Solar EPC for Factories in Telangana: DISCOM Rules, Approvals and Cost
A Telangana factory planning 50 kW or more of rooftop solar mostly deals with one rulebook: the Telangana Electricity Regulatory Commission's Rooftop Solar PV Grid Interactive Systems Regulation, 2025, applied by the two state DISCOMs (TGSPDCL and TGNPDCL). Net metering is capped at 500 kWp, gross metering at 1 MWp, and capacity is capped at 80% of sanctioned load or contracted demand.
Which rulebook governs a factory rooftop in Telangana?
The Commission notified the Rooftop Solar PV Grid Interactive Systems Regulation as Regulation 1 of 2025 in the Telangana Gazette Extraordinary of 15 November 2025. It repealed the 2016 net metering regulation (No. 6 of 2016). It applies to the distribution licensees, to eligible consumers and to third-party owners of rooftop systems, which matters if you want a leased or RESCO-style plant.
The licensees are the Telangana Southern Power Distribution Company (TGSPDCL) and the Northern Power Distribution Company (TGNPDCL). Which one supplies you is printed on your electricity bill. Application forms, the connection agreement and the online portal are hosted by the DISCOM. The Commission's regulation list and the DISCOM portals are where you should confirm the current text, because regulations are amended; this article reflects the gazette text of November 2025.
Net metering, gross metering or open access: which route and what cap?
| Route | Capacity limit in the 2025 regulation | What it means for a factory |
|---|---|---|
| Net metering | Up to 500 kWp; existing prosumers already above 500 kWp continue | Solar offsets your own consumption first. Monthly surplus is settled at a rate the Commission notifies, linked to the lowest Section 63 solar tariff the Telangana DISCOMs discovered in the preceding financial year, not at your retail tariff |
| Gross metering | Up to 1 MWp | Used when you want to go above 500 kWp on the rooftop. Net metering and gross metering cannot be combined on the same connection |
| Virtual net metering | Below 100 kWp (group net metering is limited to domestic and township categories) | Rarely relevant to a single factory; it serves several connections |
| Open access, alongside rooftop | Rooftop capacity plus open access capacity must not exceed contracted maximum demand or contracted load | Permitted under the TGERC open access regulation of 2024. Check wheeling and cross-subsidy charges before assuming a saving |
For industrial and commercial consumers, rooftop capacity is limited to 80% of sanctioned load or contracted demand. A 500 kWp plant therefore needs a sanction of at least 625 on the same unit basis. The regulation says "sanctioned load/contracted demand" without spelling out how a kVA contract demand converts to kWp, so ask your DISCOM which basis it applies. Our sanctioned load calculator shows the headroom before you size anything.
Two more limits can stop a good plan. Total rooftop solar on an LT distribution transformer is limited to 50% of its rated capacity, and on an 11 kV or 33 kV feeder to 50% of the feeder's permitted load or of the substation capacity. The licensee must publish available capacity on its website and update it quarterly, so check it before you commission drawings.
What does the approval sequence look like?
- Application: filed with the Assistant Divisional Engineer (Operations) for LT consumers and the Divisional Engineer (Operations) for HT consumers, with the form and processing fee set out in the regulation (₹2,500 for LT, ₹15,000 for HT at the time of the 2025 notification).
- Acknowledgement: within seven working days, with any deficiencies listed.
- Feasibility: the licensee assesses the transformer or feeder within 15 working days. An application not acted on in that time is deemed approved. The feasibility stays valid for four months unless extended.
- Estimate: if network strengthening is needed, you pay the estimate within 15 days or the application is cancelled.
- Connection agreement: within 15 days of approval.
- Safety certification: above 56 kWp the Chief Electrical Inspector to the Government (CEIG) must certify protection and safety, within 15 working days of receiving the information. Up to 56 kWp, the consumer inspects and self-certifies. Our CEIG guide covers the file.
- Commissioning: after you submit the installation certificate, the licensee must sign the agreement, fit the meter and commission within 15 days.
Plants above 56 kWp may connect to the 11 kV or 33 kV feeder serving the consumer. The regulation also references the Central Electricity Authority connectivity standards for distributed generation and the CEA safety regulations. Timelines in a regulation are targets the licensee must meet; real files lose time on deficiency letters, so submit a complete application the first time.
What does a plant cost at 100 kW, 500 kW and 1 MW?
Our published benchmark for turnkey C&I rooftop solar is ₹24,000 to ₹32,000 per kW, excluding GST, and it falls as plants get larger. At 100 kW the band on our 100 kW cost page is ₹28,000 to ₹32,000 per kW. At 500 kW it is about ₹26,000 per kW, roughly ₹1.30 crore (see 500 kW). At 1 MW it is ₹24,000 to ₹26,000 per kW, or ₹2.40 to ₹2.60 crore (see 1 MW). These are indicative, ex-GST, rooftop figures. They exclude HT-side works where needed, roof strengthening, batteries and statutory fees.
In Telangana the figures that move the economics most are not the module price. They are the surplus settlement rule (net metering rewards self-consumption, so size to your daytime load), whether your sanctioned load allows the size you want, and whether HT works are needed at 500 kW and above. Run your bill through the solar calculator for a first view, then ask for a load-profile based design.
Where do the factories sit, and what does the roof need?
Telangana's industrial parks are developed and managed by the Telangana Industrial Infrastructure Corporation (TGIIC), which publishes its list of industrial areas and park-wise vacant plots; many other factories sit in private estates. Whichever applies, the roof question is the same: structure, orientation, shadow-free area and the age of the sheeting. Confirm roof rights with the landlord or industrial area authority if you do not own the building outright.
One national rule affects module selection. MNRE's office memorandum of 4 August 2026 says net-metering projects, which it defines to include gross metering, are exempt from the cell-list (ALMM List-II) requirement only if commissioned by 31 December 2026. The module list (List-I) still applies. Behind-the-meter plants used only for captive consumption by private consumers are outside both lists. Your EPC contractor must tell you which category your plant falls in, and the date you can realistically commission.
How Secured Engineers helps
This is a buyer's guide, and it cites no Telangana project of ours. We are a pan-India EPC contractor that mobilises from our offices in Noida (Delhi NCR) and Ludhiana. We design in-house, file Fire NOC, CEIG and DISCOM net-metering applications in-house, and take MEPF and solar under one contract. Our record is 535+ projects across 18+ states with 89.77% repeat clients. For a Telangana plant, we would start with your last twelve bills, your sanctioned load and the transformer or feeder headroom, then tell you which route and size make sense.
See our solar EPC service for scope, or send us your bills on WhatsApp, call +91 70099 85817, or request a free proposal.
Frequently asked
What is the net metering limit for a factory in Telangana?
Under TGERC Regulation 1 of 2025, eligible consumers can install net-metered rooftop solar up to 500 kWp, and industrial or commercial capacity is also limited to 80% of sanctioned load or contracted demand. Prosumers who already had more than 500 kWp under net metering keep it. Above 500 kWp, gross metering up to 1 MWp is the rooftop route.
Do I need CEIG approval for rooftop solar in Telangana?
For rooftop systems above 56 kWp the regulation requires the Chief Electrical Inspector to the Government to test and certify safety and protection, within 15 working days of receiving the information. Systems up to 56 kWp are inspected, tested and self-certified by the consumer. Whether your plant also needs other inspections depends on its connection voltage, so confirm with the DISCOM.
Can a Telangana factory use rooftop solar and open access together?
The 2025 regulation allows consumers with net or gross metering to use open access under the TGERC open access regulation of 2024, provided the open access capacity plus the rooftop capacity does not exceed contracted maximum demand or contracted load. Wheeling and cross-subsidy charges still apply to the open access portion, so model them before relying on it.
How long does DISCOM approval take?
The regulation sets seven working days for acknowledgement, 15 working days for the feasibility assessment, with deemed approval if the licensee does not act, and 15 days to commission after the installation certificate. Network strengthening, deficiency letters and the CEIG visit add time, so treat the regulation as the minimum and plan a longer window.
Is the cost per kW the same in Telangana as elsewhere?
Our published band for turnkey C&I rooftop solar is ₹24,000 to ₹32,000 per kW, excluding GST, lower at larger sizes. Site factors, not the state, move it most: roof type, cable runs, HT works and the structure. We have not priced a Telangana site specifically, so treat the band as indicative until a design is done.
Related services
More insights
Elevate the Array, and the Land Underneath Doesn't Have to Sit Idle.
Large ground-mount captive or open-access solar plants use land that could otherwise stay in agricultural use. Agrivoltaic design — elevating and spacing the array so farming continues beneath it — is a real option for industrial buyers structuring these deals, with real structural cost and yield trade-offs, not a default.
Solar EnergyDCR vs non-DCR solar panels, and ALMM List-II: the 2026 commissioning guide