Solar for Forging and Re-rolling Units: Sizing, Roof, Approvals and Payback (50 kW+)
A forging or steel re-rolling unit can use rooftop solar well, because furnaces, reheating and mill drives run through daylight shifts. The sizing limit is rarely roof area. It is the daytime base load your plant actually holds, your sanctioned load or contract demand, and the power quality on your bus. Size to the first two, survey the third, and check payback against the tariff you pay in solar hours.
Size the plant from the bill, in four steps
- Find the daytime share. Take interval data if your meter records it, or the shift pattern. A unit running one or two day shifts uses most of its energy while the sun is up. A three-shift unit with a heavy night furnace load uses less of a solar plant's output. Solar produces for roughly the middle eight hours of the day.
- Find the daytime base load. This is the load that is on even in the quietest daylight hour, not the average. A plant sized above it exports at those hours.
- Check headroom. Most DISCOMs cap rooftop capacity at or near the sanctioned load or contract demand, and some states set a lower percentage. Our sanctioned load calculator shows the ceiling before you design.
- Take the smallest of three numbers: daytime base load, headroom, and roof or land area at roughly 100 sq.ft per kW.
Then consider what changes in your plant over the next five years. Bureau of Energy Efficiency baseline audits of Ludhiana forging units assess replacing fuel-fired reheating furnaces with induction units. If you are considering that, remember that electrifying heat adds load, so decide that first and size solar to the new daytime load rather than the old one.
What is different about this sector
| Sector factor | What it does to a solar plant | What to do |
|---|---|---|
| Induction furnaces and heaters | Large, steady daytime load, but power-electronic converters inject harmonics | Harmonic survey before design; inverter and capacitor selection to suit |
| Rolling mill and press drives | Cyclic, sharp load swings; variable-speed drives add harmonics | Look at interval data for swings; check protection settings so inverters do not trip on voltage dips |
| Low power factor | Capacitor banks and detuned reactors already on the bus can interact with inverters | Review the PF correction scheme; see our power factor calculator |
| Weekly off and furnace relining | Load drops while the sun keeps shining; export or curtailment | Model the lowest-load Sunday; agree how the DISCOM settles export |
| Scale, dust and heat | Fuel-fired furnaces and chimneys soil modules; hot shops raise module temperature | Place arrays upwind and away from flue outlets; plan cleaning frequency |
| HT connection | Larger units are commonly on an 11 kV supply, in which case solar interconnects on the HT side | Protection coordination and the electrical inspector's approval |
| DG sets for outages | Solar must not back-feed a generator | Interlock changeover logic in the scope |
Power quality is the sector-specific risk
Induction heating and drives distort the supply. Harmonics, flicker and a poor power factor are not reasons to skip solar, but they must be measured. A power quality survey of the incoming supply, taken across a full production cycle, tells you the voltage and current distortion that the inverter will see, and whether the existing capacitor bank is likely to resonate. Without it, the usual symptoms are inverter trips, nuisance protection operation and complaints from the DISCOM. Ask the designer to state which standard the inverter's harmonic output complies with and how the plant is protected against grid distortion.
Roof or ground?
Forge shops and rolling mill sheds are tall, hot and often crowded with crane gantries, ridge vents and exhaust stacks. Check the sheeting age and the purlin capacity with the roof load calculator and a structural survey, and plan roof access away from furnace exhaust. Many units in industrial estates have open land inside the boundary. A ground-mount on that land avoids roof issues, though it uses land you may want for expansion; the plant area calculator gives the area. Keep cable routes and modules clear of hot work, flue gas outlets and scrap handling.
Which approval route applies by size?
| Plant size | Usual route | What to check |
|---|---|---|
| 50 kW to 100 kW | Rooftop net metering with the DISCOM | Sanctioned load, transformer headroom, whether your state requires an inspector's certificate at this size |
| 100 kW to 500 kW | Net metering, usually on the HT side at this size, with the electrical inspector's approval where your state requires it | The central rules allow net metering up to 500 kW or the sanctioned load, whichever is lower; states may set their own limits |
| Above 500 kW | Gross metering, behind-the-meter captive use, group captive or open access | State regulations decide; the economics depend on banking and wheeling rules |
Open access and captive routes follow national rules as well as state ones. The Green Energy Open Access Rules, 2022 lowered the open access threshold for green energy from 1 MW to 100 kW, with approval deemed granted if not decided in 15 days. The Electricity Rules, 2005 define a captive plant by ownership and consumption tests; the rule was amended in March 2026, so read the current text. Our open access guide compares the routes.
Payback: use the tariff that applies in solar hours
Our published benchmark for turnkey C&I rooftop solar is ₹24,000 to ₹32,000 per kW excluding GST. At 100 kW, the cost page shows ₹28 to ₹32 lakh; at 250 kW about ₹68 to ₹75 lakh; at 500 kW about ₹1.30 crore. Annual value is the units generated and used on site, multiplied by the energy charge you avoid, which is not the same as the average rate on your bill. Demand charges, fixed charges and taxes do not fall unit for unit with solar.
Check the time-of-day structure too. Under the 2023 amendment to the Electricity (Rights of Consumers) Rules, commercial and industrial consumers above 10 kW are on time-of-day tariffs, with a lower tariff during the solar hours your state commission sets. For a solar plant, the avoided cost is the solar-hour rate, so a unit generated at noon may be worth less than the bill's average. The solar calculator gives a first view; for a decision, ask for payback shown as scenarios by self-use share.
How Secured Engineers helps
We design in-house and take MEPF and solar under one contract, so the HT connection, protection and DG interlocks are designed with the solar plant. Fire NOC, CEIG and DISCOM net-metering applications are filed in-house. We work from offices in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients. We do not cite a specific forging or re-rolling client here. Start with your last twelve bills and your shift pattern.
See solar for factories for how we scope a plant. To discuss yours, WhatsApp us your bills, call +91 70099 85817, or ask for a free proposal.
Frequently asked
How big a solar plant should a forging unit install?
Take the smallest of three numbers: the daytime base load that is on even in the quietest daylight hour, the headroom allowed by your sanctioned load or contract demand under your DISCOM's rules, and the roof or land area at about 100 sq.ft per kW. Interval data or the shift pattern gives the first; the DISCOM gives the second.
Do induction furnaces cause problems for solar inverters?
They can. Induction heating and variable-speed drives inject harmonics and may create flicker, and capacitor banks can interact with them. A power quality survey across a production cycle shows what the inverters will face. It is a design input, not a reason to avoid solar; ask the designer how the plant is protected against grid distortion.
Can a steel re-rolling mill use net metering?
Yes, up to the limit in your state. The central rules allow net metering for loads up to 500 kW or the sanctioned load, whichever is lower, and states can set their own limits and percentages. Above that, gross metering, captive use or open access may apply. Confirm the current ceiling and banking rules with the DISCOM before fixing capacity.
Does solar reduce a forging unit's demand charge?
Not reliably. Solar cuts energy units, but demand charges are set by the highest interval of the month, which can fall on a cloudy day or outside sun hours. Treat solar as an energy saving, and check your interval data before assuming any change in recorded maximum demand.
How do I work out payback for a forging unit?
Divide the installed cost by the yearly value of units generated and used on site, at the energy charge you actually avoid, not the average bill rate. Time-of-day tariffs can make solar-hour units cheaper than average. Show payback as scenarios by self-use share, and include cleaning and maintenance in the running cost.
Related services
Related guides
- A Plant Down 8% Looks Exactly Like a Plant Working Fine.
- Three Vendors, One Roof, Three Different Generation Figures.
- Perovskite Cells Promise 30%+ Efficiency. Your Roof Doesn't Have Ten Years to Wait and See.
- Solar for Foundries: Sizing, Roof, Approvals and Payback (50 kW+)
- Solar for Injection Moulding Units: Sizing, Roof, Approvals and Payback (50 kW+)
- Solar for Paper and Packaging Plants: Sizing, Roof, Approvals and Payback (50 kW+)
Related on this site
- termShadow-Free Area
- termGross Metering
- termOpen Access (Solar)
- serviceMounting Structures & BOS (Solar EPC)
- serviceO&M & Performance (Solar EPC)
- calculatorSolar Roof Load Calculator
- calculatorSolar Water Pump Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guidePESO licence for diesel storage
- guideFactory licence and DISH approval
More on Solar & Renewables · all insights