Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

Payment Milestones in a Solar EPC Contract: What to Pay Against and When

22 October 2026 · 5 min read · by

Title card reading Payment Milestones in a Solar EPC Contract: What to Pay Against and When.
Title card. Not a photograph of a Secured Engineers site.

Pay a solar EPC contractor against evidence, not dates. A sound schedule has a modest advance backed by a bank guarantee, then instalments for approved design, material delivered and insured at site, mechanical completion, commissioning and a passed performance test, with a retention held through the defects period. Each payment should match a document you can inspect, and the largest instalments should come late.

What should each payment be tied to?

MilestoneEvidence you should seeWhat it protectsWatch-out
Advance on orderSigned contract; advance bank guarantee from the contractorContractor's cost of mobilising and orderingAn advance with no guarantee is an unsecured loan
Design and drawings approvedYour written approval of layout, single-line diagram and structural checkYou hold a design you acceptedApproval of drawings is not approval of the roof's strength
Material delivered at siteDelivery challans, serial numbers of modules and inverters, test certificates, storage and insurance coverEquipment is real, yours and protectedPay for what is stored and tagged, not what is invoiced
Mechanical completionStructure, modules and cabling installed; punch list agreedWork in place matches the drawingHold back for punch-list items
Ready for commissioningPre-commissioning tests recorded; statutory and DISCOM applications lodgedThe contractor's part is finishedDo not let a DISCOM delay stall this payment unfairly
Commissioned and synchronisedCommissioning certificate; net meter installed where applicable; monitoring liveThe plant works on the gridDefine "commissioning" in the contract
Performance ratio test passedTest report on the agreed method over the agreed periodThe plant delivers what was promisedAgree method, instruments and weather limits in advance
Retention releasedEnd of defects period; punch list and warranty documents completeEarly defects are fixedDo not release at handover

How big should the advance be, and how is it secured?

There is no regulation that sets a percentage for a private solar contract; it is commercial. A useful reference is how a government works contract treats the same questions. The General Conditions of Contract for PWD works, 2023 allow a mobilisation advance not exceeding 10% of the tendered amount, released in two or more instalments each not exceeding 5%, with later instalments only after proof that the earlier one was used on the work. They also pay a secured advance of up to 75% of the assessed value of non-perishable materials brought to site and adequately stored, and for fragile or combustible items only if the contractor provides comprehensive insurance cover. That advance is recovered when the material is built into the work. See the GCC. The same document asks for a performance guarantee valid up to the completion date plus at least six months, and a 2.5% security deposit deducted from running bills.

A private owner does not have to copy those figures. The principles carry over: keep the advance modest, release it in steps, back it with a bank guarantee that reduces as it is recovered, and pay for material only when it is at site, identified and insured. Solar modules are glass, so the insurance point applies.

How should material at site be paid?

Modules, inverters and structures are usually the largest part of the price, so this is where owners are most exposed. Pay against delivery, not against a pro-forma invoice. Insist on serial numbers listed against the delivery challan, so that the warranty and the ALMM listing can be tied to the modules actually on your roof. Insist on covered storage, tagging and insurance cover for the stored goods. Title to the material should pass to you on payment. Check the supplier's test certificates before you pay. The batch should match what the design needs.

What happens when the DISCOM controls the date?

Between "installed" and "commissioned" sit the electrical inspector's approval where it applies and the DISCOM's net-metering process: agreement, meter installation, synchronisation. Neither is wholly in the contractor's hands. A contract that ties a large payment to commissioning without saying so lets one side bear the DISCOM's delay. The fair answer is a separate "ready for commissioning" milestone, payable when the contractor's work and its filings are complete, with the final commissioning instalment following.

The date also matters for the law. As of October 2026, MNRE's O.M. of 4 August 2026 exempts net-metering and open-access projects from ALMM List-II (solar cells) only if they are commissioned by 31 December 2026; after that, List-II compliance applies (O.M.). If the contract runs close to that date, say who bears the risk of a slip and what it costs.

How do the performance test and retention work?

A performance ratio (PR) test compares measured output to what the plant should produce at the irradiance and temperature recorded during the test. The contract should fix the method, the instruments and their calibration, the irradiance window, the test duration, and what happens on a fail: a retest period, then a price reduction or liquidated damages. The balance of the contract price should depend on a pass.

Retention is the second lever. Hold it until the end of the defects period, and state its amount as a number, not as "reasonable". Set it above the likely cost of the commonest early defects, such as loose terminations, inverter faults and mounting corrosion. A public-works benchmark is the 2.5% security deposit above; private contracts vary. Our notes on payment terms and retention and retention disputes apply directly. If your contractor is a micro or small enterprise, the statutory 45-day rule for paying registered MSME suppliers also bites; see the MSME 45-day rule.

What are the red flags in a proposed schedule?

  • A large advance with no bank guarantee.
  • Payment on invoice date or on dispatch, not on delivery at site.
  • No definition of "commissioning", or one that depends on a third party's action.
  • No performance ratio test, or a test the contractor runs and reports alone.
  • Retention released at handover, or no retention at all.
  • A final instalment smaller than the cost of rectifying a likely defect.

How Secured Engineers helps

We design the plant in-house and file the CEIG and DISCOM net-metering applications ourselves, so the "ready for commissioning" and "commissioned" steps sit with one team. Solar and MEPF can be contracted together, which means one payment schedule instead of two. We work from offices in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients. Our guide to selecting a solar EPC contractor and our testing and commissioning page give more.

If you hold a draft solar EPC contract or a quotation, send it and we will read its payment schedule against the points above. Start from our solar EPC service, message us on WhatsApp, call +91 70099 85817, or ask for a free proposal.

Frequently asked

How much advance should I pay a solar EPC contractor?

No regulation sets a figure for a private contract, so it is a commercial term. Keep it modest, release it in instalments, and back it with a bank guarantee that reduces as the advance is recovered. As a public-works reference, PWD's 2023 conditions allow a mobilisation advance up to 10% of the tendered amount in instalments of up to 5%.

Should I pay when material reaches the site?

Yes, but pay for what is delivered, identified and protected. Ask for delivery challans, module and inverter serial numbers, covered storage and insurance cover, and let title pass to you on payment. Check the test certificates first. Paying on a pro-forma invoice before delivery leaves you exposed if the supplier fails.

What is a performance ratio test and why tie payment to it?

A performance ratio test compares the plant's measured output with what it should produce at the irradiance and temperature during the test. Tying the final payment to a passed test gives the contractor a reason to commission carefully. Fix the method, instruments, duration and fail remedy in the contract before work starts.

Who bears the risk if the DISCOM delays commissioning?

The contract must say. A fair structure has a separate milestone for completion of the contractor's work and filings, paid on that, with the commissioning instalment following. Without it, one side silently bears the delay. The date can also carry a regulatory consequence, as with the 31 December 2026 ALMM List-II window for net-metering projects.

How long should retention be held on a solar plant?

Until the end of the defects liability period, not until handover, and as a stated amount. The percentage is a commercial choice; a public-works reference is a 2.5% security deposit with a performance guarantee valid to completion plus six months. Set yours above the likely cost of common early defects.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it