Factory Electrical Load Enhancement: From Measured Demand to an Approved Connection
Adding production load is an electrical question twice over. Inside the fence, the transformer, switchboard and cables must carry it. At the boundary, the DISCOM has sanctioned a contract demand — the maximum demand in kVA it has agreed to supply — and drawing more needs a load-extension application. For a growing factory, that application can turn into a new connection at a higher voltage, a transformer of its own and an inspection before energisation. For a high-load site such as a cold store, a data centre or an EV hub, it can also wait on network works at the DISCOM's substation.
The way to stop it gating production is to size the enhancement from measured demand, file a complete application early, and settle the transformer and protection consequences in the same design.
Connected load versus maximum demand
The application asks for both, and they are different numbers. PSPCL's FAQ defines connected load as the sum of the manufacturer's rated capacities of all energy-consuming devices that may be connected simultaneously, excluding standby equipment on a changeover switch; contract demand as the maximum demand in kVA sanctioned to the consumer; and sanctioned load as the load in kW (or BHP) the licensee has agreed to supply. Maximum demand itself is what the meter records: the highest average kVA over a demand interval — normally 30 minutes, though the Bureau of Energy Efficiency notes it varies between 15 and 60 minutes from utility to utility.
The ratio of maximum demand to connected load — the demand factor — is why the sum of nameplates overstates the requirement: machines do not all run at full load together. The question an enhancement must answer is what the meter will record once the new equipment runs alongside the old.
| Item | Existing plant | After the expansion | Where the number comes from |
|---|---|---|---|
| Connected load (kW or BHP) | Sum of installed ratings | Add the new equipment's ratings | Equipment schedule; nameplates |
| Contract demand (kVA) | As sanctioned | The figure you will apply for | The bill; the sanction letter |
| Recorded maximum demand (kVA) | Highest and typical monthly values | Measured peak plus the coincident increment | Twelve months of bills |
| Load profile | Demand by interval, shift and season | Expected profile with the new line running | The meter's stored interval data, or a logger at the incomer |
| Coincident increment (kW) | — | What the new machines add to the peak when running together | Duty cycles and the production plan |
| Power factor | Monthly average (kWh ÷ kVAh) | Expected PF after the expansion | Bills; a logger; drive and capacitor data |
| Transformer | Rating and measured loading | Required kVA at the expected PF | Nameplate; logger |
| Main breaker, busbar and cables | Ratings | Loading after the expansion | Single-line diagram; panel schedules |
| Fault level | At the main LT bus | With any new or larger transformer | DISCOM fault data; a protection study |
| Backup | DG and UPS ratings | What they must carry after the expansion | Nameplates; the changeover scheme |
Read twelve months of history before choosing a number
A single month's maximum demand is a sample, not a basis. Pull at least twelve months of bills to find the seasonal peak, then get the interval data behind them: ask the DISCOM whether your meter stores a load survey it can download, and if not, log at the incomer over a representative production cycle. Look at when the peak happens, what was running, and whether it was a start-up surge or sustained load.
Then add the new equipment as a coincident increment — what it adds to that peak — rather than as its nameplate. The factory electrical spare-capacity calculator does this arithmetic. In its worked example, a measured peak of 300 kW plus a 100 kW coincident increment at power factor 0.9 needs 444.44 kVA; an existing 630 kVA transformer planned at 80% utilisation offers 504 kVA, leaving 59.56 kVA of headroom. At power factor 0.85 the same load needs 470.59 kVA — which is why power factor correction belongs in the same study.
The contract demand you apply for is a choice: the required kVA plus a margin you decide for growth. Set it too low and exceeding it attracts the surcharge in your tariff order; too high and you may pay demand-based fixed charges on capacity you never use. Our guide to contract demand and ToD tariffs covers that trade-off.
The DISCOM process and documents
Procedures are state-specific. Two published examples show the shape.
Punjab (PSPCL). PSPCL's FAQ routes industrial applications through the Common Application Form on the state industries portal (pbindustries.gov.in), with applicants whose fixed capital investment is under ₹25 crore redirected to PSPCL's own single window. It says demand up to 100 kVA is usually supplied at LT, demand above 100 kVA and up to 5,000 kVA at HT (above 650 V and up to 33 kV), and demand above 5,000 kVA at EHT. Applicants above 150 kW/kVA receive a demand notice valid for six months, extendable up to a year in three-month blocks; where total demand including the addition exceeds 2,000 kVA, a feasibility clearance comes first. The charges include a processing fee, security (consumption) for the additional demand at the slab rate of the total, meter security, and service-connection or works charges from the commission's standard cost data. Where total demand exceeds 150 kVA, the consumer pays for any augmentation of its own service line and a proportionate share of the common line up to the feeding substation, including the breaker or bay, for the additional demand; and where the addition changes the supply voltage from LT to HT, the expenditure is charged as for a new connection under the Supply Code 2024.
The tariff category can change too. PSPCL's tariff structure for FY 2026-27 (Commercial Circular 09/2026, issued under the PSERC order of 6 March 2026) places industry up to 50 kVA in Small Power, above 50 kVA and up to 100 kVA in Medium Supply, and above 100 kVA in Large Supply. The Small Power limit was 20 kVA in FY 2025-26, so read the order in force rather than an older FAQ.
Uttar Pradesh (UPPCL). UPPCL's industrial connection application asks for the present sanctioned load with its sanction number and date, the additional load required, the present supply voltage, whether an independent feeder is needed, a possession letter or NOC from the industrial development institution, the pollution control board's NOC, the industries department registration, whether the process is continuous, and the proposed date production starts.
In Haryana, Delhi and other states, the equivalent rules sit in the state commission's supply code and the DISCOM's schedule of charges. Read them before deciding the number you apply for.
| Your situation | Likely route | What changes | Confirm with the DISCOM |
|---|---|---|---|
| New demand stays within the present category and voltage | Load extension on the existing connection | Contract demand, security deposit, possibly metering | Charges, documents and the test report required |
| New demand crosses a tariff category boundary | Load extension with a change of category | Tariff, fixed charges, ToD terms | Which category applies, and from when |
| New demand crosses the LT/HT threshold | New HT supply with your own transformer, HT switchgear and metering | Substation design, inspection before energisation, charges as for a new connection (in Punjab) | Supply voltage, metering arrangement, line and bay works and their cost |
| Total demand above the DISCOM's feasibility threshold | Feasibility clearance before the application proceeds | A technical review of the network | Earnest money, submission deadlines, any augmentation |
| Feeding substation or feeder lacks capacity | DISCOM augmentation or an independent feeder | Network works outside your boundary, and your share of their cost | Whether supply can be phased while the works proceed |
| Supply already HT, transformer too small | Transformer upgrade or a second transformer | Fault level, protection settings, inspection of the additions | Whether the contract demand also needs extending |
Transformer and protection implications
- Transformer. Compare the required kVA at a realistic power factor with the rating at a utilisation you choose, then decide between replacing the transformer and adding a second unit with a plan for how the two share load. Location matters: the CEA 2023 regulations allow only dry-type transformers inside residential and commercial buildings, require indoor oil-filled transformers in other buildings to sit on the ground floor or not below the first basement, and call for separation walls and an oil soak pit where oil-filled apparatus holds more than 2,000 litres (regulation 46). Our note on undersized substations covers sizing for growth.
- Protection. A larger transformer raises the prospective fault current at the LT bus, so breaker breaking capacity, busbar and cable short-circuit ratings and relay discrimination must be rechecked — see fault level and coordination failures.
- Metering and the supplier's equipment. For supply above 650 V, regulation 46(1) requires the consumer to provide a separate building, or a locked, weatherproof and fireproof enclosure to which the supplier always has access, to house the supplier's apparatus and metering — or to segregate them where an enclosure is impracticable.
- Inspection. Installations above your state's notified voltage are inspected and tested by the Electrical Inspector before supply commences (regulation 45(3)); the owner tests every circuit or addition and submits the results with the application (45(5)); and additions or alterations are not connected until approved in writing by the Electrical Inspector or self-certified, as applicable (45(6)). Our CEIG approval guide walks through the file.
- Continuing duties. A factory with more than 250 kW connected load must designate an Electrical Safety Officer (regulation 5(3)), and periodic inspection or self-certification continues at the interval your state directs, which may not exceed five years (regulation 32).
When the grid needs work first
For genuinely high-load sites the constraint may sit outside your boundary: the feeding substation may have no spare capacity, or the load may need an independent feeder. That is network work on the DISCOM's programme, and it is why the application should be filed as early as the land and layout allow — in parallel with design, not after it. Where commissioning cannot wait, discuss phasing with the DISCOM: part of the demand on the existing supply while the rest follows the works. Our note on HT connection delays in North India covers where files stall; for a solar plant's own grid connection, see the solar interconnection guide.
Secured Engineers' turnkey EPC and electrical infrastructure services cover load calculations, substation design, the approval filings and the installation. More expansion guides are on the Insights page; to have an engineer review your enhancement, share existing and proposed loads, the layout and production constraints through a scope review request.
Sources and how to verify
- Central Electricity Authority — CEA (Measures relating to Safety and Electric Supply) Regulations, 2023, notified 8 June 2023: regulations 5(3), 32, 45 and 46.
- Punjab State Power Corporation Ltd — FAQs on new connection and extension of load (refers to the Supply Code 2024; read 6 Oct 2026).
- Punjab State Power Corporation Ltd — Commercial Circular 09/2026: tariff structure for FY 2026-27, under the PSERC tariff order of 6 March 2026.
- Uttar Pradesh Power Corporation Ltd — application form for an industrial electricity connection (read 6 Oct 2026).
- Bureau of Energy Efficiency — guide book chapter "Basics of energy and its various forms" (connected load, maximum demand and demand interval).
Confirm locally: your DISCOM's current supply code, schedule of charges and portal procedure; your state's notified voltage for inspection and self-certification; and the tariff order in force on the date you apply.
Frequently asked
What information do I need before applying for a factory load enhancement?
Twelve months of bills showing maximum demand, contract demand and power factor; interval data from the meter or a logger; the single-line diagram; transformer, breaker and cable ratings; the list of new equipment with ratings and duty cycles; and the documents your DISCOM asks for — in UP, for example, the present sanction number and date, the NOCs and the industries registration. With those you can apply for a contract demand you can defend.
Which site conditions could change the scope or cost of a load enhancement?
A new demand that crosses your state’s LT/HT threshold; a feeding substation or feeder without spare capacity; the distance to the DISCOM’s line; space for a transformer, HT switchgear and the supplier’s metering enclosure; a fault level the existing switchgear cannot handle; earthing conditions; and an existing installation without current drawings. Any of these can add a substation, network works or an inspection to what looked like a form.
What should I send an engineer to review a load enhancement?
Existing and proposed loads — the bills, the single-line diagram and the new equipment schedule — with the layout and the production constraints, such as when the plant can shut down for tie-ins. An engineer can then check the demand, the transformer and protection, and the application before anything is ordered.
Should I apply for my connected load or my maximum demand?
You declare both, but they answer different questions. Connected load is the sum of installed ratings; contract demand is the kVA you ask the DISCOM to supply. Base the contract demand on measured maximum demand plus the coincident increment from the new equipment, at a realistic power factor, plus a margin you choose — not on the sum of nameplates.
Does a load enhancement need Electrical Inspector approval?
The additions do. Under regulation 45(6) of the CEA 2023 regulations, additions or alterations are not connected to supply until they are approved in writing by the Electrical Inspector or self-certified by the owner, depending on whether the installation is above or within the voltage your state has notified. A new installation above that voltage is inspected by the Electrical Inspector before supply commences.
Related services
Guides that reference this page
- MEP for Industrial Park Developers: Tendering Trunk Power, Water and Fire Networks
- MEP Design for an Industrial Park Developer: Trunk Services, Plot Loads and Phasing
- HT Panel Specification for a Factory: VCB, Relays, Metering and What to Demand
- CEIG Approval for a Transformer Installation: Drawings, Tests and Energisation
- When a 2027 Factory Needs a 33 kV Connection: Thresholds, Works and Timelines
- MEP Load Estimation at Concept Stage: Electrical, Cooling and Water From the Equipment List
Related on this site
- termCAPEX vs OPEX Solar
- termHarmonic Distortion (THD)
- termContract Demand
- serviceWater supply and distribution systems
- serviceEPABX and intercom systems
- calculatorMEP Renovation Budget Calculator
- calculatorTransformer Sizing Calculator
- buyer's guideHow to Compare MEPF Quotations
- guideFactory licence and DISH approval
- guideCTE/CTO pollution consent
More on Electrical & Power · all insights