MEP Bid Evaluation Sheet: Technical and Commercial Scoring Template
A bid evaluation sheet scores every MEP bidder on the same technical criteria and then compares prices only among bidders who qualify. This template has four parts: pass-or-fail gates, a weighted technical score, a commercial normalisation checklist and a clarification log. Fill the technical part before opening any price, and sign it.
How the sheet works
The Department of Expenditure's Manual for Procurement of Works (second edition, 2025) is a public-sector document, but its logic is useful to a private owner. It makes least-cost selection, the L1 among technically responsive bids, the default for routine works, and allows quality-and-cost based selection for complex or critical ones. It also says marking should not rely on the subjective opinion of the evaluating panel: two evaluators should reach close to the same score from the same bid.
The sheet follows that sequence. Gates first, because a bid that fails one is not scored. Technical score second, on the evidence in the bid. Commercial comparison last, on prices brought to the same scope. Keep the three apart in your file and in the order of work.
If you decide to combine quality and price into one score instead, the sheet needs one more line: the weights. The manual's worked example gives cost 80 per cent and technical 20 per cent and says the technical weight should never be more than 30 per cent. A hospital or pharma package, where a failed qualification test costs months, may justify more weight on quality than a warehouse does. Whatever you pick, write it in the tender before anyone prices.
Part A: gates (pass or fail)
A gate is a yes-or-no question. One failure and the bid is not evaluated further, unless you have agreed in writing to a clarification.
| Gate | What to check | The mistake it prevents |
|---|---|---|
| Complete submission | All requested forms, drawings, datasheets and the priced BOQ in the format issued | Comparing a full bid with a summary letter |
| Similar work | At least the number of completed jobs of similar type and scale that you stated in the tender, with client contact | Awarding a hospital package to a bidder who has done offices |
| Licences | Electrical contractor licence and supervisor certificate where required, and registrations for fire and plumbing work | Finding at inspection that the licensee is not on site |
| Financial capacity | Turnover and net worth against the contract value, from audited statements | A bidder who cannot fund the first three months of material |
| Makes | Every item in the approved-make list quoted by an approved make, or a deviation sought in writing | Silent substitution of lesser equipment |
| Scope acceptance | No unilateral exclusions or conditions written over your terms | A cheap price that depends on a rewritten contract |
| Validity and security | Bid validity period and bid security as the tender asks | Prices that lapse before you decide |
| Safety record | Site safety policy and a named safety officer for the package | Safety left to the owner on site |
Part B: technical score
Score each line from 0 to its maximum, using a rubric you write before bids arrive. The weights below are a starting point; change them to suit the package and fix them in the tender.
| Criterion | Max | What earns full marks |
|---|---|---|
| Experience in similar work | 20 | Completed jobs of the same type, verified with clients |
| Site team and key personnel | 15 | Named project manager and trade leads with relevant years and no other full-time assignment |
| Method and programme | 15 | Sequence, shutdown plan and manpower histogram that match your milestones |
| Compliance with specification and makes | 15 | Line-by-line compliance, deviations listed and justified |
| Design and coordination capability | 10 | In-house design or a named designer; clash-checking method for services |
| Approvals and testing support | 10 | Clear plan for Fire NOC, electrical inspection and commissioning tests |
| Safety and quality system | 5 | Written plan, inspection and test procedures, record formats |
| After-sales and maintenance support | 10 | Defect response time, spares, local presence, AMC terms |
Set a minimum technical score before opening prices, say 70 out of 100, and drop bidders below it. Two scorers working independently, then reconciling, remove most personal bias. The manual has the marking criteria discussed with bidders at a pre-bid meeting and expects any change that follows to be formally recommended, not made informally. Do the same: publish the rubric, take questions, and re-issue it to everyone if it changes.
Part C: commercial normalisation
Prices are only comparable when they cover the same work. Build a normalised price for each bidder, then compare.
- Quantities. Everyone prices your BOQ quantities. If a bidder changed quantities or added lines, restate to your BOQ.
- Exclusions. List every exclusion and cost it from the other bids' rates. A bidder excluding cabling, painting of pipework or testing has not saved money.
- Provisional and PC sums. Compare like with like. A large provisional sum can hide real cost.
- Taxes. Keep prices exclusive of GST in every bid, then apply the rate once.
- Price variation. Fixed price or escalation clause? Our note on price escalation in MEP quotes shows how copper and steel clauses change the real figure.
- Payment, retention and warranty. An advance, a lower retention or a short defects period each has a cost. Convert the difference to a number or a note.
- Abnormally low rates. Ask for a rate breakdown. The government manual advises against a fixed percentage below the estimate that is deemed abnormal, and says that drawings and specifications should be prepared with enough care to protect against it.
Our MEP quotation comparison calculator lays out the same comparison in a form you can fill, and the note on turnkey scope gaps lists where bids most often differ.
Part D: clarification and decision log
- Clarification number, date, bidder and the item.
- Question asked, in writing, copied to all bidders if it changes scope.
- Answer received and date.
- Effect on score or normalised price.
- Final ranking, who signed, and the reason if the recommended bidder is not the lowest evaluated price.
If the recommendation is not the lowest evaluated bid, write the reason in the log in plain words. A later dispute is easier to answer from a signed page than from memory.
How Secured Engineers helps
We design MEP in-house and file Fire NOC, CEIG and DISCOM net-metering in-house, so we can read a bid for what it leaves out. MEPF and solar can sit under one contract, which changes how scope gaps show up between trades. We work from offices in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients. Our turnkey EPC page describes how we package the trades.
To use this sheet on live bids, send the tender documents and the quotations through the RFQ page and we will compare them against your drawings and tell you what differs. You can also WhatsApp us or call +91 70099 85817. If we are one of the bidders, we will say so.
Frequently asked
Should I always award an MEP package to the lowest bidder?
Only among bidders who pass your technical gates and whose prices have been normalised to the same scope. The Government of India's works procurement manual makes least-cost selection among technically responsive bids the default for routine works and allows quality-and-cost scoring for complex ones. A low price that leaves out scope is not the lowest price.
What technical weight should I use if I score quality and price together?
Set it before bids open and write it in the tender. The government works manual's own worked example gives cost 80 and technical 20 and says the technical weight should never be more than 30 per cent in its example, which shows how price-led its approach is. A private owner with a complex hospital or pharma package may choose differently, but must justify and fix the weights in advance.
How do I treat an abnormally low bid?
Ask the bidder to explain the rate item by item before you decide. The government works manual advises against fixing a normative percentage below the estimate that automatically counts as abnormally low, and recommends getting the drawings and specification right so low bids are less likely. Look for missing scope, thin site staffing and unrealistic material rates.
Why score technical criteria before opening the price?
Because knowing the price changes how people score. Opening the commercial envelope only for bidders who pass the technical gates keeps the marks about capability. It also lets you issue clarifications on scope without anyone seeing numbers. Record the technical scores and sign them before the price envelopes are opened.
Can Secured Engineers fill this sheet for my bids?
We can review your bids and BOQ against the drawings and tell you where scope, makes or exclusions differ between them. Send the tender documents and the quotations through the RFQ page. The review compares and flags; it does not pick a contractor for you, and we will say if we are one of the bidders.
Related services
Related guides
- The Duct and the Beam Both Fit. On Separate Drawings.
- The Thresholds Moved. Your Factory May Have Changed Category Without Doing Anything.
- MEPF Cost per Sq Ft in India: How to Build a Budget You Can Defend
- One Bill, Six Tenants, and No Way to Prove Who Used What.
- A Digital Twin Is Not a 3D Model. It Is a Live Data Obligation.
- Fire System Weekly and Monthly Inspection Log: A Template for Factories
Related on this site
- termSolar Payback Period
- termAMC / O&M SLA
- termEPC
- serviceSoil, Waste & Rainwater Drainage (Plumbing)
- servicePumping & Hydro-Pneumatic Systems (Plumbing)
- calculatorWater Reuse Savings Calculator
- calculatorPump Head Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guideEnvironmental clearance (EIA 2006)
- guideNBC 2016 fire and life safety for factories
More on Project Delivery & Commercial · all insights