Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh TEDx talk, books & interviews
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics EV Charging Infrastructure
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Submit RFQ Get a Free Quote
EV Charging

EV charging EPC tender checklist: BOQ, OEM scope and handover

7 November 2026 · 6 min read · by

EV site model, electrical enclosure, cable tray sample and tender folders arranged on an engineering meeting table.

A useful EV charging tender defines a working outcome and assigns every interface. “Supply and install chargers” leaves too much unresolved when the meter, transformer, civil contractor, OEM and software provider belong to different parties. Give bidders one site brief, one output requirement and one acceptance schedule.

This checklist is for factories, property owners, fleets, CPOs and OEMs procuring installation or rollout work. It helps make bids comparable; the final BOQ and specification still need project engineering and current authority requirements.

Issue the same technical baseline to every bidder

Include the site plan, electricity bill and sanctioned load, existing SLD, available demand data, proposed vehicle list and charging schedule, survey access, shutdown restrictions, target expansion and known authority conditions. Where drawings or measurements are missing, require a survey assumption register and identify who closes it.

Tender itemRequire a bidder responseAcceptance evidence
Energy serviceVehicles, delivered energy, dwell windows and simultaneous charging assumptionsAgreed schedule and representative session demonstration
EquipmentExact model, firmware, connectors, shared output, input characteristics and environment limitsSerial register, datasheets and applicable model test documentation
Electrical worksPoint of supply, design calculations, panels, protection, cables, containment and earthingApproved/as-built drawings and signed test records
Civil worksFoundation, trench, reinstatement, drainage, barriers and bay markingsInspection records and dimensional/site checks
Utility and inspectionApplicant, submissions, fees, deposits, utility work and release dependenciesRequired approvals and energisation records
SoftwareCMS, connectivity, permissions, payments, local control and data exportFunctional test results and owner access
SupportDefect liability, OEM warranty, preventive work, spares and escalationWritten support matrix and handover acknowledgement

Make free-issue equipment an explicit package

If the CPO or OEM supplies chargers, identify the delivery point, unloading equipment, storage requirements, inspection for transport damage and custody transfer. Require final dimensions, weight, cable entries, foundations, input requirements and communication details before associated works are released.

State who attends first energisation, loads firmware, registers assets in the CMS and authorises warranty activation. Define responsibility when a charger fails acceptance because of an internal defect, an installation fault or a platform configuration. “OEM commissioning included” should name the activity, provider, travel allowance and required site readiness.

Separate design changes from quantity variations

Use a variation register with cause, drawing revision, quantity change, cost, programme effect and written approval. A changed cable route, a longer trench and a larger upstream supply are different events. Agree whether rates apply only to measured quantities or also to redesigned equipment. List exclusions where a purchaser can compare them directly rather than burying them in quotation footnotes.

Payment milestones should follow evidence: approved design, accepted delivery, installation readiness, successful acceptance and document handover. Retention and warranties are commercial terms to agree; they do not replace an inspection or demonstrate that the software works.

Check certificates against the supplied configuration

The national EVCI guidance, Annexures I and II, addresses charger standards and model-specific type-test evidence. Ask for the applicable standard edition and test scope for the exact model, power rating and communications configuration. Use the BIS standards resources to confirm current references; do not copy a superseded edition into a tender by habit.

For an OCPP claim, verify the official OCA certificate record and match the product, role, version and certified profiles. Protocol certification is separate from electrical product safety and from site acceptance. Membership of an industry body is not the same as certification of the offered model.

Run a bid clarification meeting with a closure log

Ask each bidder to identify deviations, missing information and dependencies. Close the same questions for all bidders and distribute material clarifications consistently. Evaluate delivered scope, design evidence, service boundaries and commercial terms alongside price. A low bid that excludes utility works cannot be compared directly with a complete upstream package.

For repeated CPO/OEM sites, standardise the survey form and acceptance pack while keeping site-specific load, ground conditions and authority requirements visible. The electrical infrastructure service provides the relevant supply-side context.

Share your BOQ / rollout tender Share the site location and your requirement with Secured Engineers. Electrical infrastructure, charger supply, software and ongoing support responsibilities are agreed in the project scope.

Continue planning your installation

Sources checked 7 November 2026. Confirm the applicable order, equipment revision and site conditions before procurement.

Related services

Request an EV Site Assessment

Tell us the building, the parking and the chargers you have in mind. We check the headroom your transformer and panels really have before anything is bought.

Add project details (optional — company, type, stage, timeline, size)

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Speak to a Lead Engineer