Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

String Inverter Brands Comparison: How to Compare Inverter Offers for a C&I Plant Without a Brand Ranking

22 October 2026 · 5 min read · by

Title card reading How to Compare Inverter Offers for a C&I Plant Without a Brand Ranking, with a wall-mounted string inverter drawn in outline.
Title card. Not a photograph of a Secured Engineers site.

To compare string inverter offers for a commercial or industrial plant, line every bidder up on the same ten points rather than on brand: AC rating and DC/AC ratio, MPPT inputs, temperature derating, grid-protection settings, test certificates, warranty terms, service response, monitoring access and the replacement price when the warranty ends. The brand follows from those answers. It cannot replace them.

What should you compare first?

A brand ranking looks helpful and fails in practice. The same unit performs differently on a hot metal shed in a dust belt and on an RCC roof in a cooler town, and the best unit on paper is useless if the nearest trained engineer is two days away. So we do not rank brands here. We give you the table to fill in, one column per bidder.

Comparison pointWhy it changes the outcomeWhat to ask each bidder for
AC rating and DC/AC ratioThe plant can never export more than the inverter's AC rating, and a high ratio clips the peakThe ratio used, and the clipping loss from a simulation on your roof
MPPT inputs and voltage windowSeparate inputs let strings with different tilt or shade run at their own optimumNumber of MPPTs, start-up and operating voltage range, maximum current per input against the module's short-circuit current
Efficiency evidencePeak efficiency flatters; weighted efficiency reflects real loadingThe test report and the standard it was measured to
Temperature deratingInverters reduce output when hot, and rooftop installations run hotThe derating curve and the ambient temperature at which full power is held
Grid-protection settingsThe DISCOM tests these before it connects youVoltage and frequency trip windows, anti-islanding, harmonic performance, as the local standard requires
CertificatesProof that type tests were done, and by whomCertificate names, dates and the laboratory, plus BIS registration where it applies
WarrantyReplacement versus repair, and who bears labour and freightYears, scope, extension price, and conditions that void it
ServiceDowntime costs generation every sunny dayNamed service centre, spare stock location, written response time
MonitoringYou cannot manage what you cannot seeString-level data, who owns the data, any subscription fee, alert routing
Replacement priceAn inverter typically needs replacing at least once in a plant's lifeA written price or formula for a like-for-like replacement

Which datasheet numbers are easy to misread?

Three numbers mislead buyers more than any others. The first is peak efficiency. A figure quoted at the best operating point tells you little about a morning, afternoon or cloudy hour; ask for weighted efficiency. The second is the DC/AC ratio: it is a design choice, not a quality mark, and the useful question is how much energy is clipped on your array over a year. The third is the temperature at which full output is held. Two inverters with the same nameplate can deliver different energy on the same hot afternoon, and the difference shows up in the generation report.

Also check the rating basis. Some offers state kW AC, some kVA, and some give the DC capacity of the array and leave the AC rating implicit. Convert everything to AC kW before you compare prices per kW.

What does the grid operator require of any inverter?

Requirements come from the state regulator and the DISCOM, so they vary, but they follow the Central Electricity Authority's technical standards for distributed generation. As one worked example, the Joint Electricity Regulatory Commission's rules for Goa and the Union Territories set out these inverter conditions in an annexure:

  • Efficiency and measurement to IEC or IS 61683, and environmental testing to IEC 60068-2 or the equivalent BIS standard.
  • Continuous supervision of grid conditions, with disconnection on grid failure, under-voltage or over-voltage.
  • An operating voltage window of 80% to 110% of nominal, with the plant isolating itself from the grid after a two-second clearing time beyond it.
  • Harmonics to IEEE 519, with individual harmonics under 3% and total distortion under 5%.
  • A grid frequency synchronisation device, with synchronisation causing no voltage fluctuation greater than 5% at the connection point.
  • Protection against islanding, and a separate backup wiring arrangement with isolation switches where a battery is connected.

Other states set their own details, and those numbers should be read from the regulation that applies to your site. The point for buyers is that every bidder should be able to show, on paper, how their unit meets the same list. If one cannot, that is information.

String or central: what changes in the offer?

String inverters suit roofs with several orientations, mixed shading or many small sections, because each input tracks its own strings and a single failure takes out only a fraction of the plant. Central inverters can make sense on a large, uniform array where one machine serves a block, but they bring longer DC runs, a dedicated enclosure and a larger single point of failure. Our page on string and central solar inverters sets out how we select between them for a given array. The size pages show how this plays out at different scales: our 100 kW page describes two to four string units, while the 1 MW page discusses where architectures change.

When you compare offers across the two types, compare installed cost including cabling, enclosures and civil work, and compare the loss from one failure. Ask each bidder: if one unit trips for a week, what share of generation do I lose, and how fast will you replace it?

How should you read the commercial terms?

Put the commercial terms side by side the way you put the technical ones. Warranty length is only the headline. What matters is the remedy (replacement or repair), who pays freight and site labour, how quickly a replacement arrives, whether warranty continues if the plant is monitored by a third-party platform, and how much the extension costs. Ask for a named service contact and a written response time. If the offer says "equivalent make" in the bill of quantities, insist on the datasheet and your approval before any substitution, because that single phrase can undo a careful comparison.

How Secured Engineers helps

We design the plant in-house, select inverters to the array and the DISCOM's connection standard, and commission them with the protection settings recorded for the inspection. Approvals including DISCOM net-metering are prepared in-house, and MEPF and solar can sit under one contract. We work from offices in Noida (Delhi NCR) and Ludhiana, across 535+ projects in 18+ states, with 89.77% repeat clients. We have no brand to push in this article and will review any set of offers on the same table.

If you already have two or three inverter offers, send them to us and we will put them on one comparison sheet and tell you what each is silent about. Start from the solar EPC service page, then reach us on WhatsApp, call +91 70099 85817, or ask for a free proposal.

Frequently asked

Which string inverter brand is best for a factory roof?

No honest ranking exists without your roof, tariff and service location, so we do not publish one. Choose on measurable points instead: weighted efficiency, temperature derating, MPPT layout, certificates, warranty terms, and how quickly a trained engineer can reach your site. A well-supported mid-range unit usually beats a better datasheet with no service engineer within a day's travel.

What DC to AC ratio should I ask for?

Ask the bidder to show the ratio and the clipping loss from a yield simulation of your own roof, because the right ratio depends on module tilt, orientation and local irradiance. A ratio above 1 is normal and lets the inverter run near its rating for more hours. A high figure with an unstated clipping loss is the point to challenge, not the ratio itself.

Is a central inverter cheaper than string inverters?

Not always. Central inverters can lower the cost per kW on a large, uniform array, but they need longer DC cable runs, a dedicated room or enclosure and a bigger single failure. String inverters suit roofs with several orientations or shade patterns and keep a failure to a fraction of the plant. Compare installed cost including cabling and civil work, not the inverter line alone.

What warranty terms matter most?

Look beyond the number of years. Ask whether the warranty covers a replacement unit or only repair, who pays transport and site labour, how long a replacement takes, whether it can be extended and at what price, and whether it stays valid if monitoring or settings are changed. Get these in the offer, not in a brochure.

Will the DISCOM check the inverter?

Yes. At the connection inspection the licensee typically checks that grid-protection settings such as voltage and frequency trip limits and anti-islanding match its standard, and that the inverter's test certificates are on file. Ask the contractor to hand you the recorded settings and certificates at commissioning so they survive a change of site staff.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Speak to a Lead Engineer