Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Calculator · Electrical · Operating cost

DG Running Cost per Unit Calculator

Put a rupee figure on every unit your diesel generator delivers. Enter the fuel you measured at your usual load, the kW delivered over the same run, your fuel price and the maintenance cost per running hour — then the hours it runs in a year, if you want the annual cost.

What this tool estimates

Your DG's running cost per kWh delivered — measured fuel at your fuel price plus maintenance that scales with running hours, divided by the kW delivered — and, if you give annual running hours, the running cost for the year.

What it cannot decide

  • What the set burns at a load you have not measured: fuel per unit changes with loading, so measure at the load you run.
  • The cost of owning standby — the set, room, panel and financing — which stays out of the per-unit figure on purpose.
  • Whether solar or a battery can take over DG hours: that depends on how the plant is designed to run alongside the set.
  • Whether the set's condition, fuel quality or maintenance practice is right.

Your inputs

Measured on your set
litres / hour

Litres used over a steady-load run (tank dip or flow meter) ÷ the hours run. The maker's figure at the same load is the fallback.

kW

kWh on the set's meter ÷ the same hours. Must be more than 0 — a set delivering nothing has no cost per unit.

Prices
₹ / litre

What you pay per litre delivered to site.

₹ / hour

Lube oil, filters, service visits and any overhaul reserve, ÷ running hours. Enter 0 to see fuel alone.

Year optional
hours / year

From the hour meter or log book. Leave blank if you only need the cost per unit.

Your inputs stay in this browser. Nothing is sent anywhere unless you choose to send a review request further down this page — and that shows you exactly what it would send first.

Result

Running cost per unit delivered —
Running cost per hour—
Fuel per unit—
Running cost for the year—
Units and fuel for the year—
Calculation steps
StepValue
Sensitivity: ₹ per kWh if the fuel price or the measured fuel use is 10% lower or higher
Fuel priceFuel use −10%As measuredFuel use +10%

Standby capital cost — the set, its room and panel, financing — is not in these figures. It is the cost of having backup at all, and spreading it over the few hours a standby set runs would make the per-unit figure meaningless. Compare it separately.

Method version 6 October 2026. A screening estimate, not a design: see the limits below.

Comparing diesel with solar or a battery

This page no longer estimates a solar saving. A grid-connected solar plant must stop energising the network within two seconds of an unintended island — regulation 11(6)(e) of the CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations, 2013 — so a plain grid-tied plant shuts down when the grid fails. It is not backup, and it cannot carry the load during the outages your DG covers unless the plant is designed to run with the DG (a solar–DG controller that protects the set from reverse power and light loading) or with batteries.

For daytime running costs, the DG vs Solar calculator puts diesel and solar side by side per unit. How grid, DG and solar can share one bus safely is covered in the factory microgrid guide.

Method

How this calculator works — and where it stops

What it calculates

The running cost of a diesel generator per kWh delivered, from the fuel you measured at your load, your fuel price and the maintenance cost that scales with running hours — and, with annual running hours, the running cost for the year.

Inputs

  • Measured fuel consumption, litres per hour — litres used over a steady-load run (tank dip or flow meter) ÷ the hours run, at the load the set normally carries.
  • Net power delivered over the same run, kW — the set's kWh meter ÷ the same hours. Zero is refused.
  • Fuel price, ₹ per litre delivered to site.
  • Variable maintenance, ₹ per running hour — lube oil, filters, service visits and any overhaul reserve ÷ running hours. Zero is allowed.
  • Running hours a year (optional) — blank means no annual figure, not zero.

Method

  1. Fuel cost per hour = litres per hour × ₹ per litre.
  2. Running cost per hour = fuel cost per hour + maintenance per hour.
  3. Running cost per unit (₹/kWh) = running cost per hour ÷ net kW delivered.
  4. Fuel per unit = litres per hour ÷ kW, shown with its inverse in kWh per litre for comparison with the maker's figure at the same load.
  5. For the year: running cost = running cost per hour × running hours; units = kW × hours; fuel = litres per hour × hours.
  6. Sensitivity: the cost per unit with the fuel price and the measured fuel use each 10% lower and higher — nine cases.

Assumptions

  • The measured run represents how the set normally runs. Fuel per unit changes with loading — engine makers publish fuel consumption against percentage load — so a run at one load says nothing about another.
  • The kW is the average electrical output over the same period as the fuel measurement.
  • Maintenance entered per hour is the part that scales with running. A fixed yearly contract that does not depend on hours belongs with the cost of standby.
  • Standby capital cost — the set, room, panel and financing — stays out of the per-unit figure: spread over the few hours a standby set runs, it would make the figure depend on how rarely the set runs.

Limitations

  • No universal litres-per-kWh figure is used or offered as a default: a set that has not been measured has no answer here.
  • Does not model part-load fuel curves, start-up and cool-down fuel, fuel losses or the tax treatment of fuel.
  • Does not compare with grid or solar units. A grid-tied solar plant stops in a grid outage (CEA 2013 connectivity regulations, regulation 11(6)(e)), so it cannot carry the outage load a DG covers unless the plant is designed to run with the DG or with batteries. The DG vs Solar calculator compares daytime running costs.
  • Does not assess emission norms or any restriction on running the set.

Worked example

Produced by running this calculator with the inputs below.

Inputs

  • Measured fuel 25 litres per hour at the usual load
  • Net power delivered 100 kW over the same run
  • Fuel price ₹90 per litre
  • Variable maintenance ₹250 per running hour
  • Running hours 500 a year

Working

  1. Fuel cost per hour = 25 × ₹90 = ₹2,250.
  2. Running cost per hour = ₹2,250 + ₹250 = ₹2,500.
  3. Cost per unit = ₹2,500 ÷ 100 kW = ₹25 per kWh — fuel ₹22.50 and maintenance ₹2.50.
  4. Fuel per unit = 25 ÷ 100 = 0.25 litres per kWh, or 4 kWh per litre.
  5. Running cost for the year = ₹2,500 × 500 hours = ₹12.5 lakh, for 50,000 kWh and 12,500 litres.

Result. ₹25 per kWh delivered and ₹12.5 lakh a year in running cost at 500 hours — with the capital cost of the set kept separate.

Sensitivity — what moves the answer

  • Fuel dominates: here fuel is ₹22.50 of the ₹25 per kWh, so a 10% change in the fuel price moves the cost per unit by ₹2.25 — to ₹22.75 or ₹27.25.
  • Fuel use moves it the same way: 10% more litres per hour for the same output gives ₹27.25 per kWh, and 10% more on both price and use gives ₹29.73.
  • Output matters as much as fuel: the same 25 litres per hour delivering 80 kW instead of 100 kW costs ₹31.25 per kWh — which is why fuel must be measured at the load the set actually runs.

How engineers use the result

To put a defensible rupee figure on each DG hour and unit before deciding on load segregation, maintenance, a solar–DG controller or storage — and to compare a set's measured fuel per unit with its maker's figure at the same load.

When a professional design must replace it

Before the figure is used to justify an investment: an engineer should check how the fuel and kWh were measured (instrument, duration, steady load), whether that load is representative of the year, the maintenance cost basis, and — for any solar or battery alternative — whether the plant can actually run alongside the DG.

Sources

An engineer in a hard hat checks a tablet chart in a generator room beside a wall diagram linking a fuel icon, a generator and icons for hours, output and cost, with a diesel generator set and control panels behind.
Concept illustration made for this page with an AI image tool — not a photograph of a Secured Engineers project.

Questions people ask before using it

What information do I need before using the DG running cost calculator?

Fuel used over a steady-load run, by tank dip or a fuel flow meter, divided by the hours run; the kWh the set's meter recorded over the same run, divided by the same hours, for the average kW delivered; what you pay per litre of fuel delivered to site; the costs that scale with running hours — lube oil, filters, service visits and any overhaul reserve — divided by hours; and, for the annual figure, the running hours from the hour meter or log book. This is the same measurement BEE's guide book uses to assess a DG set: a two-hour steady-load trial with fuel and kWh logged every fifteen minutes.

Which site conditions could change the cost per unit?

Loading first: engine makers publish fuel consumption against percentage load, and a set run well below its best operating point — idling on a small night load, say — burns more fuel for each unit than the same set loaded near that point. Then the fuel price and quality, the set's condition (injectors, filters, turbocharger), hot or dusty intake air, unbalanced or harmonic-rich loads, and frequent short runs with starts and cool-downs. Measuring at the load you actually run captures most of this; one litres-per-kWh figure applied to every set does not.

What should I send an engineer for a project-specific review?

The DG log book with hour-meter, kWh-meter and fuel-fill entries; fuel bills; maintenance or AMC invoices; the set's datasheet with its fuel-consumption figures at part load; the single-line diagram showing what the DG feeds and where the changeover sits; and recent electricity bills or demand records, so the hours the DG runs can be set against what the grid supplied.

Optional: ask an engineer to look at it

The result above is yours with no form. If you want an engineer to check it against your drawings, schedules or bills, send a request. Nothing is sent until you press the button.

Exactly what this request will send
{}

Added automatically: this page's address, the tool name, the time, a reference number, the pages you opened on this site in this visit, how you arrived (landing page, referring site and any campaign tags) and your device type (touch or pointer, narrow or wide screen). Nothing else.

Prefer to talk? WhatsApp or the contact form.

One of 56 free MEPF and solar calculators on this site. Every input term is defined in the engineering glossary; the specification libraries, clearance guides and checklists for design teams are in the architects' section.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Verify my numbers