Payment Milestones in a Solar EPC Contract: What to Pay Against and When
Pay a solar EPC contractor against evidence, not dates. A sound schedule has a modest advance backed by a bank guarantee, then instalments for approved design, material delivered and insured at site, mechanical completion, commissioning and a passed performance test, with a retention held through the defects period. Each payment should match a document you can inspect, and the largest instalments should come late.
What should each payment be tied to?
| Milestone | Evidence you should see | What it protects | Watch-out |
|---|---|---|---|
| Advance on order | Signed contract; advance bank guarantee from the contractor | Contractor's cost of mobilising and ordering | An advance with no guarantee is an unsecured loan |
| Design and drawings approved | Your written approval of layout, single-line diagram and structural check | You hold a design you accepted | Approval of drawings is not approval of the roof's strength |
| Material delivered at site | Delivery challans, serial numbers of modules and inverters, test certificates, storage and insurance cover | Equipment is real, yours and protected | Pay for what is stored and tagged, not what is invoiced |
| Mechanical completion | Structure, modules and cabling installed; punch list agreed | Work in place matches the drawing | Hold back for punch-list items |
| Ready for commissioning | Pre-commissioning tests recorded; statutory and DISCOM applications lodged | The contractor's part is finished | Do not let a DISCOM delay stall this payment unfairly |
| Commissioned and synchronised | Commissioning certificate; net meter installed where applicable; monitoring live | The plant works on the grid | Define "commissioning" in the contract |
| Performance ratio test passed | Test report on the agreed method over the agreed period | The plant delivers what was promised | Agree method, instruments and weather limits in advance |
| Retention released | End of defects period; punch list and warranty documents complete | Early defects are fixed | Do not release at handover |
How big should the advance be, and how is it secured?
There is no regulation that sets a percentage for a private solar contract; it is commercial. A useful reference is how a government works contract treats the same questions. The General Conditions of Contract for PWD works, 2023 allow a mobilisation advance not exceeding 10% of the tendered amount, released in two or more instalments each not exceeding 5%, with later instalments only after proof that the earlier one was used on the work. They also pay a secured advance of up to 75% of the assessed value of non-perishable materials brought to site and adequately stored, and for fragile or combustible items only if the contractor provides comprehensive insurance cover. That advance is recovered when the material is built into the work. See the GCC. The same document asks for a performance guarantee valid up to the completion date plus at least six months, and a 2.5% security deposit deducted from running bills.
A private owner does not have to copy those figures. The principles carry over: keep the advance modest, release it in steps, back it with a bank guarantee that reduces as it is recovered, and pay for material only when it is at site, identified and insured. Solar modules are glass, so the insurance point applies.
How should material at site be paid?
Modules, inverters and structures are usually the largest part of the price, so this is where owners are most exposed. Pay against delivery, not against a pro-forma invoice. Insist on serial numbers listed against the delivery challan, so that the warranty and the ALMM listing can be tied to the modules actually on your roof. Insist on covered storage, tagging and insurance cover for the stored goods. Title to the material should pass to you on payment. Check the supplier's test certificates before you pay. The batch should match what the design needs.
What happens when the DISCOM controls the date?
Between "installed" and "commissioned" sit the electrical inspector's approval where it applies and the DISCOM's net-metering process: agreement, meter installation, synchronisation. Neither is wholly in the contractor's hands. A contract that ties a large payment to commissioning without saying so lets one side bear the DISCOM's delay. The fair answer is a separate "ready for commissioning" milestone, payable when the contractor's work and its filings are complete, with the final commissioning instalment following.
The date also matters for the law. As of October 2026, MNRE's O.M. of 4 August 2026 exempts net-metering and open-access projects from ALMM List-II (solar cells) only if they are commissioned by 31 December 2026; after that, List-II compliance applies (O.M.). If the contract runs close to that date, say who bears the risk of a slip and what it costs.
How do the performance test and retention work?
A performance ratio (PR) test compares measured output to what the plant should produce at the irradiance and temperature recorded during the test. The contract should fix the method, the instruments and their calibration, the irradiance window, the test duration, and what happens on a fail: a retest period, then a price reduction or liquidated damages. The balance of the contract price should depend on a pass.
Retention is the second lever. Hold it until the end of the defects period, and state its amount as a number, not as "reasonable". Set it above the likely cost of the commonest early defects, such as loose terminations, inverter faults and mounting corrosion. A public-works benchmark is the 2.5% security deposit above; private contracts vary. Our notes on payment terms and retention and retention disputes apply directly. If your contractor is a micro or small enterprise, the statutory 45-day rule for paying registered MSME suppliers also bites; see the MSME 45-day rule.
What are the red flags in a proposed schedule?
- A large advance with no bank guarantee.
- Payment on invoice date or on dispatch, not on delivery at site.
- No definition of "commissioning", or one that depends on a third party's action.
- No performance ratio test, or a test the contractor runs and reports alone.
- Retention released at handover, or no retention at all.
- A final instalment smaller than the cost of rectifying a likely defect.
How Secured Engineers helps
We design the plant in-house and file the CEIG and DISCOM net-metering applications ourselves, so the "ready for commissioning" and "commissioned" steps sit with one team. Solar and MEPF can be contracted together, which means one payment schedule instead of two. We work from offices in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients. Our guide to selecting a solar EPC contractor and our testing and commissioning page give more.
If you hold a draft solar EPC contract or a quotation, send it and we will read its payment schedule against the points above. Start from our solar EPC service, message us on WhatsApp, call +91 70099 85817, or ask for a free proposal.
Frequently asked
How much advance should I pay a solar EPC contractor?
No regulation sets a figure for a private contract, so it is a commercial term. Keep it modest, release it in instalments, and back it with a bank guarantee that reduces as the advance is recovered. As a public-works reference, PWD's 2023 conditions allow a mobilisation advance up to 10% of the tendered amount in instalments of up to 5%.
Should I pay when material reaches the site?
Yes, but pay for what is delivered, identified and protected. Ask for delivery challans, module and inverter serial numbers, covered storage and insurance cover, and let title pass to you on payment. Check the test certificates first. Paying on a pro-forma invoice before delivery leaves you exposed if the supplier fails.
What is a performance ratio test and why tie payment to it?
A performance ratio test compares the plant's measured output with what it should produce at the irradiance and temperature during the test. Tying the final payment to a passed test gives the contractor a reason to commission carefully. Fix the method, instruments, duration and fail remedy in the contract before work starts.
Who bears the risk if the DISCOM delays commissioning?
The contract must say. A fair structure has a separate milestone for completion of the contractor's work and filings, paid on that, with the commissioning instalment following. Without it, one side silently bears the delay. The date can also carry a regulatory consequence, as with the 31 December 2026 ALMM List-II window for net-metering projects.
How long should retention be held on a solar plant?
Until the end of the defects liability period, not until handover, and as a stated amount. The percentage is a commercial choice; a public-works reference is a 2.5% security deposit with a performance guarantee valid to completion plus six months. Set yours above the likely cost of common early defects.
Related services
Related guides
- A Plant Down 8% Looks Exactly Like a Plant Working Fine.
- Three Vendors, One Roof, Three Different Generation Figures.
- Perovskite Cells Promise 30%+ Efficiency. Your Roof Doesn't Have Ten Years to Wait and See.
- What an 800 kW Solar Plant Costs and Needs: Roof, Connection, Approvals
- CEIG Approval for a 1 MW Solar Plant: Drawings, Tests and the Inspection
- Solar Plant Handover Documents: The File You Must Have Before Final Payment
Related on this site
- termDCR Modules
- termSolar Payback Period
- termOpen Access (Solar)
- serviceO&M & Performance (Solar EPC)
- serviceBattery / Hybrid Storage (Solar EPC)
- calculatorMEP Maintenance Budget Calculator
- calculatorSolar Amc Cost Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guideFactory approvals roadmap, India
- guideCLU for industrial land
More on Solar & Renewables · all insights