Solar for Warehouses and Logistics Parks: Sizing, Roof, Approvals and Payback (50 kW+)
A warehouse or logistics park suits a 50 kW+ solar plant mainly for its roof, not its own load. Most warehouses use little power, so a plant sized to the roof exports, and net metering stops paying beyond what the meter consumes. The workable routes are sizing to the landlord's load, putting the plant on tenant meters, or a shared route such as group captive or open access.
Why is a warehouse roof not the same as a factory roof?
A factory uses what its roof makes. A warehouse often has a large roof and a small load: lighting, dock equipment, offices, and fans or chillers in some buildings. The roof can host many times more than the meter can absorb. So the first question is not how many kW fit, but who will use the units.
Three limits apply together, and the smallest wins:
- Consumption. Under the Punjab and Haryana rooftop regulations of 2021, generation is capped at 90% of the consumer's consumption in the settlement period, and surplus beyond it earns nothing in net metering. A lightly used warehouse can hit this limit with a small plant.
- Sanctioned load. Punjab limits non-domestic rooftop AC capacity to 70% of sanctioned load or contract demand; Haryana allows net metering up to 500 kW or the sanctioned load, whichever is lower. Our sanctioned load calculator shows the headroom.
- Roof. Usable area after skylights, ridge vents, gutters and shade, and what the structure can bear.
Who uses the power in a landlord and tenant park?
In a logistics park the roof belongs to the landlord, while the power is bought by tenants on their own meters, often on short leases. A solar plant has a 20-plus year life, so the commercial structure decides more than the engineering. These are the usual routes.
| Route | Who signs with the DISCOM | Works when | Watch for |
|---|---|---|---|
| Landlord plant on the landlord's meter | Landlord | Common-area, pump, office or EV load is large enough | Small load caps the plant; the 90% rule |
| Tenant-owned plant on the tenant's roof | Tenant, as the consumer | Long lease, tenant has its own load, landlord consents | Roof licence, structural liability, lease term against payback |
| Third-party or RESCO plant on a tenant meter | Tenant, with a developer owning the plant | Tenant wants no capex; regulations allow third-party ownership | Tariff, term and buy-out; HERC and PSERC regulations contemplate third-party ownership |
| Group or virtual net metering | Participating consumers under one agreement | The state has notified the scheme and the connections share a DISCOM area | Not available everywhere; rules and charges vary |
| Group captive or open access | Consumers as owners and users, through the DISCOM and SLDC | Total load is large, 100 kW or more per connection or entity | Ownership and consumption tests, wheeling and other charges, longer approvals |
| Gross metering | Plant owner sells all output to the DISCOM | Roof is large and own load is tiny | Paid the commission-set tariff, not your retail rate |
HERC's 2021 regulations describe the third-party model: the developer leases the system and remains the owner of the equipment, the rooftop owner provides the roof, and generation meets the consumer's own needs with the excess exported under net metering. Group captive rules sit in Rule 3 of the Electricity Rules, 2005; the Ministry of Power amended them in March 2026 to clarify ownership, simplify group captive arrangements and set verification over the whole financial year. The Green Energy Open Access Rules, 2022 set the open-access threshold at 100 kW and a 15-day approval with deemed grant. Our guides to open-access solar and industrial solar EPC explain the off-site routes.
What is special about a PEB sheet roof?
Many warehouses are pre-engineered buildings with light metal sheeting on purlins, designed for a light load. Check four things before you quote.
- Load. The frame was designed for roof sheeting, not necessarily the weight of modules and structure plus wind uplift. Get the design loads from the PEB supplier or a structural engineer, and use the roof load calculator for a first check.
- Fixing. Clamp systems that grip the standing seam avoid roof penetrations; through-fixing needs sealed fasteners. Penetrations create leak paths over a 25-year life.
- Roof life. Sheeting that needs replacement in a few years should be replaced before the plant goes on, not after.
- Warranty. The sheet supplier's warranty may exclude damage from fixing, so ask early.
See our article on solar on a PEB sheet roof for more.
How do you size and judge the payback?
- Pull twelve months of bills for every meter that will use the plant: kWh, maximum demand, sanctioned load, and the tariff category.
- Find the daytime share. A warehouse operating one shift uses less than a cold store with compressors round the clock.
- Pick the route from the table, and size to the smallest of the consumption on the meters the route serves, the cap and the roof.
- Compute generation and the share used on site. Test it against the settlement-period rule.
- Compare simple payback across routes using the avoided tariff, including any Time of Day bands: the Ministry of Power's amendment of June 2023 puts solar-hour tariffs 10% to 20% below normal for commercial and industrial consumers with demand of 10 kW and above from 1 April 2024.
Our published C&I band is ₹24,000–32,000 per kW excluding GST; see the 500 kW and 1 MW pages. Roof type, structure, wind design, cable run and interconnection voltage move a price inside it. A park with a large roof and small load can find that a lower price per kW buys nothing if the units go unused. A battery can shift some daytime generation to evening use; see battery energy storage. Put your own numbers into the solar calculator before judging.
What risks are specific to warehouses?
- Fire. Warehouses carry high fire loads and racking. Cables, inverters and isolators must be laid out so that fire services can isolate the plant, and the Fire NOC drawings should show it. See Fire NOC for warehouses.
- Tenant turnover. A tenant who leaves takes the load. Contracts need a clause for what happens to credits and payments.
- Landlord liability. Roof leaks and structural damage need a named responsible party.
- Power sold on. If the landlord supplies solar power to tenants for a charge, check with the DISCOM and a lawyer whether that is allowed in your state before you write it into leases.
How Secured Engineers helps
We design the plant in-house and file the DISCOM net-metering application, and the Fire NOC and CEIG files where needed, ourselves. MEPF and solar can be carried under one contract, which suits a warehouse that needs electrical, fire fighting and ventilation as well. We work from offices in Noida (Delhi NCR) and Ludhiana, on 535+ projects across 18+ states, with 89.77% repeat clients. See our warehouse MEPF contractor page too.
If you send the roof drawings, the meter list and twelve months of bills, we will tell you which route and size the load and the rules support. Start at solar for factories and large sheds, then message us on WhatsApp, call +91 70099 85817, or ask for a free proposal.
Frequently asked
How much solar can a warehouse install under net metering?
Usually the smaller of the state's ceiling and its sanctioned-load rule, and in practice the plant is also limited by consumption. Punjab and Haryana cap net-metered generation at 90% of the consumer's consumption in the settlement period, so a lightly used warehouse hits the limit with a small plant. Check your state's current regulation, then size from twelve months of bills.
Can a landlord put solar on a roof for tenants to use?
It depends on the state. Tenants are the DISCOM's consumers, so the usual routes are a plant on each tenant's meter, a third-party plant under the state's rules, group or virtual net metering where the state has notified it, or captive and open access. Whether a landlord may sell solar power to tenants is a legal question to ask the DISCOM and a lawyer before drafting leases.
Is a PEB roof strong enough for solar panels?
It may be, but it was designed for light sheeting, so check the design loads with the PEB supplier or a structural engineer, including wind uplift. Standing-seam clamp systems avoid penetrations; through-fixing needs sealed fasteners. Replace sheeting that is near the end of its life before the plant goes on, and ask the sheet supplier whether fixing affects the warranty.
When does open access or group captive make sense for a logistics park?
When total load is large and the roof cannot serve the meters that use the power. The Green Energy Open Access Rules, 2022 set the threshold at 100 kW, with approval in 15 days or deemed grant. Group captive needs the ownership and consumption tests under Rule 3 of the Electricity Rules, 2005, which the Ministry of Power amended in March 2026. Expect wheeling charges and a longer process.
What does solar cost for a warehouse?
Our published band for C&I solar is ₹24,000–32,000 per kW excluding GST, with larger plants typically nearer the lower end. Roof type, structure and wind design, cable length, interconnection voltage and equipment make move the price inside it. The saving depends on how many units you use on site or can credit, which for a warehouse is usually the deciding variable.
Related services
Related guides
- A Plant Down 8% Looks Exactly Like a Plant Working Fine.
- Three Vendors, One Roof, Three Different Generation Figures.
- Perovskite Cells Promise 30%+ Efficiency. Your Roof Doesn't Have Ten Years to Wait and See.
- Your Factory Has a Reservoir, an ETP Pond, or a Cooling Tank. That's Roof Area You Haven't Counted.
- Elevate the Array, and the Land Underneath Doesn't Have to Sit Idle.
- Bifacial Panels Generate From Both Sides. On the Wrong Roof, the Second Side Generates Almost Nothing.
Related on this site
- termSolar EPC
- termModule Mounting Structure
- termOpen Access (Solar)
- serviceO&M & Performance (Solar EPC)
- serviceBattery / Hybrid Storage (Solar EPC)
- calculatorMEP Maintenance Budget Calculator
- calculatorSolar Carbon Offset Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guideCTE/CTO pollution consent
- guideEnvironmental clearance (EIA 2006)
More on Solar & Renewables · all insights