Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

Solar for Forging and Re-rolling Units: Sizing, Roof, Approvals and Payback (50 kW+)

22 October 2026 · 5 min read · by

Title card reading 'Solar for forging and re-rolling units' with sizing, roof, approvals and payback beneath the heading.
Title card. Not a photograph of a Secured Engineers site.

A forging or steel re-rolling unit can use rooftop solar well, because furnaces, reheating and mill drives run through daylight shifts. The sizing limit is rarely roof area. It is the daytime base load your plant actually holds, your sanctioned load or contract demand, and the power quality on your bus. Size to the first two, survey the third, and check payback against the tariff you pay in solar hours.

Size the plant from the bill, in four steps

  1. Find the daytime share. Take interval data if your meter records it, or the shift pattern. A unit running one or two day shifts uses most of its energy while the sun is up. A three-shift unit with a heavy night furnace load uses less of a solar plant's output. Solar produces for roughly the middle eight hours of the day.
  2. Find the daytime base load. This is the load that is on even in the quietest daylight hour, not the average. A plant sized above it exports at those hours.
  3. Check headroom. Most DISCOMs cap rooftop capacity at or near the sanctioned load or contract demand, and some states set a lower percentage. Our sanctioned load calculator shows the ceiling before you design.
  4. Take the smallest of three numbers: daytime base load, headroom, and roof or land area at roughly 100 sq.ft per kW.

Then consider what changes in your plant over the next five years. Bureau of Energy Efficiency baseline audits of Ludhiana forging units assess replacing fuel-fired reheating furnaces with induction units. If you are considering that, remember that electrifying heat adds load, so decide that first and size solar to the new daytime load rather than the old one.

What is different about this sector

Sector factorWhat it does to a solar plantWhat to do
Induction furnaces and heatersLarge, steady daytime load, but power-electronic converters inject harmonicsHarmonic survey before design; inverter and capacitor selection to suit
Rolling mill and press drivesCyclic, sharp load swings; variable-speed drives add harmonicsLook at interval data for swings; check protection settings so inverters do not trip on voltage dips
Low power factorCapacitor banks and detuned reactors already on the bus can interact with invertersReview the PF correction scheme; see our power factor calculator
Weekly off and furnace reliningLoad drops while the sun keeps shining; export or curtailmentModel the lowest-load Sunday; agree how the DISCOM settles export
Scale, dust and heatFuel-fired furnaces and chimneys soil modules; hot shops raise module temperaturePlace arrays upwind and away from flue outlets; plan cleaning frequency
HT connectionLarger units are commonly on an 11 kV supply, in which case solar interconnects on the HT sideProtection coordination and the electrical inspector's approval
DG sets for outagesSolar must not back-feed a generatorInterlock changeover logic in the scope

Power quality is the sector-specific risk

Induction heating and drives distort the supply. Harmonics, flicker and a poor power factor are not reasons to skip solar, but they must be measured. A power quality survey of the incoming supply, taken across a full production cycle, tells you the voltage and current distortion that the inverter will see, and whether the existing capacitor bank is likely to resonate. Without it, the usual symptoms are inverter trips, nuisance protection operation and complaints from the DISCOM. Ask the designer to state which standard the inverter's harmonic output complies with and how the plant is protected against grid distortion.

Roof or ground?

Forge shops and rolling mill sheds are tall, hot and often crowded with crane gantries, ridge vents and exhaust stacks. Check the sheeting age and the purlin capacity with the roof load calculator and a structural survey, and plan roof access away from furnace exhaust. Many units in industrial estates have open land inside the boundary. A ground-mount on that land avoids roof issues, though it uses land you may want for expansion; the plant area calculator gives the area. Keep cable routes and modules clear of hot work, flue gas outlets and scrap handling.

Which approval route applies by size?

Plant sizeUsual routeWhat to check
50 kW to 100 kWRooftop net metering with the DISCOMSanctioned load, transformer headroom, whether your state requires an inspector's certificate at this size
100 kW to 500 kWNet metering, usually on the HT side at this size, with the electrical inspector's approval where your state requires itThe central rules allow net metering up to 500 kW or the sanctioned load, whichever is lower; states may set their own limits
Above 500 kWGross metering, behind-the-meter captive use, group captive or open accessState regulations decide; the economics depend on banking and wheeling rules

Open access and captive routes follow national rules as well as state ones. The Green Energy Open Access Rules, 2022 lowered the open access threshold for green energy from 1 MW to 100 kW, with approval deemed granted if not decided in 15 days. The Electricity Rules, 2005 define a captive plant by ownership and consumption tests; the rule was amended in March 2026, so read the current text. Our open access guide compares the routes.

Payback: use the tariff that applies in solar hours

Our published benchmark for turnkey C&I rooftop solar is ₹24,000 to ₹32,000 per kW excluding GST. At 100 kW, the cost page shows ₹28 to ₹32 lakh; at 250 kW about ₹68 to ₹75 lakh; at 500 kW about ₹1.30 crore. Annual value is the units generated and used on site, multiplied by the energy charge you avoid, which is not the same as the average rate on your bill. Demand charges, fixed charges and taxes do not fall unit for unit with solar.

Check the time-of-day structure too. Under the 2023 amendment to the Electricity (Rights of Consumers) Rules, commercial and industrial consumers above 10 kW are on time-of-day tariffs, with a lower tariff during the solar hours your state commission sets. For a solar plant, the avoided cost is the solar-hour rate, so a unit generated at noon may be worth less than the bill's average. The solar calculator gives a first view; for a decision, ask for payback shown as scenarios by self-use share.

How Secured Engineers helps

We design in-house and take MEPF and solar under one contract, so the HT connection, protection and DG interlocks are designed with the solar plant. Fire NOC, CEIG and DISCOM net-metering applications are filed in-house. We work from offices in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients. We do not cite a specific forging or re-rolling client here. Start with your last twelve bills and your shift pattern.

See solar for factories for how we scope a plant. To discuss yours, WhatsApp us your bills, call +91 70099 85817, or ask for a free proposal.

Frequently asked

How big a solar plant should a forging unit install?

Take the smallest of three numbers: the daytime base load that is on even in the quietest daylight hour, the headroom allowed by your sanctioned load or contract demand under your DISCOM's rules, and the roof or land area at about 100 sq.ft per kW. Interval data or the shift pattern gives the first; the DISCOM gives the second.

Do induction furnaces cause problems for solar inverters?

They can. Induction heating and variable-speed drives inject harmonics and may create flicker, and capacitor banks can interact with them. A power quality survey across a production cycle shows what the inverters will face. It is a design input, not a reason to avoid solar; ask the designer how the plant is protected against grid distortion.

Can a steel re-rolling mill use net metering?

Yes, up to the limit in your state. The central rules allow net metering for loads up to 500 kW or the sanctioned load, whichever is lower, and states can set their own limits and percentages. Above that, gross metering, captive use or open access may apply. Confirm the current ceiling and banking rules with the DISCOM before fixing capacity.

Does solar reduce a forging unit's demand charge?

Not reliably. Solar cuts energy units, but demand charges are set by the highest interval of the month, which can fall on a cloudy day or outside sun hours. Treat solar as an energy saving, and check your interval data before assuming any change in recorded maximum demand.

How do I work out payback for a forging unit?

Divide the installed cost by the yearly value of units generated and used on site, at the energy charge you actually avoid, not the average bill rate. Time-of-day tariffs can make solar-hour units cheaper than average. Show payback as scenarios by self-use share, and include cleaning and maintenance in the running cost.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it