Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh TEDx talk, books & interviews
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Submit RFQ Get a Free Quote
Costing & Procurement

Electrical Preventive Maintenance Schedule for a Factory: Template by Asset

31 October 2026 · 5 min read · by

Title card reading Electrical Preventive Maintenance Schedule for a Factory: Template by Asset

An electrical preventive maintenance schedule lists every electrical asset in the factory, the task done on it, how often, who signs it off and what record is kept. Intervals are set by the manufacturer's manual, your duty cycle and your risk assessment, not by one universal number. This template shows the fields and the asset rows to start from.

What should each field of the schedule say?

A schedule that only says "check panel monthly" cannot be audited. Each row needs seven fields, and each one answers a question an inspector or insurer will ask.

  • Asset ID and location: the tag on the equipment and the room or yard it sits in.
  • Task: the specific check, test or service, in a verb-first line.
  • Frequency: daily, weekly, monthly, quarterly, annual or by running hours.
  • Basis: the manual, regulation or standard the task comes from.
  • Done by: in-house electrician, licensed contractor or OEM engineer.
  • Acceptance value: the reading that passes, such as an earth resistance limit from the design.
  • Record: the log sheet, test report or photograph that proves it was done.

Where do the requirements come from?

The Electricity Act, 2003 makes the Electrical Inspector a statutory authority, and the Central Electricity Authority's safety regulations set duties on owners to maintain installations safely and to keep them inspectable. Earthing practice follows IS 3043. Switchgear maintenance practice is covered by the IS 10118 series. For each row, the template says "manual" where the OEM document is the basis; those documents differ by make and model, so the schedule must be built from your own.

State inspectorates also run periodical inspections of HT installations. The schedule is the evidence you hand over on that day. Our CEIG guide explains what the inspector looks at.

What does the template look like by asset?

The table below is a copyable structure. Frequencies are typical starting points that you adjust to the manual and your own history; they are not regulatory minimums unless your inspectorate or insurer says so.

AssetTaskTypical frequencyBasisRecord
HT switchgear (VCB/RMU)Visual check, cleaning, operation test, protection relay testQuarterly check; annual relay testOEM manual; IS 10118 practiceSwitchgear log, relay test report
Power transformerOil level, temperature, breather, oil tests, tap positionMonthly check; annual oil testOEM manual; oil maintenance practiceTransformer log, oil test report
LT panels, MCC, PCCThermography, torque check on terminals, cleaningAnnual, before peak load seasonOEM manual; site risk assessmentThermal images, torque sheet
Earthing systemEarth resistance of each pit and the grid, connection checkAnnual, ideally in dry seasonIS 3043; design valueEarth pit test sheet by pit number
DG set and AMF panelOil, coolant, filters, load test, changeover testWeekly run; periodic service by running hoursOEM manualDG log, service report
APFC panelCapacitor current, contactor condition, controller settingsQuarterlyOEM manualPanel check sheet
UPS and batteriesVoltage and temperature check, discharge testMonthly check; annual capacity testOEM manualBattery log
Cables and terminationsInsulation resistance test, visual check for heatingAnnual, or after any faultSite risk assessmentIR test report by feeder
Lightning protectionAir-terminal and down-conductor continuity, earth testAnnual and after storm damageDesign basis; IS 3043LPS test report
Emergency lighting and exit signsFunction and duration testMonthlyFire scheme; OEM manualTest register

Who should do which task?

Daily rounds, log readings and cleaning can sit with trained in-house electricians. HT switching, relay testing, transformer oil sampling and thermography should be done by people with the right licence and instruments. Under the Electricity Act framework, work on installations is done by licensed electrical contractors and supervisors, and the schedule should name who holds the licence for each task. Keep calibration certificates for the instruments, because a reading from an uncalibrated meter proves little.

What goes on the daily and weekly rounds sheet?

The rounds sheet costs the least in the programme and catches the most. The electrician walks the substation, panel rooms and DG yard and records what he sees against a fixed list.

  • Panel room: temperature, ventilation, door seals, no stored material, no water ingress, indicator lamps working.
  • Transformer yard: oil level and temperature readings, breather colour, no oil leaks, fencing and signage intact.
  • Meters: voltage, current per phase, power factor and maximum demand noted against the previous day.
  • DG set: fuel level, battery condition, coolant level, no alarms, and a no-load or load run as per the plan.
  • Safety kit: rubber mats, insulated gloves, fire extinguishers and the single-line diagram displayed and in date.

Readings matter more than ticks. A current that creeps up by a few percent over weeks on the same load is an early warning of a loose termination or a failing motor, and it only shows if the number is written down.

What mistakes make a schedule fail?

  • Copying a template without removing assets the factory does not have, or missing assets it does, such as a new solar inverter or a lift panel.
  • Setting frequencies once and never reviewing them against faults.
  • Doing shutdown work without a permit-to-work and lock-out procedure, so the task is skipped when production objects.
  • No spares list, so a known weak part waits weeks for delivery.
  • Test results filed without acceptance values, so nobody can tell a pass from a warning.

How do you keep the schedule working?

Three habits matter more than the template. First, every task generates a record, even when the finding is "no defect". Second, every defect gets an action, an owner and a closing date, so findings do not accumulate unseen. Third, review the frequencies once a year against the fault history: if a feeder trips twice, its row moves from annual to quarterly. A schedule that never changes is probably not being used.

The cost of running the programme depends on the asset count, the HT content and who does the work. The MEP maintenance budget calculator gives a starting budget, and the AMC page explains what a contract covers.

How Secured Engineers helps

For maintenance the company writes asset-wise schedules for electrical, fire, HVAC and plumbing systems and can carry them under an annual maintenance contract. Design is done in-house, and approvals such as Fire NOC, CEIG and DISCOM net-metering are filed in-house. Mechanical, electrical, plumbing, fire and solar work can sit under one contract. The company works from offices in Noida and Ludhiana and reports 535+ projects across 18+ states and an 89.77% repeat-client rate.

To discuss your site, WhatsApp or call +91 70099 85817, or request a free quote. The relevant page is AMC and maintenance services.

Frequently asked

How often should a factory's electrical panels be serviced?

There is no single legal interval for every panel. A common starting point is an annual shutdown service with thermography and terminal torque checks, plus quarterly visual checks. The manufacturer's manual and your fault history should set the final frequency, and any panel that has tripped or shown heating moves to a shorter interval.

Is a preventive maintenance schedule required by law?

The Central Electricity Authority's safety regulations place duties on owners to keep installations safe, and state electrical inspectorates inspect HT installations periodically. The schedule is the evidence of that upkeep. Whether a specific format is mandatory depends on the state and on your insurer, so confirm with the inspectorate.

What is the difference between preventive and predictive maintenance?

Preventive maintenance is done on a fixed calendar or running-hours basis whether or not a fault is visible. Predictive maintenance uses condition data, such as thermography or oil analysis, to decide when to act. Most factories use both: the calendar sets the checks and the readings decide the follow-up.

Who can carry out electrical maintenance in a factory?

Trained in-house electricians can do routine rounds and logging. HT switching, relay testing and work on licensed installations should be done by people holding the licence required in your state. The schedule should name the licence holder for each task so that the record stands up at inspection.

What records should be kept, and for how long?

Keep the log sheets, test reports, thermal images and calibration certificates for every task, with defects and closure dates. The retention period depends on your insurer, your quality system and the inspectorate, so ask them. Keeping records from at least the last inspection cycle is a sensible minimum.

Related services

Send the BOQ, the quotations you are comparing or the drawings the budget is for — the review starts from your documents, not a rate card.

Comparing quotes or building a budget?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Speak to a Lead Engineer