Documents Required for a Fire NOC Application: The Complete List by Stage
A Fire NOC application runs in two stages. The provisional or pre-construction stage needs the approved building plan, drawings with the fire systems marked, the design calculations and the applicant's forms and proof of ownership. The final or occupancy stage needs as-built drawings, completion and equipment certificates and sometimes an audit or licensed-agency certificate. Each state's checklist differs.
What are the two stages, and what does each one approve?
Delhi Fire Service's published FAQ states the pattern most clearly. For buildings covered by rule 27 of the Delhi Fire Service Rules, 2010, which includes industrial and storage buildings with a covered area above 250 square metres on all floors and hazardous buildings above 100 square metres, the first stage comes before construction, when plans are approved and fire safety recommendations are issued. The second stage comes after construction and before occupancy, when the installed measures are verified and a Fire Safety Certificate is issued. Other states use their own names for the same idea: Rajasthan separates "temporary, pre-construction" and "final, post-construction" applications, Telangana separates a provisional NOC from an occupancy NOC, and Odisha issues a Fire Safety Certificate with an installation certificate from a Licensed Agency.
So your document list depends on the stage. Carrying a stage-one file into stage two is the usual way an application is returned.
Which documents go with each stage?
The table sets out what the state sources below ask for. It is not one state's checklist; use it to see what to assemble, then check your own state's portal.
| Document | Provisional or pre-construction | Final or occupancy | Where a state source asks for it |
|---|---|---|---|
| Approved building plan | Yes, or referred through the sanctioning authority | Approved plan again | Delhi (UBBL 2016 clause 2.8), Rajasthan, Odisha Form III |
| Drawings with fire systems marked | Site, basement, ground, floor-wise, terrace, section and elevation, systems marked in red | As-built drawings of the same set, certified by architect and engineer | Telangana, Rajasthan, Delhi |
| Sprinkler hydraulic calculations and layout | Yes, with the plans | Reflected in as-built | Delhi |
| Smoke control calculations and layout | Yes, where smoke ventilation applies | Reflected in as-built | Delhi |
| Application forms and ownership proof | Common application form; ownership, lease or rent proof | Forms again; previous NOC if renewing | Delhi (CAF), Himachal Pradesh, Rajasthan, Uttar Pradesh (Forms A, B, C) |
| Non-deviation affidavit and tax receipt | Yes (Rajasthan) | Yes (Rajasthan) | Rajasthan |
| Cost estimate, bank guarantee, risk report | For large industries and buildings above 15 m (Telangana) | Third-party safety audit report for the same class | Telangana TS-iPASS page |
| Installation certificate from executing agency | Not usually | Licensed Agency certificate, Form IV-A | Odisha |
| Extinguisher test records | Not usually | Explosive certificate for CO2 units, hydraulic pressure test reports, manufacture-year proof, location list | Himachal Pradesh |
What does the drawing set have to show?
Drawings are where most applications are won or lost. Delhi Fire Service asks for architectural plans drawn to the scale in the bye-laws, marking the fire control room, the fire pump house with direct access, fire water tanks, ladders, yard hydrants, ventilation cut-outs and fire shafts, plus the sprinkler design calculation and schematic layout, the smoke control calculation and layout, and the filled common application form. Telangana's list asks for the drawings to be signed by the builder or owner and an authorised technical person, with fire-fighting systems marked in red; it adds that deviations from approved drawings can lead to prosecution of the builder, architect and site engineer under its fire service act.
Two practical points follow. The fire drawings must match the building plan the authority has approved, down to the pump room position. And the calculations must be a document, not a note on the drawing: sprinkler hydraulics and smoke ventilation sizing are reviewed separately. Our guide to the MEP drawing set that approvals actually need lists the drawings across Fire NOC, CEIG and DISCOM, and our note on plan changes and resubmission explains what a mid-project change triggers.
What do you need at the final stage?
The final stage is about proof that what was built matches what was approved. In Rajasthan this means a copy of the approved plan, as-built drawings showing the complete fire-fighting plan, the non-deviation affidavit and the deposit and tax receipts. Telangana asks for as-built plans, four copies of the provisional NOC drawings corrected as built and certified by a competent architect and engineer, certified electrical drawings and equipment specifications, and, for large industries and buildings above 15 metres, a third-party safety audit report. Himachal Pradesh's checklist lists the extinguisher test records noted above. In Odisha, the installation certificate comes from the Licensed Agency that executed the work.
The contractor should hand over, with the as-built set, the records the officer may ask for even where your state's checklist does not list them: pump test and performance records, hydrant and sprinkler pressure and flow tests, detection and alarm test records, and equipment datasheets. Ask the authority whether it wants them with the application or at inspection. Delhi's FAQ also notes that the owner or occupier carries the duty to install and maintain the systems and that Delhi Fire Service does not authorise any vendor.
In what order should you assemble the file?
- Confirm the stage and the checklist on your state's portal, and note whether it asks for a fee, a form number or a particular file format.
- Collect the approved building plan or the sanction reference, and the ownership or lease proof.
- Issue the fire drawings and calculations against that plan, and have them signed by the people your state names.
- Add the stage-specific items: affidavit, estimate, risk report, licensed-agency certificate or test records.
- Have a second engineer read the file against the checklist before upload.
What timelines and renewals should you plan around?
Timelines are state-specific. Telangana's page states 14 days for provisional or occupancy NOCs for buildings above 15 metres and 7 days for 15 metres and below, under its citizen's charter. Himachal Pradesh states 30 days under its Public Service Guarantee Act. Delhi's Fire Safety Certificate is valid for three years for non-residential buildings and renewal is applied for at least six months before expiry. Use the Fire NOC calculator for a first view of the system your building is likely to need, and the guide to renewals for the later stage.
How Secured Engineers helps
We prepare and file Fire NOC applications in-house, with the design, drawings, calculations and as-built records produced by the same engineers who execute the fire fighting and electrical work. MEPF and solar can sit under one contract. We work from offices in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients. Our Fire NOC assistance service covers the application, the drawings and the follow-up with the authority.
If you have a file ready or half ready, send it and we will tell you which documents are missing for the stage you are at, before the authority returns it. Message us on WhatsApp, call +91 70099 85817, or ask for a free proposal.
Frequently asked
What documents are needed for a provisional Fire NOC?
Typically the approved building plan or its reference, fire-fighting drawings with the systems marked, sprinkler and smoke calculations where they apply, the application forms, and proof of ownership or tenancy. Rajasthan also asks for a non-deviation affidavit and tax receipt, and Telangana asks large industries for a cost estimate, bank guarantee and risk analysis report. Check your state's current checklist.
What is needed for the final or occupancy Fire NOC?
As-built drawings certified by the architect and engineer, the approved plan, and records showing the systems were installed and tested. Odisha asks for the Licensed Agency's installation certificate; Himachal Pradesh lists extinguisher test records; Telangana asks large industries and buildings above 15 metres for a third-party safety audit report. Plan to hand over pump, hydrant, sprinkler and alarm test records in any case.
Do I need drawings in a particular format?
Yes, in most states. Telangana lists site, basement, ground, floor-wise, terrace, section and elevation plans with the fire-fighting systems marked in red, signed by the owner and an authorised technical person. Delhi asks for plans to the bye-law scale with the pump house, tanks, hydrants, ladders and shafts marked. Rajasthan's portal takes PDF copies. Confirm the format on your state's portal before drawing.
Why do Fire NOC applications get returned?
The common cause is a mismatch between stages or documents: fire drawings that do not match the approved plan, missing calculations, or a stage-one file submitted for stage two. Deviations from approved drawings can also draw penalties; Telangana's page refers to prosecution of builder, architect and site engineer. Check the documents against your state's list before filing.
Is a fee payable for Fire NOC documents?
It depends on the state. Delhi Fire Service states that it charges no fee for plan approval, the Fire Safety Certificate or its renewal, and Himachal Pradesh states that no fee is charged for the NOC. Telangana and Rajasthan collect a fee online. Check the fee schedule on your own state's portal before you budget.
Related services
Related guides
- Common problems we find in existing fire pump rooms
- How should a factory plan fire pump capacity?
- Firestopping and Fire Doors After a Renovation: Restoring Fire Separation
- The Lights That Only Matter When Everything Else Has Failed
- A Sprinkler Head Is Easy to Approve. A Clean-Agent System Is Not.
- Hydrants or Sprinklers: How the Design Requirement Is Determined
Related on this site
- termWet Riser
- termFire Damper
- termFire NOC
- serviceGas & Special-Hazard Suppression (Fire Protection)
- serviceFire Pumps & Pump Room (Fire Protection)
- calculatorMEP Maintenance Budget Calculator
- calculatorFire Noc Calculator
- buyer's guideHow to Evaluate Fire Protection Quotes
- guideCEIG approval for factories
- guideFactory approvals roadmap, India
More on Fire Safety · all insights