CEIG Approval in Andhra Pradesh: Process for Factories, DG Sets and Solar
CEIG approval in Andhra Pradesh means the state Electrical Inspectorate inspects an installation and approves it in writing before supply is given or restored. Which installations need that inspection depends on a voltage and a generating capacity that the state government notifies, and below them the owner self-certifies. Confirm the current limits with the Inspectorate before you fix an energisation date.
Who decides what needs inspection in Andhra Pradesh?
The national rule is Regulation 45 of the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023. An installation at or below the "notified voltage" is inspected, tested and self-certified by its owner before supply, with the report sent to the Electrical Inspector in the Schedule II forms. An installation above the notified voltage, and generating units above the capacity named under Regulation 34, are inspected by the Electrical Inspector before supply commences. The Regulations leave both numbers to each state. You can read them in the gazette copy of the Regulations.
Andhra Pradesh has used this power before. DISCOM-hosted copies of 2016 government orders indicate that G.O.Ms.No. 21 (9 June 2016) introduced self-certification for installations up to 11 kV, that G.O.Ms.No. 36 (1 November 2016) amended it, and that G.O.Ms.No. 38 (20 December 2016) extended the exemption from mandatory Chief Electrical Inspector inspection to 33 kV. Those orders were issued under the 2010 safety regulations that the 2023 Regulations replaced. We could not retrieve the notification now in force under the 2023 Regulations, so do not assume the 2016 figures still apply. Ask the Inspectorate which voltage and capacity limits it applies today, and get the answer in writing.
How does the approval fit into a factory project?
For a factory, CEIG is not a single event. It sits at the end of a chain that starts with the power sanction. The table sets out the stages and what each needs.
| Stage | What happens | What you prepare | Who acts |
|---|---|---|---|
| 1. Power sanction | The DISCOM sanctions the load and the HT or LT connection point | Load schedule, site plan, connection application | Owner and DISCOM |
| 2. Design freeze | Single-line diagram, sub-station layout, earthing, DG and solar interfaces fixed | Drawings with ratings and protection settings | Owner's designer |
| 3. Installation | Work done by a contractor licensed by the State Government, under a competent supervisor (Regulation 31) | Contractor licence, supervisor certificate, material approvals | Licensed contractor |
| 4. Testing | Every circuit tested; manufacturers' type, acceptance and routine certificates collected where required (Regulations 45(5) and 48) | Signed test sheets, calibration records | Contractor, owner |
| 5. Inspection or self-certification | Electrical Inspector inspects above the notified limits; owner files the Schedule II report below them | Application, drawings, test records, fee | Owner, Inspectorate |
| 6. Energisation | Supply commences only after written approval where inspection is needed; DISCOM then connects | Approval letter, DISCOM agreement | DISCOM |
| 7. Periodic renewal | Inspection or self-certification repeated at the government's directed interval, not exceeding five years (Regulation 32) | Maintenance and test history | Owner |
What changes when a factory adds a DG set or solar?
A DG set and a solar plant are generating units, so Regulation 34's capacity threshold applies to each of them separately from the HT intake. A factory could therefore have an HT sub-station inspected by the Inspector, a DG set self-certified and a solar plant inspected, or any other combination, depending on the state's limits and the equipment ratings.
Solar brings its own safety content. Regulation 121 asks for roof pathways at least 75 cm wide with hand rails, cables in trenches for ground-mounted plants, 1.8 m fencing on ground-mounted sites, a manual disconnection switch outside the AC combiner box, surge and lightning protection, earth-fault protection and insulation monitoring, and fire detection and suppression meeting the relevant standards. If your roof layout leaves no room for those pathways, the Inspector will notice, so settle them with the structural drawings, not at inspection. The rules for interconnection and metering are the DISCOM's; our note on solar with DG sets explains the interface design, and the DG inspection checklist covers what is looked at on the set itself.
What should the application file contain?
The Inspectorate publishes its own checklist, and you should follow it over any list here. In our experience of preparing these files in other states, the following are the items that are most often missing or inconsistent.
- Single-line diagram showing every transformer, breaker, DG set and solar inverter with ratings and settings, matching the equipment actually installed.
- Sub-station and DG room layouts with clearances, ventilation, fire protection and escape routes.
- Earthing layout and earth-resistance records, with the lightning protection design where it applies.
- Insulation-resistance, high-voltage withstand, protection-relay and interlock test sheets, signed and dated.
- Manufacturers' test certificates for transformers, HT switchgear and cables.
- Licences and certificates of the contractor and supervisor.
- The DISCOM sanction and any feasibility letter.
Our guide to the MEP drawing set shows how the same drawings serve Fire NOC, CEIG and DISCOM filings, and the CEIG factory approval page sets out the northern-state process we follow day to day.
How do you keep the energisation date from slipping?
Three habits protect the date. First, ask the DISCOM and the Inspectorate which of them needs to act first, since the order differs between projects and one is sometimes a precondition for the other. Second, finish testing early enough to leave time for observations: an Inspector who finds an unsigned test sheet or an undocumented relay setting will send the file back, and the clock restarts. Third, treat every later addition, such as a second transformer or a solar expansion, as a fresh approval. Regulation 45(6) bars connecting an addition or alteration until it has been approved or self-certified.
The CEIG readiness calculator turns these points into a checklist score for your project, and the glossary entry defines the terms used above.
How Secured Engineers helps
Secured Engineers designs the electrical system in-house and files CEIG approval, Fire NOC and DISCOM net-metering applications in-house, so the drawings, test records and approvals come from one team. MEPF and solar can be contracted together. We work from offices in Noida (Delhi NCR) and Ludhiana, and have delivered 535+ projects across 18+ states, with 89.77% repeat clients. For Andhra Pradesh we mobilise from Noida and Ludhiana; this article is a buyer's guide and does not describe work in the state.
If you have a file ready or nearly ready, we can review it against the Regulations and flag what the Inspector is likely to ask for. See the CEIG approval consultancy page, then reach us on WhatsApp, by phone on +91 70099 85817, or ask for a free proposal to review your file.
Frequently asked
Is CEIG approval compulsory for a factory in Andhra Pradesh?
Where the installation is above the voltage the state notifies, or includes a generating unit above the notified capacity, inspection by the Electrical Inspector is compulsory before supply. Below those limits, the owner self-certifies and files a report. Because the limits are set by the state and have changed before, ask the Inspectorate for its current figures in writing before deciding which route applies.
What is the difference between CEIG approval and self-certification?
With CEIG approval the Electrical Inspector inspects and tests the installation and approves it in writing. With self-certification the owner inspects and tests, then files a report in the prescribed Schedule II form. Under the 2023 Regulations, a self-certified report is treated as received if not acknowledged within three working days. Owners can still opt to have the Inspector inspect an installation that qualifies for self-certification.
Does the DISCOM or the Electrical Inspector come first?
It varies by project and should be asked of both offices. The DISCOM sanctions load and the connection point; the Inspector approves the installation before supply. Some offices want the DISCOM sanction in the file before they inspect, and some DISCOMs want the approval before they connect. Agree the sequence in writing so neither office waits for the other.
Do I need fresh approval when I add a transformer or solar later?
Yes. The Regulations bar connecting an addition or alteration to supply until it has been approved in writing by the Electrical Inspector or self-certified, as the case requires. A second transformer, a larger DG set or a solar expansion is treated as a change to the installation. Keep the original approval and test records so the additional file builds on them.
How often must the installation be inspected again?
The Regulations require periodic inspection or self-certification at the interval the state government directs, and that interval cannot exceed five years. Check the interval that applies to your installation type with the Inspectorate and enter the due date in your maintenance calendar. Installations disconnected for six months or more also need approval or self-certification before supply is restored.
Related services
Related guides
- Three Vendors, One Roof, Three Different Generation Figures.
- Perovskite Cells Promise 30%+ Efficiency. Your Roof Doesn't Have Ten Years to Wait and See.
- A Plant Down 8% Looks Exactly Like a Plant Working Fine.
- Addressable Lighting Control Pays in Some Buildings and Not in Others.
- Your Shopfloor Is Probably Lit Wrong in Both Directions at Once
- Solar EPC for Factories in Odisha: DISCOM Rules, Approvals and Cost
Related on this site
- termTransformer Sizing (kVA)
- termCEIG Approval
- termOpen Access (Solar)
- serviceCabling, Cable Trays & Bus Ducts (Electrical)
- serviceEarthing & Lightning Protection (Electrical)
- calculatorLed Retrofit Savings Calculator
- calculatorSolar Panel Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guideCEIG approval for factories
- guideFactory approvals roadmap, India
More on Electrical & Power · all insights