Delhi rooftop solar: net-metering & approvals
Who approves what, in what order, and where files actually stall — for C&I rooftop solar in Delhi. Written by the team that files these applications.
BRPL + BYPL + TPDDL (three DISCOMs, by zone)
Electrical Inspectorate, Labour Department, GNCTD
The approval route, in order
- 1
Feasibility & sanctioned-load check
Confirm your connection can carry the plant. BRPL + BYPL + TPDDL caps rooftop capacity against sanctioned load in most cases, and the exact measure varies — we check the current rule for your connection rather than assume.
- 2
Net-metering application
Filed with BRPL + BYPL + TPDDL, with the load study, single-line diagram and site details. Incomplete drawings are the single most common cause of a file sitting still.
- 3
Technical feasibility approval
BRPL + BYPL + TPDDL assesses transformer headroom and the feeder. A refusal here is usually about the network, not your roof — and often solvable with a design change.
- 4
Installation & CEIG approval
Electrical Inspectorate, Labour Department, GNCTD inspects and approves the installation. Drawings, test reports and the inspection itself are coordinated by our team.
- 5
Bi-directional meter & synchronisation
Meter installed, agreement executed, plant synchronised. Export begins once the meter is in and the agreement is countersigned.
Caps, banking terms and subsidy positions are set by state policy and revised periodically. We deliberately do not publish a figures table that would go stale — we confirm the rule that applies to your connection at feasibility stage, in writing.
Does your plant fit the cap?
Check your proposed capacity against your sanctioned load and see whether a load enhancement is needed.
Where net-metering files stall
From filings we have actually run in UP, Punjab and Haryana — and how to sequence around the delays.
Solar EPC in Delhi
Turnkey design, supply, installation and approvals — with the industrial estates we serve here.
100% DISCOM Net-Metering & CEIG Approvals Handled In-House — Zero Bureaucracy for You.
Approvals are our core trade as an MEPF contractor. We run Delhi net-metering and CEIG filings ourselves — you sign, we file, we follow up.
- 1
Feasibility & application
Load study, single-line diagram and the net-metering application prepared and filed.
- 2
CEIG / Electrical Inspector
Drawings, test reports and the inspection itself — coordinated and attended by our team.
- 3
Synchronisation & meter
Bi-directional meter, DISCOM sign-off and grid synchronisation, through to commissioning.
What would solar save your Delhi facility?
Three inputs. Your numbers appear before we ask for anything.
- 1 Your site
- 2 Your numbers
- 3 Full report
Indicative only — not a quotation. Actual output depends on shading, tilt, tariff structure and DISCOM policy. Open the full model for payback, IRR and NPV.
Where should we send the full report?
Equipment recommendations, a shadow-aware layout, DISCOM route for your state, and the full financial model — prepared by an engineer, not generated.
Your report request is in
An engineer will send your feasibility report within one business day.
Delhi net-metering questions
Who approves rooftop solar net-metering in Delhi?
BRPL + BYPL + TPDDL (three DISCOMs, by zone) handles the net-metering application, technical feasibility and the bi-directional meter. Electrical Inspectorate, Labour Department, GNCTD handles the electrical safety approval for the installation. They are separate approvals with separate timelines, and both are required before you can export.
Is there a cap on how much solar I can install in Delhi?
Most DISCOMs cap rooftop net-metering relative to your sanctioned load or contract demand, and the measure used — kW against kWp, AC against DC — differs by state and is revised periodically. Rather than quote a number that may be out of date by the time you read it, we check the rule that currently applies to your connection and tell you whether a load enhancement is worth filing alongside. Our free sanctioned-load checker gives an indicative answer in seconds.
How long do the approvals take?
It depends on the DISCOM, the completeness of the file and whether the feeder has headroom. Our published guide on net-metering delays in UP, Punjab and Haryana is written from filings we have actually run, and describes where files stall in practice rather than what the timeline says on paper.
Do you handle the paperwork or do I?
We do, in-house — the net-metering application, the CEIG approval and synchronisation. Approvals are our core trade as an MEPF contractor, not something we sub out.
Planning rooftop solar in Delhi?
We file BRPL + BYPL + TPDDL net-metering and Electrical Inspectorate, Labour Department, GNCTD approvals in-house. Send your latest bill and we'll come back with a feasibility view.