Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Design & Coordination

MEP Load Estimation at Concept Stage: Electrical, Cooling and Water From the Equipment List

22 October 2026 · 6 min read · by

Title card reading MEP Load Estimation at Concept Stage: Electrical, Cooling and Water From the Equipment List.
Title card. Not a photograph of a Secured Engineers site.

At concept stage, list every item of equipment with its rated kW, duty and heat to space, apply diversity to get a maximum demand, add a growth allowance of about 15 to 20 percent as NBC 2016 suggests, and convert to kVA at the supply authority's power factor. Cooling and water follow from the same list. The result sizes plant rooms and budgets before drawings exist.

What does the equipment list need to say?

A load estimate is only as good as the list it starts from, and the list is usually the process engineer's, written for another purpose. Ask for these columns for each item: description, location, rated input kW (not only shaft kW), voltage, duty (continuous, intermittent, standby), starting method, heat released into the room, water use, and whether it is existing, planned or future. Mark which items run together in the worst hour of the year.

NBC 2016 Part 8 Section 2 asks that the supply authority be consulted early on feasibility, and says the wattage per square metre and permissible diversity depend on the building type, such as industrial, commercial or hospital, and on city grading so that future loading is accounted for. A factory is not an office; do not borrow office densities.

How do you get from the list to electrical demand?

NBC 2016 sets the sequence: load assessment and application of a suitable diversity factor to estimate the full-load current is the first step, made for every circuit, submain and feeder. Power factor, harmonics and the efficiency of loads are considered, and the diversity factor is based on one's own experience or on its table. The code adds that an allowance of about 15 to 20 percent should be made for extension in the near future.

Here is the arithmetic with invented numbers, to show the steps. They are not benchmarks for any plant.

Load groupConnected kWDemand factorMaximum demand kW
Process machines6000.60360
Chiller plant, running units only2201.00220
Compressed air and pumps1500.70105
Lighting and small power800.7056
Sum of group demands741
Diversity between groups, assumed 0.90667
Growth allowance of 15 to 20 percent767 to 800
kVA at an assumed power factor of 0.95about 807 to 842 kVA

The result is a number to size the incoming supply and the transformer against, together with the DG set for the loads that must run in an outage. Fire pumps and other standby units are not in the normal maximum demand but belong on the emergency schedule. Transformer selection is a separate step, covered in the HT connection and substation approval guide, and the DISCOM's contract demand rules apply.

Three cautions follow from the code. The diversity table in NBC 2016 covers households, small shops, offices and small hotels, so take utilisation for process loads from the process engineer, not from a table written for small premises. Power factor is not a detail: licensees generally stipulate 0.90 or better, so size correction capacitors, and watch harmonics from drives. And the growth allowance is a minimum for near-term extension; ask whether the client has a phase two.

How do you estimate the cooling load at concept stage?

The code requires a cooling and heating load estimate before HVAC equipment is designed and installed, and lists what it should take in: indoor temperature, humidity, air velocity and activity; outdoor design conditions; building construction and orientation; fenestration and shading; occupancy; ventilation and infiltration; internal loads from equipment, computers and lighting; effective volume; and occupancy, lighting and equipment schedules. It also asks for a suitable diversity factor based on usage, for off-peak loads at night and on weekends, and for anticipated future changes.

At concept stage you will not have all of these. Take the conditioned floor area and the occupancy from the brief, convert installed electrical equipment in conditioned spaces into heat gain (the electrical input of the equipment, less any heat taken away by process cooling or exhaust), add the ventilation load for the fresh air needed, and apply the building envelope allowance for the site. Use the chiller capacity calculator for the plant size and remember that one TR is 3.517 kW. Replace this with a full calculation at design development, and keep the concept figure for plant-room areas and budget only.

Two code observations help the early decisions. For a water-cooled plant the cooling tower footprint is 0.07 to 0.10 square metres per TR for mechanical-draft towers, and the code notes that centralised systems usually prove more cost-effective when the total building load exceeds 100 TR, depending on climate and use. Evaporation from the tower is usually about 1 percent of circulation, which feeds the water estimate.

How do you estimate water demand?

Water has three parts. Domestic and flushing demand comes from headcount and NBC 2016 Part 9 Section 1, Table 1. For factories where bathrooms are provided it gives 30 litres per head per day for domestic use plus 15 for flushing, a total of 45; where bathrooms are not provided, 20 plus 10, a total of 30. For offices including canteen it gives 25 plus 20, a total of 45. Process water comes from the equipment list: boilers, washers, compressors, cooling towers. Fire water is a reserve set by the fire design and the fire authority, and it sits in the tank volume, not in daily demand.

Cooling tower make-up is the part most often missed. At about 1 percent of the circulating flow for evaporation, plus drift and blow-down, a circuit circulating 500 cubic metres an hour needs several cubic metres an hour of make-up. Put it on the schedule with its own tank, which the code asks to be kept separate from the drinking water tank.

Which mistakes undersize the plant rooms?

  • Nameplate as demand. Adding every rated kW without diversity oversizes the incoming supply; ignoring starting currents and standby duties undersizes the DG. Do both calculations on purpose.
  • Standby counted as running. A duty/standby pair is one load, not two, but the room must hold both machines.
  • No growth room. The code's 15 to 20 percent is for load. Space for the next transformer, chiller or pump is a layout decision made now.
  • Cooling counted twice. Chiller power belongs in the electrical schedule once, and its heat rejection belongs in the tower sizing.
  • Ignoring the supply authority. Contract demand, power factor and HT or LT thresholds can change the layout of the electrical room.
  • Heat from the equipment room itself. Panels, transformers and drives release heat into their own rooms that needs ventilation or cooling.
  • Water treated as an afterthought. Tower make-up, process water and the fire reserve can double the tank volume that a headcount alone suggests.

The MEPF cost calculator turns a first set of loads into a budget range, and our guide to the MEP design brief lists the information to collect. Later stages are in MEP design deliverables by stage.

How Secured Engineers helps

Secured Engineers' MEP design consultancy prepares load schedules, plant room layouts and the drawing sets that the Fire NOC, CEIG and DISCOM applications need, all in-house, and the same team can build the works as a single MEPF contract with solar. Fire NOC, CEIG and DISCOM net-metering filings are prepared in-house. We work from offices in Noida (Delhi NCR) and Ludhiana, across 535+ projects in 18+ states, with 89.77% repeat clients.

If you have an equipment list and a concept layout, send them and we will review the load assumptions, the growth margin and the plant room areas, and tell you what we would change. The service is described on design and approvals. Message us on WhatsApp, call +91 70099 85817, or ask for a free proposal.

Frequently asked

How much growth margin should a concept estimate include?

NBC 2016 Part 8 says allowance should be made for about 15 percent to 20 percent for extension in the near future when assessing electrical load. Use that as the floor for the electrical side, and add more where the client has a stated phase two. Plant rooms deserve extra: it is cheap to leave space for a second transformer or chiller and expensive to find it later.

What diversity factor can I use for a factory?

NBC 2016 says to apply a suitable diversity factor to every circuit, submain and feeder, based on your own experience or its table. That table covers households, small shops, offices and small hotels, so it does not fit process plant. For a factory, take utilisation and simultaneity from the process engineer machine by machine, then test the result against the metered demand of a comparable plant.

Which power factor do I assume?

NBC 2016 notes that conditions of supply from electricity boards and licensees stipulate a lower limit of power factor, generally 0.90 or better. Convert kW to kVA with the figure your supply authority requires, and plan correction capacitors, with detuning where harmonic loads are present, for the difference. Confirm the requirement with the licensee before you fix the transformer rating.

How do I estimate water demand without drawings?

Use the headcount and NBC 2016 Part 9 Table 1 for domestic and flushing water, then add process, cooling tower make-up and fire reserve from the equipment list and the fire design. The table gives 45 litres per head per day for factories where bathrooms are provided, 30 where they are not, and 45 for offices including canteen. Cooling tower losses are usually about 1 percent of circulation for evaporation.

When should the cooling load be calculated?

NBC 2016 requires the cooling and heating load estimate to be carried out before the design and installation of HVAC equipment, taking in indoor conditions, outdoor design conditions, construction and orientation, fenestration, occupancy, ventilation, infiltration and internal loads. At concept stage use areas and equipment heat gain to size plant rooms and budgets, and replace the estimate with a full calculation at design development.

What happens if I undersize the plant rooms?

Equipment still has to fit, and clearances, access, ventilation and structure follow it. A transformer bay, DG yard, chiller room, pump room or water tank that is too small leads to redesign after drawings are approved, or to equipment squeezed in with no maintenance access. Fire and electrical approvals are drawn against the plant room layout, so late changes reopen submissions.

Related services

Share the coordinated layouts or clash reports you have — an engineer reviews the services zones and where they conflict.

Services not fitting the drawings?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Speak to a Lead Engineer