Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCDesign & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG ApprovalTesting & CommissioningIndustrial Audits
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 29 calculators Solar Savings Calculator Fire Water Tank Calculator Fire Pump Room Calculator AC Tonnage Calculator DG Set Sizing Calculator MEPF Cost Estimator
Projects Work With Us Get a Free Quote
100 kW Solar Plant

100 kW solar plant cost: ₹40–50 lakh, engineered honestly

A 100 kW rooftop system in India runs ₹40–50 lakh turnkey (₹40,000–50,000/kW) as of 2026 — best suited to facilities with ₹1–1.5 lakh/month electricity bills. Here's what that buys, what it generates, and the engineering that changes at this size.

15+ years · 535+ projects · Approvals in-house · ISO 9001:2015

At a glance

100 kW plant — the working numbers

Indicative turnkey cost₹40–50 lakh
Per-kW benchmark₹40,000–50,000
Roof required~10,000 sq.ft shadow-free
Generation (monthly avg.)~12,000 units
Generation (annual)~1.44 lakh units
Bill offset potential~₹1.0–1.1 lakh/month at ₹9/unit
Indicative payback3.5–4.5 years

Indicative North-India figures at ~120 units/kW/month — seasonal variation (including the winter fog dip) is real and belongs in any honest model.

Where the money goes

Cost split of a turnkey 100 kW system

Solar modules (ALMM Tier-1)50–58%
Inverters & monitoring9–12%
Mounting structure8–11%
Cabling, protection & BOS10–13%
Installation, T&C7–10%
Approvals, metering & misc.2–4%

A quote materially below the band usually removes scope — structure gauge, protection, or approval liability — rather than adding efficiency. Compare BOQs line by line, or send us one to counter-check.

What changes at 100 kW

The engineering story at this size

The 100 kW class is the C&I entry point: small factories, cold stores, schools, hospitals and mid-size commercial buildings. Approvals are the standard rooftop net-metering flow, installation is 3–5 weeks on a ready roof, and the engineering risk concentrates in just two places — roof structure and metering paperwork.

Grid interconnection

Usually LT-side (415 V) or 11 kV depending on your connection — the simplest interconnection case, with net metering under most DISCOMs' standard rooftop process.

Inverter architecture

Typically 2–4 string inverters (25–50 kW class) — no central inverter economics at this size, and string-level monitoring makes fault isolation trivial.

Approvals

DISCOM net-metering/captive registration and CEIG approval filed in-house, in parallel with procurement — approvals are our trade, not a subcontracted liaison job.

⚠ Sanctioned-load cap

Most DISCOMs cap net-metered capacity at or near your sanctioned load. A 100 kW plant on an 80 kW sanction stalls at the application stage — check headroom first with our sanctioned-load tool.

⚠ Roof reality

10,000 sq.ft on paper is rarely 10,000 usable — skylights, vents and parapet shadows typically shave 10–20% off. Shadow analysis before design, not after.

⚠ Single-phase of paperwork

At this size the DISCOM file is standard — but one mismatched load detail still restarts the clock. It's why we file approvals in-house.

Straight answers

100 kW solar plant — questions we actually get

What does a 100 kW solar plant cost in India?

Indicatively ₹40–50 lakh turnkey for a rooftop C&I system — module choice, structure type (RCC vs metal shed), cable runs and metering scope set where you land in that band. Treat any single-number quote given without a site survey as marketing, not engineering.

How much does 100 kW generate and save?

Around 12,000 units a month in North India (≈120 units/kW/month, with seasonal swing — winters dip, summers peak). At a ₹9/unit blended tariff that's roughly ₹1 lakh+/month offset if your daytime consumption absorbs it.

How much roof does 100 kW need?

Plan ~10,000 sq.ft of shadow-free area (~100 sq.ft/kW). East-west sheds, skylights and rooftop utilities reduce usable area — a shadow study converts the brochure number into your real one.

How long does a 100 kW installation take?

Typically 3–5 weeks of site work on a structurally ready roof, plus DISCOM/net-metering timelines that vary by state — we run approvals in parallel with procurement so paperwork never becomes the critical path.

Other sizes: 100 kW · 500 kW · 1 MW  |  Full service: Commercial & Industrial Solar EPC

Budgeting a 100 kW plant?

Send your electricity bill and roof details — our estimation team returns an engineered budget with the cost split above filled in for your site, free.