Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

Solar EPC Company for Factories in Goa: Electricity Department Rules, Approvals and Cost

22 October 2026 · 5 min read · by

Title card reading Solar EPC for Factories in Goa, with an industrial shed roof covered in solar modules drawn in outline.
Title card. Not a photograph of a Secured Engineers site.

A factory in Goa can net-meter solar up to 500 kWp at one premise, never above its sanctioned load or contract demand, under the JERC regulations for Goa and the Union Territories as amended in 2024. Larger projects fall under net billing, where exports earn the Commission's feed-in tariff. Our turnkey benchmark is ₹24,000–32,000 per kW excluding GST.

Which metering route can a Goa factory use?

Goa's electricity is supplied by the state Electricity Department and regulated by the Joint Electricity Regulatory Commission (JERC) for Goa and the Union Territories. The base text is the JERC Solar PV Grid Interactive System based on Net Metering Regulations, 2019, changed by a first amendment in 2024 that added gross metering and net billing. The department's own website still lists an older 2018 net metering document and a 2017 solar policy, so work from the Commission's text, not from old downloads. Press reports in 2025 described further changes; we could not retrieve a notified text for them, so ask the department whether anything has been amended since 2024.

RouteSize limitHow export is treatedPoints to note
Net meteringUp to 500 kWp at one premise, and within sanctioned load or contract demandExports offset imports in kWh at the retail tariffTime-of-day capable net meter for ToD consumers; check meter mandatory above 20 kW
Net billing or net feed-inProjects above 500 kWpImports valued at retail tariff, exports at the Commission's feed-in tariff, netted in rupeesTime-of-day tariffs may be introduced to encourage storage
Gross meteringEligible consumers or generators who sell all outputEntire output sold to the licensee under a power purchase agreement at the feed-in tariffConsumption is billed separately
Third-party ownedSame limits as the route chosenConsumer pays the developer an agreed tariffExempt from open access restrictions; the licensee records the contract
Group or virtual net meteringUp to 500 kWp or sanctioned load, whichever is lowerCredits shared across connections or participantsGroup metering for all consumers; virtual metering limited to named categories in the 2019 text

The practical lesson is to size the plant to your own load. Net metering rewards consumption on site at the retail tariff, while exports above the net-metering ceiling are valued at the feed-in tariff, so a plant much larger than daytime demand loses its economic edge. Our guide to open access solar covers the alternative for larger loads. The regulations also cap solar on a distribution transformer at 75 percent of its capacity unless the licensee's load study allows more, which makes the transformer the first thing to check.

A worked case shows the edge. Take a factory with an 800 kVA contract demand and roof for 700 kWp. The demand does not stop the plant, but 700 kWp is above the 500 kWp net metering ceiling, and the amendment places a project higher than 500 kWp under net billing or net feed-in. The choice is then between staying at or below 500 kWp to keep retail-rate offset, or accepting feed-in valuation on exports. Ask the department in writing how it treats two plants at one premise before you rely on a split, because the text does not answer that.

What does the approval path look like?

  1. Apply to the Electricity Department for connectivity with the one-time registration fee, which the 2019 text puts at ₹500 unless the Commission has since changed it. Applications are to be handled through a web-based system.
  2. Technical feasibility: for rooftop solar the study must be completed and communicated within fifteen days, otherwise feasibility is presumed. Rooftop applications up to 10 kW, complete in all respects, are deemed accepted without a study.
  3. Build the plant to the inverter, harmonics and protection standards in the regulations' annexure, with the metering the department specifies. Our note on solar inverters shows what we check for.
  4. Inspection and connection: the department tests and connects. Plants above 500 kWp are to be checked by the Chief Electrical Inspector associated with the licensee. The department's website lists an Electrical Inspectorate section with procedures and forms, including NOC for commissioning of HT units, so confirm the forms for your voltage level.
  5. Sign the connection agreement and start net metering. Solar projects installed under the regulations are exempt from banking charges.

What does the cost band mean at 100 kW, 500 kW and 1 MW?

Our published band for turnkey commercial and industrial rooftop solar is ₹24,000–32,000 per kW excluding GST, covering modules, inverters, structure, cabling, earthing, protection, installation, commissioning and the DISCOM paperwork. On our size pages that works out at about ₹28–32 lakh for 100 kW, about ₹1.30 crore for 500 kW, and ₹2.40–2.60 crore for 1 MW, all before GST. Goa adds three cost items to read in a quote: structure and fixing designed for coastal air and monsoon wind, any HT interface work, and, above 500 kWp, the metering and agreement structure for net billing. Run your own load and tariff through the solar calculator before you compare bids.

Where do Goa's factory roofs sit?

The Goa government's industrial development corporation lists 22 industrial estates in its directory. The names we could read include Verna, Corlim, Cuncolim, Madkaim, Kundaim, Pilerne, Mapusa, Margao, Sancoale, Tivim, Tuem, Bethora, Shiroda, Panchwadi, Bicholim, Honda, Pissurlem, Latambarcem, Colvale, Canacona and Kakoda. Many plots in such estates are leased rather than freehold, so check the lease terms on roof modifications and the landlord's consent before design starts. The directory we used is from 2020 and may have changed.

What should you confirm with the Electricity Department?

  • The latest notified regulation text and amendment, not a news summary.
  • Your sanctioned load or contract demand, since it caps plant size.
  • Transformer headroom against the 75 percent rule.
  • Whether your tariff category is on time-of-day billing, which affects the meter and the settlement.
  • The inspector's requirements for your voltage level, and any fees.
  • Whether the plant will be self-owned or third-party owned, because ownership decides who services it and who claims the tax depreciation.
  • Monsoon generation in your estate, which the calculator estimates from location but a site study confirms.

How Secured Engineers helps

We are a pan-India EPC contractor. Design is done in-house, and Fire NOC, CEIG and DISCOM net-metering filings are prepared in-house, with MEPF and solar available under one contract. We work from offices in Noida (Delhi NCR) and Ludhiana, across 535+ projects in 18+ states, with 89.77% repeat clients. Goa is not among our published project locations, so a Goa job would be a mobilisation from those offices, with the site-team arrangement agreed in writing before award.

To test your own numbers, read the solar EPC service page, then message us on WhatsApp, call +91 70099 85817, or request a free proposal with your sanctioned load, roof area and tariff.

Frequently asked

What is the largest solar plant a Goa factory can net-meter?

Under the JERC regulations as amended in 2024, net metering covers projects up to 500 kWp at one premise, and the plant also cannot exceed the consumer's sanctioned load or contract demand. Above 500 kWp the project falls under net billing or net feed-in, where exports are paid at the Commission's feed-in tariff rather than netted at the retail tariff.

Can a Goa factory lease its roof to a developer?

Yes. The regulations allow third-party ownership: the consumer leases or rents the roof or land to a project developer, pays an agreed tariff for the energy, and the net metering provisions apply to that project. Such projects are exempt from open access restrictions and charges. The commercial contract stays between the two parties, and the licensee records it but does not take a role in it.

Is a check meter needed?

Check meters are mandatory for solar projects larger than 20 kW and optional at or below that size, according to the 2019 regulations. The Electricity Department tests and maintains the metering. The consumer bears the cost of a check meter. A solar energy meter at the generation point is also part of the arrangement, so allow for both in the specification.

How long does Goa take to confirm technical feasibility?

The 2024 amendment says the technical feasibility study for rooftop solar must be completed and communicated within fifteen days, failing which the proposal is presumed technically feasible. Rooftop applications up to 10 kW that are complete in all respects are deemed accepted without a study. Larger factory plants should still expect a transformer-level check, since solar on a distribution transformer is normally capped at 75 percent of its capacity unless a load study allows more.

Does Secured Engineers have solar projects in Goa?

No Goa project is listed on this website. We work from offices in Noida and Ludhiana, prepare DISCOM and net-metering filings in-house and mobilise to site, so ask for references from comparable plants and a written scope split between our team and any local partner. Treat claims from any contractor the same way.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it