Buying a RIICO Plot: Utilities, Approvals and MEP Planning for the Factory
Before you pay for a RIICO plot, confirm four things in writing: the allotment scheme and its conditions, the DISCOM feeder voltage and spare capacity at the plot, the water and drainage arrangement, and the building-plan route for Fire NOC. Rajasthan's approvals then run through the DISCOM, the Electrical Inspectorate, the Local Self Government department and RSPCB.
How is a RIICO plot allotted?
RIICO is the state's industrial development corporation and the allotting authority for its industrial areas. Its schemes have changed over the years. Recent reporting describes a Direct Land Allotment scheme under which investors with executed MoUs apply online through the Rajasthan SSO login, with a quota for MSMEs, while other plots have gone through auction or lottery. Because reports differ on how selection works, and schemes carry end dates, we do not set out rates or rules here. Ask the RIICO regional office which scheme is open for your area, and read the allotment letter for construction deadlines and permitted use.
Allotment decides ownership of the plot. It does not give you a power connection, a Fire NOC or a pollution consent. Each of those is a separate file.
What should you check on the plot before paying?
The estate may have roads, water lines and street power, but the standard to ask for is specific. A short checklist helps.
- Power: voltage of the nearest feeder, distance to the substation, and spare transformer capacity. The load you need decides whether you take LT or HT supply.
- Water: source, daily allocation and pressure. This feeds both the process and the fire water tank sizing.
- Drainage and sewage: whether a common treatment facility serves the area, and where your outfall goes.
- Access: road width for fire tender movement, which the fire scheme depends on.
- Plot shape and orientation: a long east-west roof is easier to fit with solar than a cramped one.
These are questions for RIICO and the DISCOM, not assumptions. Estates differ even within one district.
Which authorities does a Rajasthan factory deal with?
| Approval | Authority | Planning note |
|---|---|---|
| Plot, lease and building plan | RIICO | Layout and use as per allotment letter |
| Power connection | JVVNL, AVVNL or JdVVNL by region | Sanction first; energise after inspectorate clearance |
| Fire NOC | Local Self Government department, under the Rajasthan Municipalities Act, 2009 | No dedicated fire act; Fire NOC precedes building-plan approval |
| CEIG drawing approval and inspection | Electrical Inspectorate Department, Government of Rajasthan | For HT installations and HT-interfacing solar |
| Pollution consent (CTE, CTO) | RSPCB, via Raj Nivesh with SSO login | Category sets validity and treatment |
| Factory licence | Factories and Boilers Inspection Department | After plans are approved |
Details for each are in our Rajasthan guides: Fire NOC in Rajasthan, CEIG in Rajasthan, CTE and CTO in Rajasthan and the factory licence in Rajasthan.
What should the MEP plan settle before construction?
Three decisions are cheap on paper and expensive on site. First, the supply voltage: if the connected load pushes you into HT, the transformer room, the HT panel and the CEIG file all enter the programme. The factory electrical capacity calculator gives a first estimate of load and transformer size from your machine list. Second, the fire scheme: the water tank, pump room and tender access must sit on the building plan that the Local Self Government department reviews. Third, the roof: if solar is planned, the structure should be designed for the module load from the start, instead of being retrofitted.
On pollution consent, RSPCB's published timelines have changed recently. Its office order of 29 July 2025 sets short windows for Green units with investment below ₹5 crore, and CTO auto-renewal for complying units began on 4 June 2025. As of October 2026, check the Board's pages for the current position, since the categorisation was also revised in early 2026.
What goes wrong when the plot is bought first and the load is sized later?
The common failure is a plot bought on the basis of price per square metre, followed by a load calculation that shows the nearby feeder cannot carry it. The DISCOM then asks for a dedicated line or a new transformer, and the cost and time land on the owner. A second failure is a shed designed without the fire scheme: the plinth, the tank and the pump room are placed first, and the Local Self Government review asks for tender access that the layout does not allow. A third is the pollution category. A process that falls in Red or Orange needs treatment space and utilities planned from day one, while a Green or White unit has a lighter file. None of these needs a large study. They need a one-page load schedule, a layout sketch and a process note, prepared before the allotment money is paid. If the plot is in an area where we have a separate page, such as Bhiwadi, Neemrana or Khushkhera, the estate page lists the authorities for that area.
Rajasthan also differs from its neighbours in one respect that catches owners from Punjab or Haryana. The Fire NOC does not come from a fire directorate. It comes through the Local Self Government department, and it is a prerequisite for the building-plan approval from the municipal body, so the fire scheme has to be ready earlier in the programme than owners from other states expect.
How does rooftop solar fit a RIICO shed?
Rajasthan has strong irradiance and large flat-roofed sheds, so rooftop solar often pays back through reduced grid purchases. The limit is regulatory as much as physical. Net-metering is applied for with the DISCOM under RERC regulations, and the capacity limit has been revised, reportedly to 1 MW in February 2024. Read the current RERC order on the RERC website before sizing, and confirm any charges with the DISCOM. For HT-interfacing plants, the CEIG file and the commercial arrangement move together.
Our C&I solar band is ₹24,000–32,000 per kW ex-GST. The final figure depends on roof type, structure, inverter selection and cable runs. See solar EPC for what is included.
How Secured Engineers helps
Design is done in-house, and so are the filings: Fire NOC, CEIG and DISCOM net-metering applications. MEPF and solar sit under one contract, so the transformer, the fire scheme and the rooftop plant are designed against the same single-line diagram and the same roof. We work from offices in Noida and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients.
For the state overview, see the Rajasthan industrial zones hub. Your RIICO area may be one we have covered separately, such as Bhiwadi.
If you are weighing a plot or a shed, send us the sanctioned load and the roof area and we will tell you what the electrical, fire and solar scope looks like before you commit. Reach us on WhatsApp or call +91 70099 85817, or ask for a free quote.
Frequently asked
How do I apply for a RIICO industrial plot?
RIICO runs allotment schemes that change over time. In recent years applications have been filed online through the Rajasthan SSO login, and some schemes have been open only to investors with an executed MoU. Others use auction or lottery. Because the scheme, eligibility and rates differ by industrial area and by year, ask the RIICO regional office for the scheme currently open for your area.
Which DISCOM serves my RIICO plot?
Rajasthan has three distribution companies by region: JVVNL in the Jaipur and eastern belt including Alwar and Bhiwadi, AVVNL around Ajmer and the south, and JdVVNL around Jodhpur and the west. The DISCOM is decided by the district, not by RIICO. Confirm the feeder voltage and spare capacity with the DISCOM division office before you buy.
Does Rajasthan have a Fire NOC law like other states?
Rajasthan has no dedicated fire act. The Fire NOC is granted through the Local Self Government department under the Rajasthan Municipalities Act, 2009, and is a prerequisite for building-plan approval. Applications are filed through the SSO Rajasthan portal or via the local fire officer. The fire scheme itself is still designed to NBC 2016 Part 4.
Is a CEIG approval required for a Rajasthan factory?
If the installation takes HT supply, builds a substation, or exports solar at high tension, drawing approval and inspection by the Electrical Inspectorate Department, Government of Rajasthan, come before energisation. The DISCOM energises only after the inspectorate's clearance. Whether a particular installation falls in scope depends on voltage and current, so check with the department at design stage.
What is the net-metering limit for rooftop solar in Rajasthan?
RERC revised its net-metering limits in 2021 and again in early 2024, when the cap was reported as raised to 1 MW. As of October 2026 the current order and any later amendment should be read on the RERC website or confirmed with the DISCOM, because limits and charges change. Do not size the plant from a secondary summary.
Related services
Related guides
- Three Vendors, One Roof, Three Different Generation Figures.
- Your BOQ Said 1,000 M. Site Said 1,470 M. Who Pays for the Missing 470 M?
- Perovskite Cells Promise 30%+ Efficiency. Your Roof Doesn't Have Ten Years to Wait and See.
- The Future of MEP Engineering: 5 Technologies to Watch
- The MSME Act Just Changed. Here Is What It Means for a Factory Owner.
- Reading an MEP Works Programme: Critical Path, Float and the Milestones That Matter
Related on this site
- termGross Metering
- termDLP (Defect Liability Period)
- termEPC
- serviceCCTV & IP Video Surveillance (Low Voltage / ELV)
- serviceBattery / Hybrid Storage (Solar EPC)
- calculatorMEP Renovation Budget Calculator
- calculatorSolar EMI Calculator
- buyer's guideHow to Compare MEPF Quotations
- guideFactory licence and DISH approval
- guideCTE/CTO pollution consent
More on Project Delivery & Commercial · all insights