Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Electrical

Electrical RFQ Template for Industrial Works: HT, LT, Earthing and Testing

22 October 2026 · 6 min read · by

Title card reading Electrical RFQ template for industrial works, with HT, LT, earthing and testing listed as sections of a checklist
Title card. Not a photograph of a Secured Engineers site.

An industrial electrical RFQ should tell every bidder the same six things: where the scope starts and stops, what the drawings and specifications are, the bill of quantities to price, the standards and makes allowed, the tests that prove the work, and the commercial terms. Leave one out and bidders fill the gap differently, so quotes cannot be compared. The template below covers HT, LT, earthing and testing.

What the template contains

Copy the section headings into your own document and fill each one. The right-hand column is the reason the section exists: each one stops a specific argument that tends to start after the order is placed.

SectionWhat you writeThe mistake it prevents
1. Project and site dataLocation, sanctioned load or contract demand, supply voltage, DISCOM, fault level if known, site access and working hoursBidders pricing a 11 kV job as if it were LT, or assuming night work is allowed
2. Scope and battery limitsFirst and last item you want supplied, and what the DISCOM, civil contractor and other trades provideThe transformer plinth, cable trench or metering cubicle that nobody priced
3. Drawings and specificationsSingle-line diagram, layout, load schedule, cable schedule, the specification for each major item, with revision numbersBids priced from different revisions
4. Bill of quantitiesItemised list in a fixed format: description, make options, unit, quantity, rate, amountLump-sum bids that hide what is excluded
5. Standards and approved makesApplicable Indian Standards and a make list per item, with a route to propose equalsUnbranded equipment at an unbranded price
6. Testing and commissioningTests per item, who witnesses, what certificates are handed over"Tested" meaning only that someone switched it on
7. Approvals and responsibilitiesWho files with the DISCOM and the Electrical Inspector, who pays the fees, who attends the inspectionEnergisation delayed while two parties each assume the other applied
8. Commercial termsPrice basis, taxes, validity, payment milestones, retention, delay damages, defects periodBids that differ in terms and not only in price

How to fill the scope and battery limits

Write the scope as a chain from the point of supply to the last socket, and mark where each link is yours, the bidder's or someone else's. A usable wording is: "From the DISCOM metering cubicle outgoing terminals to the LT distribution boards in each building, including all cables, terminations, supports, glands and labelling." Then list the exclusions the bidder should not assume: civil work, DISCOM charges, the DG set itself if bought separately.

Split HT and LT in the BOQ because they carry different risks. The HT block normally covers the transformer or transformers, the HT breaker panel with protection relays, HT cable and terminations, and the metering arrangement the DISCOM specifies. The LT block covers the main panel, motor control centres, capacitor banks, busducts or cables, distribution boards, lighting and small power. Ask for each panel as a separate line with its incomer rating, short-circuit rating and outgoing list. A line that just says "LT panel, 1 no." invites a quote for the thinnest version.

If a DG set, UPS or solar plant connects to the same bus, say so in the scope and state the changeover or synchronising arrangement you expect. These interface points are where electrical contractors and equipment suppliers most often disagree about who owns the problem.

Earthing, lightning protection and cable work

Earthing is cheap to specify and expensive to correct later, so give it its own block of the BOQ. State the earthing design basis: the earth resistance you require, the electrode type and number of pits, the grid or ring if the site needs one, and the test-pit arrangement. Indian practice follows the earthing code IS 3043; name it, and ask the bidder to state which edition they price against.

For cables, specify voltage grade, conductor material, insulation type, armouring and the applicable Indian Standard, then ask for installation method by route: trench, tray, conduit or direct burial. Cable quantities should be measured from the cable schedule, not guessed from the layout. Ask bidders to quote glands, lugs and tray separately so a low cable rate does not hide a high accessories price.

Lightning protection, if in scope, needs its own risk assessment reference and a clear boundary with the building's structural contractor. Say who supplies down-conductor supports on the roof.

The testing schedule to put in the RFQ

Name the tests in the RFQ so the bidder prices them. Typical industrial practice looks like the table below. Treat it as a starting list and let your engineer or the manufacturer's instructions add to it.

ItemTypical tests before energisationRecord to receive
HT and LT cablesInsulation resistance; high-voltage withstand test on HT cable as the manufacturer or standard allows; continuity and phase sequenceTest sheet per cable run
TransformersInsulation resistance, turns ratio, vector group, and oil breakdown voltage where oil-filledFactory test certificate and site test sheet
HT and LT switchgearInsulation resistance, contact resistance, interlock and trip checks, protection relay testing by secondary injectionRelay settings and test report
EarthingEarth resistance of each electrode and of the combined system by the fall-of-potential method, plus continuity of bondingResistance readings with pit locations
Motors and drivesInsulation resistance, direction of rotation, no-load currentCommissioning sheet
Whole installationFunctional test of changeover and interlocks; loading and thermography after a period on loadCommissioning certificate and as-built drawings

Add one sentence on who witnesses: "Tests are carried out in the presence of the employer's representative, with seven days' notice." The notice period is yours to choose.

Approvals, inspection and the commercial section

An HT installation, and in many states any new installation above 650 V, is inspected by the state Electrical Inspector before it is energised, under the CEA safety regulations. The Chief Electrical Inspectorate of the CEA describes the same split by voltage level and generating-plant size for installations in its own jurisdiction. Your RFQ should say whether the contractor prepares and files the inspection application and attends the inspection, or whether you do. The DISCOM's own demand, metering and agreement process runs alongside. Our CEIG approval guide sets out the sequence for factories.

In the commercial block, ask for prices in a fixed format with taxes shown separately, a stated validity, and the make and model behind every major item. Payment is typically tied to milestones such as material delivery, installation and testing, with a retention held until the defects liability period ends; the percentages are negotiated, so write the ones you want. Add delay damages and a defects period only if you intend to enforce them. A bidder who sees terms nobody enforces prices them as noise.

Comparing the bids that come back

Put the returned BOQs side by side and compare line by line, not by total. A total that is a long way below the others usually means a missing line, a thinner specification or an unpriced test. Check three things first: that the make is on your list, that every test in your schedule is priced, and that exclusions are written down. Then ask the low bidder to confirm the scope in writing before you compare commercial terms. The electrical infrastructure service page and our note on testing and commissioning describe what a complete scope contains.

How Secured Engineers helps

We design electrical systems in-house, so an RFQ can come from the same team that will price it. Fire NOC, CEIG and DISCOM net-metering applications are filed in-house, which means the approvals section of your RFQ can be written as a real plan rather than a placeholder. MEPF and solar can sit under one contract if you want a single scope. We work from offices in Noida (Delhi NCR) and Ludhiana, and the company has completed 535+ projects across 18+ states, with 89.77% repeat clients.

If you already have a draft, send it to us for a scope check before it goes out. Use the RFQ page to share the drawings, or message us on WhatsApp or call +91 70099 85817. If you would rather have us price the work, ask for a free proposal.

Frequently asked

What is an RFQ for electrical works?

A request for quotation is the document you send to contractors so they price the same scope. For electrical works it carries the project data, scope limits, drawings, a bill of quantities, standards and approved makes, a testing schedule and commercial terms. Its job is to make bids comparable, so the lowest bid is lower for the same work rather than for less of it.

What is the difference between an RFQ and a tender?

The words overlap in practice. An RFQ usually goes to a short list of contractors and compares price against a fixed scope. A tender is more formal, often public, with eligibility rules, bid security and a prescribed evaluation method. The template here works for either: the scope, BOQ and testing sections are the same, and a tender adds the eligibility and legal pages around them.

Should I ask for a lump sum or a priced BOQ?

Ask for a priced BOQ in your format, with a lump-sum total at the end. The itemised rates show what each bidder has included and give you a basis to price variations. A pure lump sum is easier to read but hides exclusions, and it leaves you arguing about scope when you add a feeder or change a panel.

Who should attend the Electrical Inspector's inspection?

The installation is inspected on behalf of the owner, so the owner or a representative should attend with the contractor and the licensed electrical supervisor, carrying the single-line diagram, test certificates and the earthing records. Decide in the RFQ who prepares the application and who attends, because the inspector may ask for corrections on the spot.

How many bids should I ask for?

Three to five is typical for a project of this kind. Fewer gives you no price check; more makes the evaluation slow without improving the answer. Brief each bidder the same way, answer their questions in writing to everyone, and give all of them the same closing date.

Related services

Share the single-line diagram, the equipment schedule and twelve months of bills with maximum demand — the review starts from your figures.

Need a load, supply or panel question checked?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Speak to a Lead Engineer