Solar EPC Contractor Scope of Work: What a Turnkey Rooftop Contract Covers and Excludes

13 November 2026 · 6 min read · by

Title card reading Solar EPC Contractor Scope of Work: What a Turnkey Rooftop Contract Covers and Excludes

A solar EPC contractor takes a rooftop or ground-mount plant from site survey to energisation under one contract: engineering the design, procuring the modules, inverters, structure and cabling, installing and testing the plant, filing the net-metering and electrical inspectorate approvals, and handing over the plant with its documents. The scope ends at the point where the plant exports to the grid and your meter records it; what sits outside that line is where most disputes start.

What EPC means in a solar contract

EPC stands for engineering, procurement and construction. In a solar context it means one firm is accountable for the design working, the equipment arriving and the plant performing, so you do not have to arbitrate between a designer, a supplier and an installer when generation falls short. The alternatives are a supply-and-install contract, where you or your consultant carry the design, and a power purchase agreement, where a developer owns the plant on your roof and sells you the units. Our comparison of CAPEX and OPEX solar on the same load covers that ownership choice; this article is about what the EPC route includes when you own the plant.

Scope by stage

A turnkey rooftop EPC contract moves through seven stages. The table lists what each one includes and the document you should hold before the related payment is released. The durations are the ones published on our solar EPC service page: design one to three weeks, statutory approvals three to ten weeks depending on the authority, procurement and execution four to ten weeks, and commissioning one to three weeks.

StageIncluded in a turnkey EPC scopeDocument you should receive
Site survey and feasibilityRoof measurement, shadow analysis, structural walk-through, load profile study from your electricity bills, sanctioned-load checkFeasibility report with usable area, proposed capacity, generation estimate and savings basis
Design and engineeringModule layout, string and inverter sizing, DC and AC cable sizing with voltage drop, earthing and lightning protection, structure design for the wind zone, single-line diagramDesign basis, drawings, calculations, bill of materials with makes and models
ApprovalsNet-metering or net-billing application to the DISCOM, feasibility and technical approval, electrical inspectorate approval where the capacity or voltage requires itCopies of every application, approval letter and inspection report
ProcurementModules from the approved list, inverters, mounting structure, cables, protection devices, monitoring hardware, bidirectional metering arrangements as the DISCOM requiresPurchase orders, test certificates, warranty cards in your name
InstallationStructure erection, module mounting, DC and AC wiring, inverter and panel installation, earthing, walkways and safety provisions as agreedInstallation checklists, daily progress record, material reconciliation
Testing and commissioningInsulation and continuity tests, string open-circuit and short-circuit readings, inverter commissioning, protection tests, DISCOM inspection and meter installation, synchronisationTest reports, commissioning certificate, DISCOM energisation record
HandoverAs-built drawings, O&M manual, warranty register, monitoring portal access, training for your maintenance staffHandover file and a signed snag list with closing dates

The approvals stage deserves attention. The consumer is the applicant for net metering, so the EPC contractor prepares and files on your behalf; make sure the contract says so, and names the documents you must sign. How net metering is defined

What is commonly excluded, and who pays

A per-kW price is only comparable when the exclusions are listed. These items sit outside most turnkey rooftop scopes, including ours, unless the quotation says otherwise:

  • Roof strengthening or repair. The structural check in the survey tells you whether the roof can take the load; the repair is a separate civil item. Four checks before quoting on an old roof
  • HT-side works. Modifications to the HT panel, transformer bay or metering cubicle when the plant connects at HT.
  • Battery storage. Priced and designed separately, because the use case decides the size.
  • Statutory fees. DISCOM application fees, security deposits, meter charges and inspectorate fees are paid by the consumer, usually at actuals.
  • Civil works beyond the structure footings, such as cable trenches across the yard, boundary walls or an inverter room.
  • Internet connectivity for the monitoring system, and electricity for the inverter room.
  • Insurance after handover, and the transfer of any roof waterproofing warranty.
  • Tree trimming or removal that the shadow analysis shows is needed.

Ask every bidder to price the same exclusions sheet. A quotation that leaves items off the list is not cheaper; it is incomplete. Our guide to evaluating solar EPC proposals shows how to normalise bids before comparing them.

Design and quality items to write into the scope

The scope should fix the engineering decisions that decide generation, not just the component makes.

  1. Modules from the Ministry of New and Renewable Energy's Approved List of Models and Manufacturers, with the wattage and model named. What ALMM means for your plant
  2. Inverters with make, model, quantity and warranty period in writing, and the DC-to-AC ratio stated.
  3. String design showing the number of modules per string and the voltage margin at the lowest site temperature.
  4. Cable sizing with the design voltage drop on the DC and AC sides.
  5. Structure design for the site's wind zone and the roof type, with the tilt, row spacing and walkway arrangement.
  6. Earthing and lightning protection integrated with the building's existing system.
  7. Monitoring at string or inverter level, with portal access in your name.
  8. Performance ratio to be demonstrated at commissioning, with the test method agreed in advance. What a performance guarantee should say

Price basis: what a per-kW rate must include

Our published band for a turnkey commercial or industrial rooftop plant is ₹24,000 to ₹32,000 per kW of installed DC capacity, excluding GST, with the exclusions listed above. Larger plants sit at the lower end of the band. Whatever the figure, the rate should be stated per kWp of DC capacity on a named module wattage, so that two bids with different module sizes can be compared. The solar calculator turns a capacity and tariff into a savings and payback range you can test the proposal against.

Handover documents to insist on

The plant will outlive the contractor's site team, so the handover file is part of the scope, not a courtesy. It should contain the as-built single-line diagram and layout, string and inverter test reports, the commissioning certificate, the DISCOM approval and energisation record, module and inverter warranty cards in your name, the module serial-number register, the O&M manual with the cleaning and inspection schedule, and the login for the monitoring portal. Our list of documents an EPC contractor should deliver goes through each one.

How Secured Engineers helps

Secured Engineers Pvt. Ltd. is a solar EPC and MEP contractor and consultant with offices in Noida and Ludhiana. Design is done in-house, and the DISCOM net-metering and electrical inspectorate approvals are filed in-house as part of the EPC scope. Solar can run under the same contract as the MEPF works on a new building, which removes the interface between the two. The company has delivered 535+ projects across 18+ states, with 89.77% repeat clients, and offers operation and maintenance after handover through its AMC service.

If you want the scope above priced for your roof, send your last twelve electricity bills and a roof drawing for a feasibility study through the enquiry form, on WhatsApp at +91 70099 85817, or by calling the same number.

Frequently asked

What does a solar EPC contractor do?

A solar EPC contractor engineers the plant, procures the modules, inverters, structure and cabling, installs and tests the system, files the net-metering and electrical inspectorate approvals, and hands the plant over with its as-built drawings, test reports and warranties. One contract and one point of accountability cover the whole sequence from survey to energisation.

Is net metering included in a solar EPC contractor's scope?

In a turnkey EPC scope, yes. The consumer is the applicant, so the contractor prepares the application, drawings and test documents, files them with the DISCOM, attends the inspection and arranges the bidirectional meter. The DISCOM's application fees, security deposit and meter charges are statutory fees, paid by the consumer at actuals unless the contract says otherwise.

Who pays for roof strengthening before solar installation?

The owner, as a separate civil item. The EPC contractor's survey should report whether the roof can carry the module and structure load and point to any repair needed; the strengthening itself is outside the turnkey solar scope. Ask for the structural observations in writing before you compare quotations, because a roof that needs work changes the real project cost.

What is the difference between a solar EPC contractor and a solar developer?

An EPC contractor builds a plant that you own and pay for, so the savings and the depreciation benefit are yours. A developer under a power purchase agreement owns the plant on your roof and sells you the units at an agreed tariff for a fixed term, with ownership transferring at the end. The EPC route needs capital; the PPA route needs a long contract.

How long does a rooftop solar EPC project take?

Using the stage durations published on this site: design one to three weeks, statutory approvals three to ten weeks depending on the authority, procurement and execution four to ten weeks, and commissioning one to three weeks. The approvals stage is the one most outside the contractor's control, so ask for a programme that shows the DISCOM milestones separately.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (239 Google reviews)
  • 535+ projects
  • Reply in 1 business day

Tells us which channels bring real projects. “I don’t remember” is a fine answer.

Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it