Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

Solar EPC for Factories in Tamil Nadu: DISCOM Rules, Approvals and Cost

22 October 2026 · 6 min read · by

Title card reading Solar EPC for Factories in Tamil Nadu: DISCOM Rules, Approvals and Cost.
Title card. Not a photograph of a Secured Engineers site.

A factory in Tamil Nadu planning 50 kW or more of rooftop solar should plan for net billing, not unit-for-unit net metering. Under the TNERC regulations of 2021, a factory can install up to its sanctioned load or 999 kW, with exports credited at a feed-in tariff and a network charge on every unit generated. At the published band of ₹24,000–32,000 per kW excluding GST, 100 kW costs ₹24–32 lakh.

Which metering route applies to a factory

The Tamil Nadu Electricity Regulatory Commission's Grid Interactive Solar PV Energy Generating System Regulations, 2021 (notified in the Tamil Nadu Government Gazette on 20 October 2021) are the final solar regulations listed on the Commission's website at the time of writing in October 2026. TNERC also issued Generic Tariff Order No. 8 of 2021, and TANGEDCO's technical branch circulated guidelines on it in December 2021. Later tariff orders have revised some charges, so read the table as the 2021 baseline and confirm each figure with the distribution licensee before you commit.

RouteWho it is forCapacity ruleHow energy is creditedNetwork charge (2021 order)
Net meteringDomestic consumers onlyUp to sanctioned loadUnits offset against unitsNot applicable to factories
Net billing or net feed-inAll categories except hut and agriculture, LT and HTSanctioned load or contracted demand, or 999 kW, whichever is lowerImports billed at retail tariff; exports credited at the feed-in tariff; net credit paid or carried forward at 31 MarchLT: ₹1.27 per kWh; HT: ₹0.83 per kWh, on total generation
Gross meteringHT consumers (LT consumers are not eligible) and standalone generators151 kW to 999 kWAll output sold to the licensee at the feed-in tariffNone

Gross metering needs a separate service line to the nearest HT feeder, laid and maintained at the owner's cost, and the consumer's own supply is billed separately. For most factories whose aim is to cut the electricity bill, net billing is the route, because self-consumed solar units replace units bought at the retail tariff. TANGEDCO's guideline also allows a plant behind the meter that opts for neither route, but only after prior intimation to the licensee.

What the network charge does to your payback

The order levies the network charge on the total units recorded by the generation meter, not only on exports. So each unit your plant makes costs you the network charge, whether you use it or export it. Your saving per self-consumed unit is therefore the retail energy rate on your bill minus the network charge, and each exported unit earns the feed-in tariff minus the same charge. The 2021 feed-in levelised tariffs were ₹3.37 per kWh for 11 to 150 kW and ₹3.10 per kWh for 151 to 999 kW for plants commissioned in the control period then in force, which ran to 31 March 2023. Check what applies to a plant commissioned today.

Run your own bill through the solar calculator, then subtract the network charge from the energy rate before you read the payback. Fixed and demand charges are not reduced by solar in most cases, so use the energy component only.

Capacity, transformer limits and the AC rule

The regulation and TANGEDCO's guideline on the order set these limits.

  • AC capacity governs. The plant size is the AC output capacity, reckoned from the demand recorded by the generation meter. DC panels can exceed it, but output above the sanctioned AC capacity is treated as inadvertent injection and is not paid for.
  • Transformer cap. The total net-billed solar connected to one distribution transformer should not exceed 90% of its capacity, and gross-metered HT plants should not exceed 70% of the power transformer. The licensee checks this at feasibility.
  • Arrears. A consumer with pending dues is not eligible under the regulations, so clear them first.
  • Metering. A generation meter with demand recording is required for plants above 10 kW, at the applicant's cost, and the licensee fits a check meter above 20 kW.
  • One megawatt. The ceiling is 999 kW, so a plant of 1 MW AC falls outside these routes. Look at captive or open-access options; our open access solar page explains the difference.

Approvals, fees and timelines

LT applications go through the licensee's online rooftop portal. An existing HT consumer applies to the Chief Engineer with the latest HT bill, a project report with layout and single-line diagram, a timeline, proof of ownership of the premises, a no-due certificate and GST details. Registration fees in the regulation run from ₹500 for LT plants up to 20 kW, to ₹5,000 for HT plants above 150 kW and up to 500 kW, and ₹10,000 above 500 kW and below 1 MW.

The regulation sets the licensee's clock. Registration is acknowledged within three working days. Technical feasibility is due within 15 working days of registration, and approval follows within five working days of a positive study. If the system is not feasible, the reason is due within 20 working days. The approval is valid for six months. After you submit the completion report, including a safety certificate from the Chief Electrical Inspector as applicable, the licensee should test and commission within 20 working days and fit the bidirectional meter and synchronise within 10 days after that. Real durations run longer when a transformer needs upgrading or papers are incomplete, so budget a schedule that separates installation from approvals. The electrical inspector approval guide covers the inspection. The state energy agency, TEDA, runs renewable programmes in Tamil Nadu; confirm with the licensee whether any registration with it applies to your category.

What it costs at 100 kW, 500 kW and near 1 MW

SizeIndicative cost excluding GSTRoute that fits
100 kW₹28–32 lakh, from our 100 kW page (band ₹24–32 lakh)Net billing at LT or HT, depending on your service
500 kWAbout ₹1.30 crore, from our 500 kW pageHT net billing or gross metering
Up to 999 kWToward the lower end of the band; see our 1 MW pageHT net billing or gross metering at the cap

Treat these as indicative until a site survey. Tamil Nadu adds its own cost drivers: coastal sites need corrosion-resistant structures and a wind design basis checked for the location, sheet roofs need clamp-fixed rails and a structural check, and a long cable route to the HT panel adds cost. Industrial demand sits in clusters such as Coimbatore, Tiruppur, Hosur, Sriperumbudur and Chennai, where roof area, not the rules, is usually the first constraint.

How Secured Engineers helps

We are a pan-India solar EPC contractor and we mobilise to Tamil Nadu from our offices in Noida (Delhi NCR) and Ludhiana. Design is done in-house, and Fire NOC, CEIG and DISCOM net-metering applications are filed in-house, so the HT application, the single-line diagram and the inspector's file come from one team. Mechanical, electrical, plumbing, fire and solar work can sit under one contract. Our project record lists a 120 kW rooftop plant at Bindal Agencies in Chennai, on a metal-sheet industrial roof shared with turbo ventilators. We have 535+ projects across 18+ states and 89.77% repeat clients.

Send a twelve-month bill, your sanctioned load and a roof photograph, and we will tell you which route fits and what size is realistic. Start from solar EPC for factories, message us on WhatsApp, call +91 70099 85817, or ask for a free proposal.

Frequently asked

Can a factory in Tamil Nadu use net metering for rooftop solar?

Under the 2021 TNERC regulations, net metering is for domestic consumers. Industrial and commercial consumers use net billing or net feed-in, up to sanctioned load or 999 kW, or gross metering from 151 kW. Confirm with the distribution licensee whether any later order has changed this for your category.

What is the network charge on rooftop solar in Tamil Nadu?

The 2021 order set ₹1.27 per kWh for LT prosumers and ₹0.83 per kWh for HT prosumers on net billing, charged on total generation, and none for gross metering. TNERC revises network charges in later tariff orders, so ask the licensee for the figure in force before you work out payback.

What is the largest rooftop solar plant a factory can connect in Tamil Nadu?

The regulation caps net billing and gross metering at 999 kW, and net billing is also limited to the sanctioned load or contracted demand, whichever is lower. A plant of 1 MW AC is outside these routes, so larger plants look at captive or open-access arrangements.

How long does the DISCOM approval take in Tamil Nadu?

The regulation gives the licensee 15 working days for technical feasibility from registration, five working days to convey approval, and 20 working days to test and commission after your completion report, with the meter and synchronisation within 10 days after that. Actual time depends on transformer capacity and the completeness of your papers.

Do you have solar projects in Tamil Nadu?

Our project record lists a 120 kW rooftop solar plant for Bindal Agencies in Chennai. We otherwise mobilise to Tamil Nadu from Noida and Ludhiana, and we file the approvals in-house. For any site, we start with your bills, sanctioned load and roof before quoting.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it