Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

CEIG Approval for a 1 MW Solar Plant: Drawings, Tests and the Inspection

22 October 2026 · 6 min read · by

Title card reading CEIG Approval for a 1 MW Solar Plant: Drawings, Tests and the Inspection.
Title card. Not a photograph of a Secured Engineers site.

A 1 MW solar plant almost always needs the state Electrical Inspector's approval before it is energised, because each state notifies the capacity above which a generating unit, renewable ones included, must be inspected, and 1 MW sits above every threshold we could read. You file drawings first, build to them, record the tests, and the inspector checks the plant and grants safety approval. Which officer decides, and on what capacity, varies by state.

When does a 1 MW plant need CEIG approval?

Regulation 34 of the CEA safety regulations 2023 leaves the capacity above which a generating unit must be inspected before commissioning to the state government's notification. Regulation 45 then says that every installation above the notified voltage, and the apparatus of generating units above that capacity, is inspected and tested by the Electrical Inspector before supply starts, and that the supplier may not commence supply until the Inspector's written approval is obtained. A 1 MW plant also brings an HT interconnection and usually a step-up transformer, so you are approving an electrical installation, not only a solar array.

One trap is the unit of capacity. A plant sold as "1 MW" may be 1,000 kW of inverter capacity with more DC capacity on the roof. Karnataka's March 2025 delegation notice counts rooftop solar in kWp, and its boundary sits exactly at 1,000 kWp, so the officer who decides could change with how the office counts. Ask which figure the office uses, and put that figure on the drawings.

How do the states differ?

StateWhat the published source saysWhat to confirm
Tamil NaduG.O. Ms. No. 98 (14 October 2024) notifies 10 kVA as the capacity above which generating units, renewable included, are inspected before commissioning; notified voltage 650 V; installations above 650 V inspected every two yearsHow the office counts the plant's capacity (inverter kVA or DC kWp) against the 10 kVA limit
KarnatakaMarch 2025 notification: rooftop solar drawings go to the Electrical Inspector up to 100 kWp, the Deputy Chief from 100 to 250 kWp, the Additional Chief for 251 to 1,000 kWp and the CEIG above 1,000 kWp. An older rooftop page says above 100 kWp goes to the CEIGWhich page the office follows, and whether it counts DC kWp or AC kW
GujaratSolar checklist: single-line diagram, equipment layout, earthing layout with standard earth pit, PV capacity and inverter calculation, GEDA sanction letter, key plan; a 30-day timeline notified under the RCPS Act (chart dated 2017)Current checklist, notified capacity and voltage
HaryanaRooftop regulation 2021: above 20 kWp the work completion report goes to the Directorate of Electrical Safety, which inspects and issues the safety certificate within seven days of submission; net metering is limited to 500 kW or sanctioned load, whichever is lowerWhich arrangement governs a 1 MW plant, since it exceeds the net-metering limit
Other statesNot read for this articleNotified capacity and voltage from the state Electrical Inspectorate

What goes into the drawing set?

Expect the single-line diagram to run from the modules through string combiners and inverters to the LT panel, step-up transformer, HT breaker or RMU and the DISCOM's metering point, with ratings, protection and the net-metering arrangement shown. Add an equipment layout with clearances, an earthing layout with the standard earth pit, the PV capacity and inverter calculation, and, where your state asks for it, the nodal agency's sanction letter. Karnataka's rooftop procedure also asks for the supply company's no-objection letter and, if the owner claims central subsidy, the nodal agency's no-objection.

Three details from the regulations should be visible on the drawings. For a transformer of 1,000 kVA and above, regulation 37 requires a circuit breaker on the primary side. At the same rating, regulation 47 requires a Buchholz relay, a pressure relief device and winding and oil temperature protection with alarm and trip contacts. And where two supplies are not meant to run in parallel, such as grid and DG, breakers must be interlocked against back-feed. Regulation 121(4) also asks for a fire detection and automatic suppression system as per relevant standards; our note on DC fire safety on rooftops covers what that means on a roof. State what is in the contractor's licence file as well: the licensed electrical contractor and supervisor have to be named and endorsed.

Which tests must be on record before inspection day?

Regulation 45(5) makes the owner test every circuit of an installation above the notified voltage before applying, record the results and submit them. Regulation 48 asks for the manufacturer's type, acceptance and routine test certificates when required, and site tests on apparatus above 650 V as per the relevant standards, and it lets the inspector ask for more. For a 1 MW plant that means:

  • earth resistance for each pit and for the combined system, since regulation 121(2) asks for adequate interconnected pits, welded not bolted;
  • insulation resistance of DC strings, LT cables and HT cable after laying;
  • transformer tests and relay trip tests against the settings on the drawing;
  • surge protection, earth-fault and insulation monitoring as listed in regulation 121(3);
  • interlock checks between grid, DG and solar;
  • calibration certificates for the instruments, because regulation 33 expects calibration by a government-authorised or NABL-accredited laboratory.

Our CEIG readiness calculator turns a list like this into a gap check.

What happens on inspection day, and where do files get returned?

Karnataka's published procedure is typical of what most inspectorates do. The completion report is signed by the licensed contractor and supervisor. At inspection, the owner's representative and the supervisor attend with licences, permits and test instruments. Defects are listed, rectified and reported back before approval. The department's flow chart also shows an observation-letter loop at the drawing stage, where the application is returned for answers and resubmission.

We have not found a published count of reasons for rejection, so treat the following as what the checklists test, not as statistics: drawings that differ from the built plant, missing earth readings, instruments without calibration certificates, licences not endorsed to the contractor, protection settings that do not match the relay schedule, and an unapproved addition. Regulation 45(6) also requires written approval or self-certification for any later addition or alteration before it is connected, so a 200 kW extension next year starts a new file. Periodic inspection then follows under regulation 32, at a period the state sets and never above five years.

How Secured Engineers helps

We design the plant in-house and file the Fire NOC, CEIG and DISCOM net-metering applications in-house, so the drawing set, the transformer specification and the protection schedule come from one team. MEPF and solar can be delivered under one contract, which helps where the plant ties into DG changeover and fire systems. We work from our Noida (Delhi NCR) and Ludhiana offices, across 535+ projects in 18+ states, with 89.77% repeat clients. For states outside our confirmed delivery list we mobilise from Noida and Ludhiana, and this article is a buyer's guide, not a promise about what a given inspectorate will approve.

To have your drawing set and test records reviewed before filing, see our CEIG approval consultancy, message us on WhatsApp, call +91 70099 85817, or ask for a free proposal for your plant.

Frequently asked

Is CEIG approval compulsory for a 1 MW solar plant?

Assume yes. Regulation 34 of the CEA 2023 regulations leaves the inspection threshold for generating units, renewables included, to each state, and the thresholds we could read are far below 1 MW: Tamil Nadu notifies 10 kVA, and Karnataka routes rooftop solar of every size to its offices by capacity. Confirm your state's notified capacity and voltage with its Electrical Inspectorate before you plan the schedule.

Does my plant go to the Chief Electrical Inspector himself?

It depends on the state and on how capacity is counted. Under Karnataka's March 2025 notification a plant up to 1,000 kWp goes to an Additional Chief Electrical Inspector and one above 1,000 kWp to the CEIG, so a 1 MW AC plant with extra DC capacity may land with the CEIG. Other states route to regional officers. Ask the office, and quote the same capacity on every drawing.

How long does approval take?

The published targets cover parts of the process only. Gujarat's chart gives 30 days for drawing approval, Karnataka's Seva Sindhu page lists 25 days at the head office and 20 at a field office, and Haryana's rooftop regulation asks for inspection within seven days of a complete work completion report. None includes your time to answer queries or rectify defects, so plan float around each stage.

Do I need fresh approval if I add capacity later?

Yes. Regulation 45(6) of the CEA 2023 regulations says an owner who makes any addition or alteration may not connect it to supply until it has been approved in writing by the Electrical Inspector or self-certified, as applicable. In Karnataka the department's notice says the periodical inspecting officer approves additions other than transformer and DG equipment. Plan the electrical room for expansion before the first drawing is filed.

Is CEIG approval the same as DISCOM approval?

No. The DISCOM decides technical feasibility, signs the interconnection agreement, tests and seals meters and synchronises the plant. The Electrical Inspector decides whether the installation is safe to energise. Both are needed. In Haryana's rooftop regulation the DISCOM synchronises only after the work completion report is verified and the inspection certificate is issued.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it