UPS for a Factory: Load Classification, Runtime and Cost Drivers
A factory UPS should be sized from the loads that cannot stop, not from the whole plant. Sort loads into no-break, short-break and can-stop, add up their measured kW and kVA, and set battery runtime to the time the DG or a controlled shutdown needs. The cost then follows five drivers: kVA rating, redundancy, battery chemistry and autonomy, the room and cooling, and service.
Which factory loads belong on the UPS?
Most oversized UPS projects start with a list of everything that has a plug. Start instead from what each load does when the supply drops for a few seconds. The table is a classification you can fill in per machine and per panel.
| Class | Typical factory loads | On the UPS? | Autonomy is set by |
|---|---|---|---|
| No-break | PLC and control panels, SCADA and servers, network core, instrumentation, access control controllers | Yes | DG start and transfer time plus margin, or time to shut down and save data |
| Short-break | Motors, compressors, pumps, HVAC, general lighting | Usually no; they restart when the DG picks up | Not applicable; putting them on the UPS multiplies size and battery |
| Process-critical drives | Drives on lines that must not stop or lose position | Decide machine by machine with the manufacturer | Ride-through option, control-supply UPS, or whole-machine UPS |
| Life safety | Fire alarm panels, emergency lighting | Follow the fire-safety rules, not the general UPS | Standby-power requirement in the fire design |
| Can stop | Offices' general power, canteen, yard lighting | No | Not applicable |
Our guide to UPS planning for critical factory and office loads goes deeper on topology and bypass. This article is about what the answer costs.
How do you work out the runtime?
Ask what the UPS is bridging. With a DG set, the bridge is the DG's measured start and transfer time with a margin, plus any controlled shutdown for loads that cannot restart on their own. Without a DG, the runtime is the time needed to bring the process to a safe stop. A round number such as one hour "to be safe" multiplies the battery, its space, its cooling and its cost.
On an energy balance, runtime is usable battery energy divided by load. Usable energy is the nominal battery energy multiplied by the usable fraction, the inverter efficiency and an ageing fraction. Our UPS runtime calculator uses an ageing fraction of 0.8, which treats the battery as at end of life at 80% of rated capacity. In its worked example, a 1,000 W load on a 48 V, 100 Ah bank with a usable fraction of 0.8 and inverter efficiency of 0.9 gives about 2 hours 46 minutes, which is 14 minutes short of a 3-hour target. The same bank new gives about 25% more, which is why you check runtime at end of life, not on installation day.
That is a screening method. The battery maker's constant-power discharge data, at the actual end voltage and the lowest temperature expected, decides the runtime you can rely on.
What drives the cost of a factory UPS?
We quote no price here, because the figure depends on the drivers below and on the make. What we can show is what moves it and which question exposes each driver.
| Cost driver | Why it moves the number | Question for the bidder |
|---|---|---|
| kVA and kW rating | Both limits bind, and growth headroom adds capacity you may not use for years | What load, in kW and kVA, was it sized on, and was it measured? |
| Topology and redundancy | Online double conversion costs more than line-interactive; parallel or N+1 arrangements add whole units | What fails if one UPS fails, and does the process tolerate it? |
| Battery chemistry and autonomy | Battery is a large share of a UPS system's cost and grows with minutes of runtime; lithium-ion and valve-regulated lead-acid differ in price, space and life | Runtime at end of life, at what temperature, to what end voltage? |
| Battery replacement | Batteries are replaced several times in the life of the UPS; temperature shortens life | Expected replacement interval, and the cost then |
| Room, ventilation and cooling | Losses become heat; battery rooms need ventilation, and lithium-ion rooms have fire provisions | Heat load, air changes, and who builds the room |
| Input side and DG compatibility | Rectifier harmonics and inrush affect the DG and upstream cables; filters or soft-start add cost | Input power factor, THD and DG compatibility on the datasheet |
| Distribution, bypass and cabling | Maintenance bypass, output panels, cable runs and protection are separate lines | Is the maintenance bypass in the price? |
| Service | Annual maintenance, battery tests, spares and response time run for the life of the unit | What does the AMC cover, and what is the response time at my site? |
How do battery choice and room design change the budget?
Valve-regulated lead-acid batteries cost less per unit of energy at purchase, need more space and are replaced more often. Lithium-ion packs usually cost more at purchase, take less space and last longer between replacements, and they bring fire-safety conditions for the room. We have not compared specific products, so ask each bidder for the replacement interval, the warranty basis and the fire safety arrangement in writing. The compliance side is in our note on lithium-ion UPS room fire safety, and the ventilation duty for charging areas is in battery charging room ventilation.
Room design is the cost most buyers discover late. A UPS and its batteries turn losses into heat, so the room needs cooling that the UPS quotation may not include. Put cooling, ventilation, the earth connection and cable entries into the same budget line as the UPS, or the comparison between quotes is false.
UPS, DG and solar: keep the roles separate
A UPS covers seconds to minutes. A DG covers hours. Solar cuts daytime grid units but does not ride through a grid failure on its own. Do not size the UPS to replace the DG. For the longer-duration question see DG versus battery storage for factory backup. The DG must be sized to start the UPS rectifier along with the other loads, and the UPS input power factor and harmonics belong in the DG selection.
Whole-life cost, not purchase price
Compare bids on purchase price, plus battery replacements over the planning period, plus service, plus the energy lost in the UPS and the cooling that removes the heat. A UPS at light load runs at lower efficiency, so a unit sized for loads that never arrive wastes energy every hour. Ask for efficiency at 25%, 50% and 100% load on the datasheet, and a battery replacement price, so the whole-life view can be built.
How Secured Engineers helps
We design electrical systems in-house, including UPS and DG integration, and take electrical, HVAC, fire fighting and plumbing under one contract. CEIG and DISCOM filings are done in-house. Our offices are in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients. See electrical infrastructure for the scope.
If you have a UPS budget or quotation, send it with the load list, single-line diagram and DG details, and we will review it for the drivers above: what was measured, what is missing and what a revised scope would change. Reach us on WhatsApp, call +91 70099 85817, or ask for a free proposal.
Frequently asked
How much does a UPS for a factory cost?
We cannot give a figure without the load, the runtime and the make. The cost follows the kVA and kW rating, the topology and redundancy, battery chemistry and minutes of autonomy, the room and cooling, the input-side requirements and service. Send the load list and single-line diagram, and we can review a quotation for what it includes and what it leaves out.
Should the whole factory be on one UPS?
No. Motors, compressors and general lighting restart when the DG picks up, and putting them on a UPS multiplies its size and battery for little benefit. Put the no-break loads on it: controls, servers, network and critical instruments. Process-critical drives are decided machine by machine with the manufacturer.
How long should the UPS battery last in minutes?
Long enough to bridge the DG's measured start and transfer time with a margin, or to shut the process down safely if there is no DG. A longer figure adds battery, space and cooling cost. Check the runtime at the end of battery life and the lowest expected temperature, using the maker's discharge data rather than a nameplate.
Is a lithium-ion UPS battery better than lead-acid?
It depends on the site. Lithium-ion usually costs more at purchase, takes less space and may last longer between replacements, and it brings fire-safety conditions for the room. Lead-acid costs less per unit of energy at purchase but is bulkier and replaced more often. Compare whole-life cost and ask for the replacement interval in writing.
Does a UPS need CEIG approval?
The UPS is part of the electrical installation. In many states the inspector's drawing approval covers the installation's single-line diagram and equipment, so the UPS and its supply should be on the drawings. Requirements differ by state and installation size, so confirm with your electrical inspectorate before you finalise the scheme.
Related services
Related guides
- Your Shopfloor Is Probably Lit Wrong in Both Directions at Once
- MEPF Cost per Sq Ft in India: How to Build a Budget You Can Defend
- One Bill, Six Tenants, and No Way to Prove Who Used What.
- A Digital Twin Is Not a 3D Model. It Is a Live Data Obligation.
- The Most Dangerous Electrical Installation You Will Ever Own Is the Temporary One
- How to Prequalify an MEP Contractor for a Factory: The PQ Checklist
Related on this site
- termLT vs HT Distribution
- termCAPEX vs OPEX Solar
- termOpen Access (Solar)
- serviceIntrusion, X-ray & Entrance Automation (Low Voltage / ELV)
- calculatorFactory Downtime Cost Calculator
- calculatorEV Charging Load Calculator
- buyer's guideHow to Select an MEP Contractor
- guideFactory licence and DISH approval
- guideCTE/CTO pollution consent
More on Electrical & Power · all insights