms until they change capacity or reach the end of their useful life. Our note on open access solar covers the wheeling route in detail.

Two definitions matter when you size the plant. KSERC counts the plant's AC capacity, meaning the inverter rating, as its kW, and where an inverter is rated in kVA it allows 0.9 times the kVA as kW. The storage requirement is worked out on a generation potential reckoned at a 19% capacity utilisation factor. A 400 kW inverter plant on a 450 kVA contract demand therefore needs its storage sized on that formula, and the connected load or contract demand remains the ceiling whichever route you pick.

What approvals and inspections apply?

The process is online through KSEB's portal. The maximum timelines in the notification run as follows:

  1. Apply for technical feasibility with an application fee; KSEB must answer within 15 days, and silence on a complete file is deemed feasibility.
  2. Register within 45 days of the feasibility certificate. The notification sets a registration fee per kW, and the registration is valid for six months, extendable by up to six more.
  3. Build the plant. A licensed electrical contractor submits the test-cum-completion report.
  4. Obtain the Electrical Inspector's sanction for energising, where it applies under the CEA connectivity and safety regulations.
  5. KSEB tests within seven working days of the report, signs a connectivity agreement, and connects within seven working days of signing; meter installation and commissioning are listed at 15 days from the report.

The notification also fixes technical rules: inverters must filter harmonics and isolate on grid failure, the plant must meet the Kerala State Electrical Inspectorate guidelines of 2023, and the cumulative distributed capacity on a distribution transformer is capped at 90% of its rating. Those limits make the transformer check the first real gate.

What does the cost band mean at 100 kW, 500 kW and 1 MW?

Our published band for turnkey commercial and industrial rooftop solar is ₹24,000–32,000 per kW excluding GST. It covers modules, inverters, structure, cabling, earthing, protection, installation and the DISCOM paperwork, and it is not a quotation. On our size pages the figures are about ₹28–32 lakh at 100 kW, about ₹1.30 crore at 500 kW and ₹2.40–2.60 crore at 1 MW, all before GST. See the 100 kW, 500 kW and 1 MW pages for what moves each number.

In Kerala three items sit outside the band and need their own line in a quote. First, the storage the net metering rules require for new plants above 25 kW; see our battery energy storage page. Second, structure and fixing choices for coastal air, where corrosion protection is typically specified more heavily. Third, any HT interface work. Generation also dips in the June to September monsoon, which the solar calculator takes into account through your location. For a factory comparing offers, the useful discipline is to ask each bidder to state the storage kWh, the inverter type and the metering route on the first page of the quotation, because two offers with the same headline per-kW figure can differ by exactly those three lines.

Where do Kerala's factory roofs sit?

KINFRA's site lists industrial parks across the state, including the electronic manufacturing cluster at Kakkanad, the hi-tech park at Kalamassery, industrial parks at Koratty, Ottapalam and Mattannur, and an integrated industrial and textile park at Palakkad. Large flat roofs in such parks are natural candidates for solar, but check each park's lease terms on roof use and any ground-rent clause before you design. ANERT, the state's renewable energy agency, publishes the state's solar policy and programme pages.

What should you confirm with KSEB before you sign?

  • Which regime your category falls under, and the date the 2025 regulations took effect for your application.
  • Hosting capacity at your distribution transformer, and the feasibility figure in kW.
  • The grid support charges and any storage rule that applies to your capacity.
  • Metering class: smart meters for 100 kW and above, and special energy meters for 1 MW and above.
  • Whether the Electrical Inspector's sanction is required for your voltage level.

How Secured Engineers helps

We are a pan-India EPC contractor. Design is done in-house, and Fire NOC, CEIG and DISCOM net-metering filings are prepared in-house, with MEPF and solar available under one contract. We work from offices in Noida (Delhi NCR) and Ludhiana, across 535+ projects in 18+ states, with 89.77% repeat clients. Kerala is not among our published project locations, so we treat a Kerala job as a mobilisation from those offices and agree the site-team arrangement in writing before the order.

To test your own numbers, open the solar EPC service page and the calculator, then message us on WhatsApp, call +91 70099 85817, or request a free proposal with your roof size, connected load and tariff category.

Frequently asked

What is the largest rooftop solar plant a Kerala factory can connect?

It depends on the route. Under the 2025 KSERC regulations an industrial consumer can net-meter 1 to 500 kW, never above its connected load or contract demand. Net billing allows up to the lower of that load or 1,000 kW, and up to 3,000 kW with at least 30% storage. Gross metering goes to 3,000 kW. Confirm the feasibility figure KSEB grants for your transformer.

Does a Kerala factory need batteries for net metering?

For new industrial net-metered plants above 25 kW, the regulations require hybrid inverters with minimum storage: 10% of the plant's generation potential for 25 to 100 kW and 20% for 100 to 500 kW. Behind-the-meter plants that never export avoid that condition but need a reverse power relay and prior intimation to KSEB. Ask for the storage cost inside every quotation.

Who inspects and energises a factory solar plant in Kerala?

A licensed electrical contractor submits the test and completion report, the Electrical Inspector's energisation sanction is obtained where applicable, and KSEB then tests the system, signs the connectivity agreement and connects it. The regulations list maximum utility timelines of days, not months, but your own construction period sits on top of them.

How much does a 100 kW or 1 MW plant cost?

Turnkey commercial and industrial solar sits in a band of ₹24,000 to 32,000 per kW excluding GST. On our size pages that is about ₹28 to 32 lakh at 100 kW and ₹2.40 to 2.60 crore at 1 MW. Storage required by Kerala's net metering rules, HT work and unusual roofs are priced on top, so ask for scope line by line.

Does Secured Engineers have projects in Kerala?

No Kerala project is listed on this website. We work from offices in Noida and Ludhiana, file approvals in-house and mobilise to site, so ask us for references from comparable plants in similar roof types and for a clear scope split between our team and any local partner. Treat any contractor's claims the same way.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it