Solar EPC for Factories in Maharashtra: DISCOM Rules, Approvals and Cost
A factory in Maharashtra planning 50 kW or more of rooftop solar usually follows one of four routes: net metering, net billing, behind-the-meter use with limited export, or captive and open-access supply for larger plants. MSEDCL supplies most of the state and MERC sets the rules. The cost band for commercial and industrial plants is ₹24,000–32,000 per kW excluding GST.
Who decides what in Maharashtra
Four bodies matter. The distribution licensee, usually MSEDCL but in parts of Mumbai and a few other areas another licensee, decides technical feasibility and signs the connection agreement. The Maharashtra Electricity Regulatory Commission (MERC) sets the rooftop solar regulations and the tariff for surplus energy. The Electrical Inspectorate of the Government of Maharashtra approves the installation and permits charging where an inspection is required. The state nodal agency for renewable energy, MEDA, runs the state's renewable-energy programmes. Confirm which licensee supplies your plant before anything else, because the application portal and the circulars differ.
Nationally, the Electricity (Rights of Consumers) Rules, 2020, as amended in 2021, say that where state regulations do not provide for net metering or net billing, the commission may allow net metering for loads up to 500 kW or the sanctioned load, whichever is lower, with net billing or net feed-in for larger loads. These central rules sit above the state regulations, and the state commission's own text governs your plant.
The four routes compared
| Route | How it works | Capacity guide | Fits when |
|---|---|---|---|
| Net metering | One bidirectional meter; exported units are set against imported units on the same bill | Capped by the MERC regulations against sanctioned load or contract demand; check the current cap | The plant exports on weekends or holidays and you want credit for it |
| Net billing | Imports and exports are valued at different rates; surplus is credited at a rate the commission sets | Used for larger plants or where net metering is not allowed | Daytime load is lower than generation for much of the year |
| Behind-the-meter, limited or zero export | Plant is sized to the site's own load; an export-limiting device keeps power from flowing back | Set by roof and load, within the licensee's connection terms | Load is steady and high in daytime, or the feeder cannot take export |
| Captive, group captive or open access | Power is supplied to the consumer through the grid or from a dedicated plant, with settlement and charges | Larger plants, typically above the net-metering ceiling | The load is large and a rooftop cannot supply enough of it |
On the cap, trade-press reports from November 2023 say MERC amended its regulations to allow net metering up to 5 MW or the consumer's contract demand or sanctioned load, whichever is lower. We have not read the amended regulation, and the state has changed rooftop terms more than once since 2019, so treat the number as a lead to check, not a figure to design against. MERC's own site and MSEDCL's circulars are the authority. Our open access solar page explains the larger-plant route.
What the approval process looks like
- Technical feasibility. You apply to the distribution licensee with a single-line diagram, load and sanctioned-demand details, and the proposed capacity. The licensee checks the local transformer and feeder, and the result decides whether you proceed and on what terms.
- Design and procurement. Inverters and modules must meet the technical requirements the licensee and MNRE specify. The structure design has to be checked for the roof or ground.
- Installation and inspection. Larger plants and any HT arrangement need the Electrical Inspector's approval before charging. The Inspectorate describes plan approval, inspection and permission to energise on its own site.
- Metering and agreement. The licensee installs or certifies the meter and signs the connection or net-metering agreement.
- Commissioning. Synchronisation takes place after approvals, with anti-islanding and protection tested.
Thresholds for which plants need the Inspector, and for which a test report from a licensed contractor suffices, are set in the state's rules and the licensee's procedure; confirm them for your capacity. If your plot is leased from an industrial authority, check whether the lease requires consent for a roof installation.
What the cost band means at three sizes
Our published band for commercial and industrial solar is ₹24,000–32,000 per kW excluding GST, covering design, supply, installation and commissioning for a conventional rooftop. Applied to three common sizes it gives a budget range, not a quote.
| Size | Budget range, excluding GST | What moves it inside the range |
|---|---|---|
| 100 kW | ₹24 lakh to ₹32 lakh | Roof type, structure, cable run to the panel |
| 500 kW | ₹1.2 crore to ₹1.6 crore | Number of roofs, HT or LT connection, metering |
| 1 MW | ₹2.4 crore to ₹3.2 crore | Transformer and HT work, ground-mount share, evacuation |
The ranges follow arithmetically from the band; the position within it depends on the site. The size pages explain what each includes: 100 kW, 500 kW and 1 MW. GST is added, and the rate on solar supply and works has changed in the past, so confirm the current rate when you budget. The solar calculator runs the savings on your own tariff and load. Tariffs and surplus-energy rates in Maharashtra have been revised through MERC orders, so use your latest bill and the current order, not an old figure.
Where the demand is and what to check by cluster
Industrial demand sits in MIDC estates and clusters: Pune and its Chakan and Ranjangaon belt, Chhatrapati Sambhajinagar (Aurangabad), Nashik, Nagpur, the Thane–Belapur belt near Mumbai, and smaller industrial towns across Western Maharashtra. Before choosing a route, check the following for your plot: the sanctioned load or contract demand, since it caps the export route; the roof's age and load capacity; whether the plot has other generation such as a DG; and the licensee's feeder capacity. A factory that already buys power through open access should check how that interacts with rooftop net metering, as the rules treat the two together.
How Secured Engineers helps
We are a pan-India solar EPC and MEPF contractor, and we mobilise to Maharashtra from our offices in Noida (Delhi NCR) and Ludhiana. This article is a buyer's guide; it does not describe projects we have delivered in the state. What we offer is the process: design in-house, and Fire NOC, CEIG and DISCOM net-metering applications filed in-house, with MEPF and solar under one contract if your factory needs both. The company has completed 535+ projects across 18+ states, with 89.77% repeat clients.
To get a budget range for your roof, send your last twelve bills, sanctioned load and roof photographs. See our solar EPC service, message us on WhatsApp or call +91 70099 85817, or ask for a free proposal.
Frequently asked
Is net metering available for factories in Maharashtra?
Yes, within limits set by MERC's rooftop solar regulations. The cap is tied to sanctioned load or contract demand, and trade-press reports from November 2023 mention a ceiling of 5 MW. We have not read the amended regulation, so confirm the current cap and conditions with MSEDCL or your licensee before sizing the plant to it.
Who approves a rooftop solar plant in Maharashtra?
The distribution licensee approves technical feasibility and signs the connection agreement. The Electrical Inspectorate of the state approves the installation and permits charging where an inspection applies. MERC sets the regulations, and MEDA runs the state's renewable-energy programmes. Which approvals apply depends on plant size and voltage level, so check your case with the licensee.
Does the cost of ₹24,000 to ₹32,000 per kW include GST?
No, the band is excluding GST. GST is added at the applicable rate, which has changed in the past, so confirm it at the time of budgeting. The band covers a conventional rooftop plant; a ground mount, a long cable run, HT work or an unusual roof can move a project outside it.
What is zero export and when does a factory need it?
Zero export is a control that keeps a plant from sending power into the grid, using a meter and a controller that cut inverter output. A factory needs it when net metering is not available or the licensee will not permit export. The plant is then sized to your own daytime load.
Does Secured Engineers have projects in Maharashtra?
This guide does not claim any. We are a pan-India EPC based in Noida and Ludhiana and mobilise to other states; the projects we publish are listed on our projects page. Ask us for references relevant to your site and we will tell you plainly what we have and have not delivered.
Related services
Related guides
- A Plant Down 8% Looks Exactly Like a Plant Working Fine.
- Three Vendors, One Roof, Three Different Generation Figures.
- Perovskite Cells Promise 30%+ Efficiency. Your Roof Doesn't Have Ten Years to Wait and See.
- The Array Is Built. The Protection Settings Decide Whether It Ever Exports.
- Size Rooftop Solar Against Your Factory's Daytime Load, Not the Roof
- Your Solar Plant Sleeps Through Your Evening Peak. A Battery Doesn't Have To.
Related on this site
- termALMM
- termNet Metering
- termOpen Access (Solar)
- serviceBattery / Hybrid Storage (Solar EPC)
- serviceNet-Metering, Metering & Monitoring (Solar EPC)
- calculatorSolar Roof Load Calculator
- calculatorSolar Sanctioned Load Calculator
- buyer's guideHow to Select a Solar EPC Contractor
- guideCTE/CTO pollution consent
- guideEnvironmental clearance (EIA 2006)
More on Solar & Renewables · all insights