Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

Lightning and Surge Protection for a Rooftop Solar Plant: LA, SPDs and Earthing

22 October 2026 · 6 min read · by

Title card reading 'Lightning and Surge Protection for a Rooftop Solar Plant: LA, SPDs and Earthing' over a line drawing of an array with air terminals and earth pits.
Title card. Not a photograph of a Secured Engineers site.

A rooftop solar plant needs two kinds of protection: air terminals and an earthing system that take a direct strike away from the array, and surge protective devices on the DC and AC sides that clip the voltage surge that still gets through. Both are designed from an IEC 62305 risk assessment, and both must tie into the factory's existing earthing.

Why does a solar array change the lightning risk of a roof?

A solar plant adds metal, height and long cable loops to a roof. Module frames and structures are conductive. String cables run for tens of metres between modules and inverter, forming loops that pick up induced voltage when lightning strikes nearby, even without a direct hit. Inverters sit at the end of those loops, and they contain the most expensive electronics on the site. The building's own lightning protection, if it exists, was designed without any of this.

So there are two separate hazards to deal with. A direct strike can damage modules, structure and the roof, and may start a fire. A nearby strike induces a surge in the cabling that damages inverters, monitoring and the AC side of the factory. The first is handled by air termination and earthing, the second by surge protection. Mixing them up is the commonest design error: arrestors on the roof do little for the inverter's DC input.

How is the protection level decided?

The IEC 62305 series is the reference. Part 2 sets out a risk assessment: the structure's size and use, how often lightning is expected to strike the area, the type of services entering the building, and the consequences of a loss. The result tells you whether a lightning protection system is needed and to which class, from I to IV. Part 3 covers physical damage to the structure and Part 4 covers electrical and electronic systems inside it. Indian practice follows IS/IEC 62305, and BIS lists at least Part 4 as an Indian Standard; confirm which parts and editions your tender calls up.

MNRE's draft Quality Control Manual for grid-connected rooftop solar, circulated for comments in February 2023, asks for the whole array area to be protected by a sufficient number of lightning arrestors, designed to NFC 17-102:2011 or IEC 62305. It says the arrestor must not be installed on the mounting structure, and it sizes the down-conductor for a class III system as at least 6 mm² copper, 16 mm² aluminium or a 25×3 mm GI strip, run in a separate pipe. The manual is a draft and we could not confirm a final version, so the specification in your contract governs. A plant at a chemical or fuel-handling site, or one with a high-value process below it, will usually justify a higher class than a warehouse roof.

Where do arrestors, SPDs and earthing go?

LocationDevice or workWhat it doesDefect we look for
Roof, around and above the arrayAir terminals or masts placed from the risk assessmentIntercepts a direct strike before it reaches modulesMast fixed to the mounting structure, or a roof area left outside the protected zone
Down-conductorsConductor from terminal to earth electrode, in its own pipeCarries strike current to groundUndersized or corroded joints, or a run that bends sharply
String cablesPositive and negative routed together, in tray or conduitKeeps the loop area small so induced voltage is lowerStrings laid far apart, with large loops between rows
DC input of the inverterDC surge protective deviceLimits surge voltage on the DC sideRating below the array's cold-weather open-circuit voltage, or no backup protection
AC output and main panelAC surge protective deviceProtects inverter output and the factory sideNo coordination with the factory's existing SPDs
Structure and module framesBonding conductors to the earth systemEqualises potential across the arrayPainted or anodised contact surfaces, loose lugs

On SPD selection, the MNRE draft manual points to IEC 63227 and IEC 61643-11 for the devices, and to IEC 62561 for lightning-protection components such as connectors and earth electrodes. A device on the DC side is typically a Type 2 unit; a Type 1 or combined device is used where part of the direct-strike current can reach the circuit. State the choice in the design basis, not just "SPD provided".

How should the plant earth tie into the factory earth?

Here the sources do not say quite the same thing. The MNRE draft manual calls for separate earth pits for DC-side earthing, AC-side earthing and lightning-arrestor earthing, with earth resistance as low as possible and never above 5 ohms, and it refers to IS 3043 for earthing. As we read IEC 62305-3 and IS 3043, the preference for an installation with lightning protection is to bond the earthing systems together so that potentials rise and fall together during a strike. Confirm the wording of the edition your tender cites. Our note on lightning protection and earthing compliance explains why individually good pits can still produce dangerous potential differences when they are not bonded.

The usual reconciliation is separate electrodes that can each be tested, joined through a bonding conductor into one equipotential system, with the factory's main earth. Whichever way your contract words it, ask the designer to show the earthing layout, the bonding points, and the test value at each pit. Resistance moves with soil moisture, so a reading taken in the monsoon is not the number the plant will see in May. See also the glossary entry on earthing to IS 3043.

What goes wrong most often on site?

  • Arrestors that shade the array. A tall air terminal placed late casts shadow on modules. Place terminals in the shadow study, not after it.
  • DC and AC SPDs sized to a catalogue, not to the string. The DC device's continuous operating voltage must sit above the array's open-circuit voltage at the coldest module temperature, otherwise it ages early.
  • Pits tested once. The commissioning value is filed and never repeated, so degradation goes unnoticed.
  • Bonding by assumption. The structure, the inverter earth and the lightning system are each connected, but not to each other.
  • Unlabelled SPD status windows. Many SPDs show when they have worn out. If nobody looks, the plant runs unprotected for years.
  • Cables loose on the roof. Mechanical damage turns into an earth fault long before lightning arrives. This is also how DC fires start, as the MNRE draft manual notes.

What should you ask an EPC to show before award?

  • The IEC 62305 risk assessment, or a written reason for not doing one.
  • The air-termination layout drawn on the same roof plan as the array, with shadow impact noted.
  • The SPD schedule: location, type, voltage rating, and the standard each device is tested to.
  • The earthing layout, bonding points to the factory earth, and test values at commissioning.
  • A maintenance plan that includes SPD checks and earth re-testing once a year at the least favourable season.

The Electrical Inspector's inspection, where the state requires it for your installation, also looks at earthing. Our guide to Electrical Inspector approval covers when that applies.

How Secured Engineers helps

  • We design the plant in-house, including the earthing, lightning and surge-protection scheme, on the same drawings as the array layout.
  • Fire NOC, CEIG and DISCOM net-metering filings are prepared in-house.
  • MEPF and solar can sit under one contract, so the plant earth is tied to the factory earth by the same team.
  • We work from offices in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients.
  • For an existing plant, we offer rectification and design review of earthing and surge protection. We do not sell audits.

For earthing and lightning protection work, see our earthing and lightning protection service and our solar EPC service. To get a plant designed with protection built in, message us on WhatsApp, call +91 70099 85817 or ask for a free proposal.

Frequently asked

Does a rooftop solar plant need a lightning arrestor?

It depends on a risk assessment. IEC 62305 Part 2 weighs the roof's size and use, local lightning frequency and the cost of a loss. MNRE's draft manual asks for the whole array area to be covered by arrestors where protection is required. At a chemical or fuel site the answer is usually yes and the class is higher. Ask your EPC to show the assessment.

What is the difference between a lightning arrestor and a surge protective device?

An arrestor, or air terminal, intercepts a direct strike and sends it to earth through a down-conductor, protecting modules and structure. A surge protective device sits inside the electrical circuit, at the inverter's DC input and the AC output, and clips the voltage surge that reaches the cables from a nearby strike. A plant needs both; one does not replace the other.

How many earth pits does a rooftop solar plant need?

MNRE's draft manual asks for separate pits for DC-side, AC-side and lightning-arrestor earthing, with resistance never above 5 ohms. Good practice is to join the electrodes through a bonding conductor into one equipotential system with the factory earth. The number of pits then follows the layout and soil. Ask for the earthing drawing and the test value at each pit.

How often should earth resistance and SPDs be checked?

At least once a year, and ideally in the season when the soil is driest, because resistance rises as moisture falls. SPDs should be inspected at the same visit, since many show a status indicator when they have worn out. Record each reading against the commissioning value. A maintenance contract should name these checks rather than leave them to the general visit.

Can a lightning mast be fixed to the solar mounting structure?

MNRE's draft manual says the lightning arrestor shall not be installed on the mounting structure. A mast on the structure can carry strike current into the array frame. Masts are normally freestanding with their own down-conductor, and their position is checked in the shadow study so that they do not shade modules.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it