What an 800 kW Solar Plant Costs and Needs: Roof, Connection, Approvals
An 800 kW rooftop plant indicatively costs about ₹1.92 to ₹2.08 crore excluding GST, at ₹24,000 to ₹26,000 per kW. It needs about 80,000 sq.ft of shadow-free roof, generates about 96,000 units a month in northern India, and usually connects at 11 kV. At this size you are above the 500 kW net-metering limit, so the metering route needs deciding before the design.
What does an 800 kW plant cost?
Secured Engineers publishes a C&I solar band of ₹24,000 to ₹32,000 per kW excluding GST on its solar EPC page, with larger plants at the lower end. We publish cost pages for 100 kW, 250 kW, 500 kW and 1 MW, but not for 800 kW, so the figure here is scaled between the 500 kW and 1 MW pages and is indicative only.
| Plant size | Per kW, excluding GST | Indicative turnkey cost | Shadow-free roof | Generation, north India |
|---|---|---|---|---|
| 500 kW | About ₹26,000 | About ₹1.30 crore | ~50,000 sq.ft | ~60,000 units/month |
| 800 kW (this article) | ₹24,000 to ₹26,000 | ₹1.92 to ₹2.08 crore | ~80,000 sq.ft | ~96,000 units/month |
| 1 MW | ₹24,000 to ₹26,000 | ₹2.40 to ₹2.60 crore | ~1,00,000 sq.ft | ~1.2 lakh units/month |
The scope behind the figure is a rooftop plant with modules, inverters, mounting structure, DC and AC cabling, earthing and lightning protection, protection and metering, installation, testing and commissioning, and DISCOM liaison. It excludes HT-side works such as a bay or transformer addition, roof strengthening, batteries, ground-mount land and statutory fees. At 800 kW the HT scope is the swing item, so check that every quotation states whether it is inside the price. Run your own bill through the solar calculator, then the solar payback calculator, which shows payback as scenarios by the share of output you use on site.
How much roof and how much generation?
Plan on about 100 sq.ft of shadow-free roof per kW, so about 80,000 sq.ft. That is rarely one roof. Expect several sheds with different heights, orientations and skylights, and let a shadow study replace the planning figure. Generation of about 120 units per kW per month is our planning figure for the northern belt, which gives about 96,000 units a month. It is higher in Rajasthan and Gujarat and lower in the east, and your location sets the real number.
If the roof is short, the usual alternatives are a carport, a ground-mount on spare industrial land, or a smaller roof plant plus open access for the balance. See our guide to open access solar for that route.
Why do buyers stop at 800 kW, and when is 1 MW better?
Buyers stop below 1 MW for reasons that have little to do with the price per kW, which our band puts at much the same for 800 kW and 1 MW. The usual reasons are:
- The roof. The usable area runs out near 80,000 sq.ft before it reaches 1,00,000.
- The sanction. The contract demand or sanctioned load does not support more, and the DISCOM caps the plant against it.
- The daytime load. Sunday and holiday output is exported, and the export rules in most states pay less than self-use.
- The transformer. Reverse flow at peak generation minus minimum load must fit the existing transformer.
1 MW is the better size when the roof, sanction and daytime load all support it. The extra 200 kW costs about ₹48 to 52 lakh on our band, and it spreads the fixed items, such as the HT bay, the protection scheme, the metering and the approvals, over more kilowatts. The reverse also holds: if the load is a single shift and the roof is tight, 800 kW may already produce more than you can use. Test both sizes in the payback calculator before you decide.
Which connection voltage and inverter architecture?
At this size the connection is usually on the HT side, at 11 kV, through your existing transformer bay or a dedicated one. Protection for reverse power, over and under voltage and frequency must coordinate with the existing scheme. Some sites with several LT supply points can stay on the LT side. The DISCOM and the electrical inspector decide. Our guides on 11 kV connection and transformer headroom cover the works.
Ask whether 800 kW means module capacity (DC) or inverter capacity (AC), because regulations and DISCOMs can apply their limits to either. On inverters, a string architecture of roughly ten to sixteen units in the 50 to 100 kW class is typical at this size, and a smaller number of larger central units is the alternative. We usually favour strings because a failed unit costs a small share of the output and is replaced from stock, whereas a failed central inverter can idle a large block. The guide to string versus central inverters sets out the trade-off.
What do the rules allow above 500 kW?
The Ministry of Power's annual report for 2021-22 records that an amendment to the Rights of Consumers Rules raised the net-metering limit from 10 kW to 500 kW. An 800 kW plant therefore exceeds it, and the state commission's regulation decides what happens next. The options are to size to the net-metering limit and add the balance later; to use net billing or gross metering where the state offers them; to run behind the meter with the plant sized to the daytime load, with export control if the DISCOM requires; or to use open access for part of the output. Banking and settlement of surplus energy differ by state, so check them before fixing the capacity.
The module rules matter too. MNRE's O.M. of 4 August 2026 says net-metering and open-access projects, defined to include gross metering and net billing, must use ALMM List-I modules, and are exempt from List-II (cells) only if commissioned by 31 December 2026. It says neither list applies to behind-the-meter plants used solely for captive consumption by a private consumer, other than government entities and public sector enterprises. Your contractor should state which applies to your metering.
What is the approval sequence, and what does a timeline depend on?
- Check the sanctioned load and transformer headroom, then freeze the capacity.
- Prepare the design and the single-line diagram.
- File the DISCOM application. Under the central rules as amended in February 2024, the feasibility study for systems above 10 kW is to be completed in 15 days, with deemed approval if it is not.
- Electrical inspector. Under the CEA safety regulations, 2023, an installation above the voltage notified by the state is inspected and approved by the Electrical Inspector before supply, and the capacity above which generating units, including solar, need inspection before commissioning is also fixed by the state. Check both for your state.
- Install and test, then arrange DISCOM inspection, metering and synchronisation. The same 2024 amendment gave the licensee 15 days to commission a rooftop system.
There is no honest single timeline at this size. The two statutory legs above are 15 days each on paper. What dominates is the module and inverter lead time, the HT works and the inspector's visit, plus the roof readiness. Ask any bidder for a dated programme that separates those items.
How Secured Engineers helps
Secured Engineers designs the plant in-house and files the DISCOM net-metering application, the electrical inspector filing and related approvals in-house. Solar can sit under one MEPF contract with your electrical, fire and HVAC work, so the HT side of an 800 kW plant is part of one scope. We work from offices in Noida (Delhi NCR) and Ludhiana, across 535+ projects in 18+ states, with 89.77% repeat clients.
Send us your last twelve electricity bills and the sanctioned load, and we will tell you what size the roof, the connection and the rules support before you buy. Message us on WhatsApp, call +91 70099 85817, or ask for a free proposal.
Frequently asked
How much does an 800 kW solar plant cost?
Indicatively about ₹1.92 to ₹2.08 crore excluding GST, which is ₹24,000 to ₹26,000 per kW. That scales from the lower end of our published ₹24,000 to ₹32,000 per kW band, between our 500 kW page (₹26,000 per kW) and our 1 MW page (₹24,000 to ₹26,000). It excludes HT-side works, roof strengthening, batteries and statutory fees, so a quotation is the only real number.
How much roof does 800 kW need?
Plan on roughly 100 sq.ft of shadow-free roof per kW, so about 80,000 sq.ft. In practice the gross area must be larger, because skylights, vents, parapet shadows and access paths remove a share of it, and the roof is usually several sheds at different heights. A shadow study turns the planning figure into your real area. If the roof falls short, consider a carport, a ground-mount or a smaller roof plant.
Can an 800 kW plant be net-metered?
Not in full under the central rules, which raised the net-metering limit from 10 kW to 500 kW in 2021. State regulations decide what happens above that, and they also tie the plant size to your sanctioned load or contract demand and to transformer headroom. Options at 800 kW include sizing to the net-metering limit, net billing or gross metering where the state offers them, behind-the-meter captive use, or open access.
How much will 800 kW generate?
About 96,000 units a month, or about 11.5 lakh units a year, at our planning figure of 120 units per kW per month for the northern belt. Western states usually yield more and eastern ones less, and output varies by season, tilt, shading and soiling. Use the solar calculator for your location. Do not use a single planning figure to guarantee a bill saving.
What connection voltage does an 800 kW plant use?
Most often 11 kV on the HT side, through an existing transformer bay or a dedicated one, because the plant is larger than a typical LT service can carry. Some sites with several LT points can connect at LT. The DISCOM and the electrical inspector decide on the basis of your contract demand, transformer headroom and the protection scheme, so confirm both before you freeze the design.
Does ALMM apply to an 800 kW rooftop plant?
It depends on how the plant is metered. MNRE's O.M. of 4 August 2026 says net-metering and open-access projects, which it defines to include gross metering and net billing, must use List-I modules, and are exempt from List-II for cells if commissioned by 31 December 2026. It says neither list applies to behind-the-meter plants used solely for captive consumption by a private consumer. Ask your contractor which category applies.
Related services
Related guides
- Perovskite Cells Promise 30%+ Efficiency. Your Roof Doesn't Have Ten Years to Wait and See.
- A Plant Down 8% Looks Exactly Like a Plant Working Fine.
- Three Vendors, One Roof, Three Different Generation Figures.
- You Were Going to Build a Parking Shed Anyway. Put Solar on It Before the EV Chargers Go In.
- PM Surya Ghar Is a Residential Scheme. Your Factory's Solar Incentives Work Differently.
- Solar, DG and Battery Integration for a Factory: Outages, Protection and Control
Related on this site
- termString Inverter vs Central Inverter
- termALMM
- termOpen Access (Solar)
- serviceBattery / Hybrid Storage (Solar EPC)
- serviceNet-Metering, Metering & Monitoring (Solar EPC)
- calculatorMEP Maintenance Budget Calculator
- calculatorSolar Payback Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guideCTE/CTO pollution consent
- guideEnvironmental clearance (EIA 2006)
More on Solar & Renewables · all insights