Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

Solar for Printing Presses: Sizing, Roof, Approvals and Payback (50 kW+)

22 October 2026 · 5 min read · by

Title card reading Solar for Printing Presses: Sizing, Roof, Approvals and Payback (50 kW+).
Title card. Not a photograph of a Secured Engineers site.

Size solar for a printing and packaging press from the daytime electricity bill, not from the roof area. Find the units the press already uses in daylight, check the sanctioned load and the roof, and fit the plant to the smallest of those. Up to 500 kW the usual approval route is net metering under your state's rules; above that, captive or open access rules apply.

How do you size the plant from the bill?

Four numbers set the size. The plant should not exceed the smallest of them.

Number to findWhere it comes fromWhat it decides
Daytime units usedTwelve months of bills; time-of-day readings on the meter if you have themHow much solar is used on site rather than exported
Sanctioned load or contract demandBill header or connection agreement; the sanctioned load calculator helpsThe capacity the DISCOM will connect
Transformer and feeder headroomTransformer rating and low-load readings such as Sunday afternoonsReverse flow when the press is idle
Usable roofA survey after shading, tanks, plant and access paths are taken outThe physical size of the array

As a planning figure for north India, a kilowatt of solar gives about 120 units a month, so 100 kW gives about 12,000 units. Compare that with your weekday daylight use. If the plant is smaller than the daylight load, nearly every unit is used on site. A press that stops on Sundays exports on those days, which is why the lowest weekend load matters as much as the weekday peak. Test sizes in the solar calculator and check area in the plant area calculator. For a view of how bills drive sizing in the north, see sizing solar from a Punjab factory bill.

What is specific to a printing and packaging press?

Most of the method is common to any factory. These points belong to the sector, and are things to check on your site rather than statistics.

  • Press-hall air conditioning. Print quality depends on stable temperature and humidity in the press hall and often in paper storage, so a large part of the daytime load may be air conditioning or dehumidification. That load runs with the sun and suits solar. Read the HVAC load from your bill and meter before assuming only the machines count; the note on sizing solar against HVAC base load explains the method.
  • Shift pattern. Presses are often run in one or two shifts on working days. Evening and night shifts use no solar, so size to the day shift and the lowest daylight load.
  • RCC roofs in urban estates. Many presses sit in multi-storey buildings with flat RCC roofs. Check slab condition and loading, existing water tanks, lift machine rooms and parapets, plus the shadows of neighbouring buildings. Anchoring panel structures through the waterproofing is a leak risk; see roof penetration and waterproofing and structural loading of older roofs. The roof load calculator gives a first check. Confirm roof rights if the plot is leased.
  • Solvents and ink vapour. Exhaust outlets for inks, washes and coating solvents should be mapped on the roof drawing. Keep the array and DC wiring clear of them and agree isolator and access arrangements with the fire officer and insurer; see rooftop solar DC fire safety.
  • Paper dust and ink mist. Deposits on modules lower output. Plan walkway access and a cleaning routine.
  • Drives, dryers and curing equipment. Variable-speed drives add harmonics and dryers add load steps; a power-quality check at the design stage avoids inverter trips. See harmonics and inverters.
  • DG interlocks. If a DG set backs up the press, the solar inverters need anti-islanding and a defined changeover; see solar with DG sets.

Which approval route applies by size?

Plant sizeUsual routeCheck first
50 kW to 500 kW on your own roofNet metering under your state regulation; central limit 500 kWState cap, often tied to sanctioned load; DISCOM feasibility; meter
Above 500 kW on your own premisesCaptive plant, or the arrangement your state regulation allowsCaptive tests, state charges, banking, and Electrical Inspector approval for HT
Supply from an off-site plantGreen energy open access, available from 100 kWWheeling, cross-subsidy and additional surcharge, banking, term

A 2021 amendment to the Electricity (Rights of Consumers) Rules, 2020 raised the net-metering limit to 500 kW from 10 kW. The Green Energy Open Access Rules, 2022 lowered the open access limit for green energy from 1 MW to 100 kW. Under Rule 3 of the Electricity Rules, 2005 a captive plant needs its users to own at least 26 percent and consume at least 51 percent of the electricity it generates annually. State regulations set the working detail, so confirm each point with your DISCOM. See open access solar and the size pages for 100 kW and 500 kW.

How is payback worked out?

Cost comes from the published band for commercial and industrial solar of ₹24,000 to 32,000 per kW excluding GST. Savings come from the energy charge avoided on each self-used unit; solar does not normally reduce fixed or demand charges, so do not apply the whole bill. Payback is cost divided by yearly saving after maintenance.

Illustration for a 100 kW plant, so the arithmetic is visible. At the mid-band ₹28,000 per kW the cost is ₹28 lakh excluding GST. Generation is about 1.44 lakh units a year at 120 units per kW per month. The avoided rate is a blended ₹9 per unit, the figure used on the site's published size pages; replace it with your own. Maintenance is taken as 1 percent of cost a year, and exported units are valued at zero.

Share of generation used in the pressYearly saving after maintenanceSimple payback
100%About ₹12.7 lakhAbout 2.2 years
80%About ₹10.1 lakhAbout 2.8 years
60%About ₹7.5 lakhAbout 3.7 years

The figures ignore GST, tax treatment, module degradation and tariff changes, and a different roof or any HT work will change the cost. Use the payback calculator with your own bill, and read rooftop solar payback in India.

What should the tender brief say?

Bidders price what the brief tells them. For a press, state the shift calendar and the lowest weekday and weekend daylight load; the roof type, age and any structural report; the position of vents, tanks and lift rooms; who owns the roof; the cleaning routine; what the insurer and fire officer have asked for on DC wiring; and who files the DISCOM application and pays for the meter. The guide to evaluating solar EPC proposals shows how to compare bids on the same basis.

How Secured Engineers helps

Secured Engineers designs solar plants in-house and files CEIG and DISCOM net-metering applications in-house. MEPF and solar can sit under one contract, which helps where a press also needs electrical upgrades, fire fighting or HVAC work alongside the array. The company works from offices in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients.

Start from our solar for factories page, or send twelve bills and a roof photograph on WhatsApp, call +91 70099 85817, or ask for a free proposal.

Frequently asked

What size solar plant suits a printing press?

The size is set by your daytime electricity use, your sanctioned load and the usable roof, whichever is smallest. Take twelve months of bills, estimate the daytime share of the units, and size so that nearly all the solar output is used on site. A press that runs one shift needs a smaller plant than one that runs two or three, so read the shift calendar before sizing. Test options in the solar calculator.

Does a printing press qualify for net metering?

Usually, up to the limits in your state regulation. The central limit for net metering was raised to 500 kW by a 2021 amendment to the Electricity (Rights of Consumers) Rules, 2020, and states often tie the cap to sanctioned load. Above that, the route is a captive plant or open access. Confirm the cap, the feasibility process and the metering with your DISCOM before the design is frozen.

Can an RCC roof carry a rooftop solar plant?

Generally yes, but a structural check is needed. Panels and their structure add load, and the roof may already carry water tanks, plant or an extra floor in future. Ballasted or anchored structures behave differently for waterproofing, wind and maintenance. The roof's age, slab condition and parapet height matter. Ask for a structural opinion and a waterproofing plan with the proposal, not after the contract.

Do solvent vapours and ink mist affect rooftop solar?

They can matter in two ways. Exhaust vents and stacks that discharge vapour or mist near the array create a deposit and a fire consideration, so keep the layout clear of outlets and discuss DC wiring, isolators and access with the fire officer and insurer. Deposits on modules lower output, so plan access for cleaning. Both are site-specific design points rather than rules from a standard.

How is payback calculated for a press?

Divide installed cost by yearly saving after maintenance. Saving comes from the energy charge avoided on each unit the press uses from the plant, not from the whole bill, because solar does not usually reduce fixed or demand charges. Exported units should be valued cautiously. Share of generation used on site is the biggest variable, which is why sizing to daytime load matters more than maximising the roof.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it