Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

Solar for FMCG Factories: Sizing, Roof, Approvals and Payback (50 kW+)

22 October 2026 · 5 min read · by

Title card reading Solar for FMCG factories, with a packing-hall roof covered in solar panels.
Title card. Not a photograph of a Secured Engineers site.

A solar plant for an FMCG factory should be sized to the factory's lowest sustained daytime load, not to the roof. Read twelve months of bills for daytime units, maximum demand and sanctioned load, fit the plant under that base load and the transformer's headroom, then choose the approval route by size. Payback follows from units used on site, not units generated.

How do you size solar for an FMCG factory from the bill?

FMCG plants differ from heavy industry in one useful way: most of the load is the packing hall, not a furnace. Filling, blow-moulding, labelling, shrink-wrapping and case-packing lines run in shifts, with air-conditioned or controlled areas, compressed air and often cold storage. The load follows the production plan, so the bill alone can mislead. Use this sequence.

  1. Pull twelve months of bills and, if the DISCOM provides it, half-hourly meter data. You need monthly units, recorded maximum demand, sanctioned load or contract demand, and any time-of-day tariff slots.
  2. Find the daytime base load. Take the lowest sustained demand between roughly 9 am and 4 pm on normal production days, not the average. Lines that stop for changeovers, lunch or a shift handover set this floor.
  3. Cap the plant near that base load. A plant whose output stays below the base load means nearly every unit is used on site. Oversizing sends units to export or curtailment, which pay far less than self-use.
  4. Check the sanctioned-load and transformer headroom. The DISCOM links permitted capacity to the sanctioned load and checks the distribution transformer. Our sanctioned-load calculator shows how capacity maps to load, and the glossary entry explains the terms.
  5. Test the roof last. Roof area, structure and shading decide whether the plant fits, but they should not set its size. The solar calculator combines these inputs.

Seasonal products change the picture. A beverage or ice-cream line peaks in summer, when solar output is also highest; a winter-weighted line does not. Look at the year, not the month with the highest bill.

Which roof or ground option suits an FMCG site?

Most plants use the roofs of the production, packing and warehouse sheds. Pre-engineered metal roofs usually need a structural check for the extra load and a clamp-on or standing-seam mounting design, so penetrations do not become leak points. Leaks matter more in food and personal-care sheds than in a fabrication yard, because product, packaging and hygiene rules are all at risk. Where roofs carry HVAC condensers, chillers or cooling towers, keep the layout clear of exhaust plumes and walkways. Where roofs are too small or too old, carports or ground mounting on spare land are the alternatives; our note on carport solar compares them. Keep access for panel cleaning and for fire-service routes. The CEA safety regulations require clear roof pathways at least 75 cm wide with hand rails.

What approval route applies, and does size change it?

Plant on the factory's own premisesTypical routeRules that applyApprovals to plan for
Up to 500 kW, within the sanctioned loadNet metering at the factory's meterThe Ministry of Power's amendment to the Consumer Rights Rules raised the net-metering limit from 10 kW to 500 kW; the state commission's regulation sets the detailsDISCOM technical feasibility and agreement, Electrical Inspector approval above the state's generating-capacity limit, meter
Above 500 kW on siteCaptive or grid-connected, as the state regulation allowsState regulation decides export, banking and metering treatment; confirm with the DISCOMDISCOM permission for parallel operation, Electrical Inspector approval, possibly open-access formalities
Off-site plant or purchase through the gridOpen accessGreen Energy Open Access Rules, 2022: threshold 100 kW, approval in 15 days or deemedOpen-access application, charges and agreements; see open access solar

The net-metering limit is reported in the Ministry of Power's year-end review, which dates the amendment to 29 September 2021. Other sources give a different date, so rely on your state commission's current regulation, which is what governs you. Module rules also matter. MNRE's O.M. of 4 August 2026 exempts net-metering and open-access projects commissioned by 31 December 2026 from ALMM List-II (solar cells), but List-I modules still apply. It also says neither list applies to behind-the-meter solar used solely for a consumer's own captive consumption, other than government entities. Read the ALMM List-II commissioning guide before you choose modules.

What risks are specific to an FMCG plant?

  • Power quality. Servo drives, VFDs on compressors and automated lines are sensitive to harmonics and voltage swings. Specify inverter harmonic limits, reactive-power control and a power-quality check at the point of connection.
  • DG interlock. Many plants keep DG sets for line protection. Solar must trip or throttle when the DG is on. See our note on solar with DG sets.
  • Hygiene zones. Cleaning water, bird droppings and dust near open product areas need a cleaning method agreed with the quality team. Mounting solar over roofs above exposed-product zones is a conversation to have with your food-safety lead before design, not after.
  • Contract manufacturing. If you pack for brand owners, they may ask for evidence of renewable share. Metered generation data, not a modelled estimate, answers that.
  • Fire. Regulation 121 of the CEA safety regulations requires fire detection and suppression systems for solar installations to meet the relevant standards. Coordinate with the plant's fire design, and see our food processing and FMCG page.

How do you work out payback?

Payback is the capital cost divided by the yearly saving. The saving is units generated, times the share used on site, times the tariff you avoid. Our solar-for-factories page uses an example of about 1,440 units per kW a year and notes that industrial tariffs sit around ₹7.5–9.5 a unit. Take a 200 kW plant at 80% self-use and ₹7.5 a unit: 288,000 units × 0.8 × ₹7.5 is about ₹17.3 lakh a year. The published C&I band of ₹24,000–32,000 per kW excluding GST puts capital at ₹48–64 lakh, so simple payback is roughly 2.8 to 3.7 years. That excludes GST, O&M, degradation and tax effects, and it moves with self-use: at 60% self-use it lengthens. The page's own benchmark is a three-to-six year band, and the calculator shows the scenarios. Use the solar for factories guide and the size pages, such as 250 kW and 500 kW, for the cost scope.

How Secured Engineers helps

Secured Engineers designs solar and the electrical systems around it in-house, and files DISCOM net-metering, CEIG and Fire NOC applications in-house. MEPF and solar can be delivered under one contract, which suits a plant adding a packing hall or cold store alongside solar. We work from offices in Noida (Delhi NCR) and Ludhiana, and have delivered 535+ projects across 18+ states, with 89.77% repeat clients.

Send twelve months of bills and a roof plan and we will size the plant from your daytime load and show the approval route. See solar for factories, then reach us on WhatsApp, call +91 70099 85817 or request a free proposal.

Frequently asked

What size solar plant suits an FMCG factory?

Size it to the lowest sustained daytime load on a normal production day, within the sanctioned load and the transformer's headroom, and check the roof last. This keeps nearly all generation on site. The tools that help are twelve months of bills, half-hourly data if available and the solar calculator. Seasonal products change the answer, so look at the whole year.

Is net metering available for a 300 kW plant at a factory?

Often yes, because the national limit for net metering is 500 kW, but the state commission's regulation and the DISCOM's feasibility decision govern the actual approval. The plant must also fit within the sanctioned load and the transformer's headroom. Ask the DISCOM for its current net-metering terms for industrial consumers before fixing the capacity.

Does solar affect food-safety audits at an FMCG plant?

It can raise questions about roof integrity, water ingress, dust and cleaning near open product areas. None of these is a barrier, but agree the mounting design, cleaning method and access routes with your quality and food-safety teams during design. Solar over roofs above exposed-product zones needs the most care. Keep the maintenance plan documented for audits.

How long is the payback for factory solar?

It depends on the share of generation used on site, the tariff you avoid and the plant cost. The solar-for-factories page uses a benchmark band of three to six years, and the calculator shows scenarios at different self-use shares. A plant sized to the daytime base load sits at the shorter end. GST, O&M, degradation and tax effects should be included in a proper model.

Can a group with many FMCG factories use one solar design?

The engineering can be standardised, but approvals, tariffs and net-metering rules differ by state, so each site needs its own sizing and DISCOM process. A common specification for modules, inverters, monitoring and O&M keeps quality and reporting consistent across sites. Start with a pilot site, then replicate the template state by state.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it