Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Compliance

The Approvals a New Factory Needs in India, in Order: Land to Energisation

22 October 2026 · 6 min read · by

Title card reading The Approvals a New Factory Needs in India, in Order: Land to Energisation.
Title card. Not a photograph of a Secured Engineers site.

A new factory in India clears its approvals in roughly this order: land use, environmental clearance where the project is listed, pollution board Consent to Establish, building plan, factory plan and fire scheme, then electrical inspection before energisation, and last the Consent to Operate, final fire NOC and factory licence. The order follows what each authority needs to see before it will sign.

What is the order, gate by gate?

The table lists the gates in the sequence most projects meet them. Several run in parallel, and state law changes the names and sometimes the order, so read it as a dependency map, not a calendar.

GateAuthorityMust be in hand beforeWhy it sits here
Land use and zoningTown planning or industrial development authorityYou buy or take allotmentIndustrial use must be permitted on the plot before anything is drawn
Environmental clearance, if the project is listedMoEFCC for Category A, the state authority (SEIAA) for Category BAny construction or land preparation, except securing the landThe EIA Notification 2006 puts it ahead of site work
Consent to EstablishState pollution control boardConstruction of the plantIt fixes the treatment scheme the plant is built to
Building plan sanctionLocal body or industrial authorityConstructionChecks the structure against bye-laws and the National Building Code
Factory plan approvalState factories inspectorateConstruction or extension of the factory buildingChecks the workplace: layout, exits, ventilation, welfare
Fire scheme approval or provisional NOCState fire serviceFire works are built (the stage varies by state)Hydrants, tanks and pump rooms sit under the ground
Electrical Inspector approvalState Electrical InspectorateSupply to the installation startsRegulation 45 of the CEA safety regulations 2023
Consent to OperateState pollution control boardProduction startsConfirms the treatment systems were built as consented
Final fire NOC and occupancyFire service; local bodyPeople occupy the buildingPhysical verification of what was built
Registration and factory licenceState factories inspectorateWork startsAsks for the earlier approval references

Why does land use and pollution category come first?

Because they decide whether the plan is possible at all. Check zoning, road width at the plot and whether the plot sits in a notified industrial estate. Then settle the pollution category. The Central Pollution Control Board revised its classification in January 2025 on a Pollution Index: above 80 is Red, 55 to 80 Orange, 25 to 55 Green and below 25 White, with a Blue category for essential environmental services. The Puducherry Gazette of 1 July 2025, which restates the method, treats White industries as exempt from Consent to Establish and Consent to Operate, with a self-declaration. Whether your state board has adopted the same treatment, and how it places your product, is for the board to confirm, so ask before you design the effluent and air systems.

Environmental clearance is separate and earlier. Paragraph 2 of the EIA Notification 2006 requires prior clearance for the projects in its Schedule before any construction or land preparation, other than securing the land. Check your product and capacity against the Schedule at feasibility stage. Our guide to environmental clearance explains when a factory is caught, and the pollution consent guide covers the board track.

How do the building plan, factory plan and fire scheme depend on each other?

They are three reviews of one building by three authorities, and the later approvals ask for the earlier ones by reference. Tamil Nadu's licence form asks for the reference number and date of the plan approval and of the effluent-disposal approval. Karnataka's plan-approval sheet asks for the pollution board's consent letter for factories with a hazardous process or storage, and for approval of the on-site emergency plan. If the earlier file is missing, the later one cannot be completed.

So the three sets of drawings must show the same building. Machine layout, exits, mezzanines, tank and pump-room positions and fire-tender access should be frozen together, then issued to the architect, the factory-plan consultant and the fire designer. A change in one drawing after submission usually means re-submitting the others. Our guide to factory licence and plan approval covers the factories-inspectorate track in the northern states, and the fire NOC guide covers the fire track.

What does the electrical inspector need before energisation?

Regulation 45 of the CEA (Measures relating to Safety and Electric Supply) Regulations, 2023 splits installations at a voltage each state notifies. At or below it, the owner inspects, tests and self-certifies, and sends the report to the Electrical Inspector on the Schedule II form; it counts as received if not acknowledged within three working days. Above it, the Electrical Inspector must inspect and test before supply starts, and the supplier needs the Inspector's written approval. An installation shut down for six months or more goes through the same step again, and additions or alterations need approval or self-certification before they are connected.

In practice a factory with an HT connection should assume inspector approval, and should ask the state which voltage it has notified. Start the single-line diagram, load schedule and the DISCOM application while the building is going up, not after, because testing and inspection come at the end of the programme with no float left. Our CEIG guide lists what the inspector checks.

What changed in 2025 and 2026?

Two things affect the last gates. The Occupational Safety, Health and Working Conditions Code, 2020 came into force on 21 November 2025 and repeals the Factories Act, 1948. It requires electronic registration and provides for a factory licence to be issued electronically within 45 days of application, or deemed issued. Existing state rules continue to the extent they do not conflict, and states are framing new rules, so plan approval and licence forms differ by state and are in transition. Karnataka's rules under the Code, for example, were still in draft in 2026, and for Tamil Nadu we found no final rules. Confirm the live forms before you file.

Second, the pollution classification above can move a product to a lighter category. Neither change removes the need to sequence the files; they change which forms you fill.

How does it vary by state?

The gates are the same in every state; the names, portals and periods are not. Our state guides read the primary sources: Tamil Nadu fire NOC, Karnataka fire NOC, Gujarat fire NOC, Madhya Pradesh fire NOC and Telangana fire NOC. As examples of how stated periods differ, Tamil Nadu's DISH charter gives three months for plan approval and 30 days for registration and licence, while Karnataka's department sheets give 60 working days for each. Treat any stated period as the department's target on a complete file.

How Secured Engineers helps

Secured Engineers designs fire, electrical, HVAC and plumbing systems in-house, so the layouts that go to the building authority, the factories inspectorate and the fire service come from one design. Fire NOC, CEIG and DISCOM net-metering filings are done in-house. MEPF and solar can be placed under one contract. We work from offices in Noida (Delhi NCR) and Ludhiana, and we mobilise from them for projects in other states. The company has delivered 535+ projects across 18+ states, with 89.77% repeat clients.

If you hold a draft approvals plan or a set of submitted drawings, we can check the sequence and the consistency between drawings before the next filing. Use the project estimator for a first view of scope, read the full factory approvals roadmap, then send the file by WhatsApp, call +91 70099 85817, or ask for a free proposal.

Frequently asked

What is the first approval a new factory needs in India?

Permission to use the land for industry. Check the zoning, the road width at the plot and whether it is in a notified industrial estate before you buy or take allotment. If the project is in the Schedule of the EIA Notification 2006, environmental clearance must follow before any construction or land preparation, other than securing the land.

Does every factory need environmental clearance?

No. The EIA Notification 2006 requires prior clearance for the projects and activities listed in its Schedule, with Category A decided by the Central Government and Category B by the state authority. Most small and medium units are not listed, but they still need the pollution board's consents unless the board treats the product as White category. Check your product and capacity against the Schedule at feasibility stage.

Can I build the shed before the Consent to Establish arrives?

Not safely. The Consent to Establish fixes the treatment scheme the plant is built to, and the Consent to Operate later checks that it was built. Construction ahead of consent risks stop-work action and rework. White-category units may be exempt from consent where the state board has adopted the 2025 CPCB classification, so confirm your category and your board's practice first.

When does the Electrical Inspector have to approve the installation?

Before supply starts, if the installation is above the voltage your state has notified. At or below that voltage the owner inspects, tests and self-certifies and files the report with the Electrical Inspector. Regulation 45 of the CEA safety regulations 2023 applies the same step again after a shutdown of six months or more and to additions or alterations.

What changed for the factory licence after the OSH Code?

The Occupational Safety, Health and Working Conditions Code, 2020 came into force on 21 November 2025 and repeals the Factories Act, 1948. It provides for electronic registration and a licence issued within 45 days or deemed issued. State rules under the Code are still being framed, so the plan approval and licence forms in use differ by state. Check the live forms with the department before filing.

Related services

Share the drawings, the SLD or the file you have prepared — an engineer checks it against what the authority actually asks for.

Need a statutory approval file reviewed before you submit?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Ask about approvals