Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Electrical

DG Set Sizing

DG set sizing selects generator capacity from the loads that must actually run on backup — their running kVA plus the starting demand of the largest motors — inside a loading band the engine stays healthy at, rather than copying the transformer rating.

Why it matters on an MEPF project

Two opposite failures dominate: sets sized to the incomer (running chronically under-loaded — wet stacking, glazing, and with CPCB IV+ machines, after-treatment grief) and sets sized to a wishful list that stalls when the chiller starts. The honest method segregates essential loads, sequences big-motor starts (or softens them with star-delta/VFD), and lands the set where typical backup load sits in a healthy band of its rating.

Sizing also inherits context: CPCB IV+ pricing changed the oversizing penalty; acoustic and stack rules constrain the room; AMF changeover design decides whether the sizing ever gets exercised cleanly; and in NCR, run-hour policy pushes the whole strategy toward solar+storage with the DG as true standby.

How it's specified in practice

Sizing method — DG Set Sizing
ParameterTypical / working positionGoverning reference
Essential-load listWhat genuinely must run on outage — walked, not assumedload segregation
Motor startingLargest starter's inrush accommodated (sequencing/soft start)design practice
Healthy loadingAvoid chronic light-load running; size to sit mid-bandengine manufacturer guidance
Compliance envelopeCPCB IV+ (new sets), acoustic enclosure norms, NCR run rulesCPCB notifications / CAQM directions

Common mistakes

  • Copying transformer kVA as generator kVA.
  • Forgetting starting kVA — the set that trips on the first compressor.
  • Chronic 20% loading — the engine pays for the flattery.
  • No load-shedding logic, so "essential" quietly becomes "everything".

Related on this site

One of 68 working definitions in the MEPF & solar engineering glossary. The buying side of the same decisions is in the buyer's guides; the numbers are in the calculators.

Frequently asked

What size DG do I need for my factory?

List the true essential loads, add the largest motor's starting demand, and select so typical backup sits in a healthy loading band. Our DG preliminary load calculator gives the steady-state kVA from the essential load and lists the motor starts for the generator maker to check.

Is bigger safer?

No — diesel engines dislike light running, and post-CPCB IV+ capacity is expensive. Right-sized with sequenced starts beats oversized every time.

Standards referenced: CPCB genset notifications · engine manufacturer application guidance

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Speak to a Lead Engineer