HT Panel Specification for a Factory: VCB, Relays, Metering and What to Demand
An HT panel specification for a factory should state the fault level at your point of supply, the breaker and busbar ratings that follow from it, the construction (metal-clad, compartmented, draw-out vacuum breaker), the protection relays, the metering classes, and the type-test evidence you will accept. Get the fault level from the DISCOM first. Every other rating follows from it.
What do you fix before you write the specification?
Five inputs go in the document header, and a bidder cannot price honestly without them.
- Fault level at the point of supply. Ask the DISCOM for the prospective short-circuit level at your incomer in writing. The breaker's breaking and short-time ratings must exceed it, with margin for growth.
- System voltage and earthing. 11 kV or 33 kV, and how the neutral is earthed at the transformer.
- The single-line diagram. Incomer, metering, bus section, transformer feeders, capacitor or DG feeders, and which breakers are spare.
- Site conditions. Ambient temperature, altitude, dust, humidity, and whether the room is indoor, ventilated or air-conditioned.
- Auxiliary supplies. The DC supply and battery charger for tripping and closing, and the control voltage you will provide.
Our notes on HT connection and substation approval and on transformer undersizing cover the load side. The HT and LT distribution page shows the full substation scope.
What should the switchgear and breaker clauses say?
A distribution company's own specification is a good model of how detailed a clause can be. Maharashtra's MSEDCL specification for 11 kV, 25 kA indoor switchgear with control and relay panels, issued in 2020, is written for its substations, not for a consumer plant, so do not copy its ratings. Copy its discipline. It names IEC 62271-100 for breakers and IEC 62271-200 for the switchgear assembly, and it writes down each requirement a bidder can be tested against.
| Item | What to write | Evidence to demand |
|---|---|---|
| Construction | Metal-clad, compartmented (breaker, busbar, cable, LV), draw-out, safety shutters | General arrangement drawing; compartment layout |
| Rated voltage and insulation level | 12 kV system with 28 kV one-minute and 75 kV impulse withstand for 11 kV in that specification | Type-test report for the offered design |
| Breaker | Vacuum, draw-out, motor-charged spring, anti-pumping, mechanical endurance class stated | Breaker type-test report; mechanical endurance test |
| Short-circuit ratings | Breaking, making and short-time current (25 kA for 3 s in that utility's spec); yours from the fault level | Short-circuit and short-time withstand test reports |
| Busbars | Same short-time rating as the breaker; phase and earth clearances stated | Busbar test certificate; temperature-rise test |
| Internal arc | State the arc classification, duration and accessibility you require | Internal arc test report to IEC 62271-200 |
| Enclosure | Degree of protection stated for the panel and for the breaker compartment | Ingress protection test |
| Interlocks | Breaker, isolator, earthing switch and door interlocks, as the regulations require | Interlock schedule; demonstrated at the works |
| Earthing | Earth bus, earthing trolley or earthing switch for each feeder | Drawing; supplied quantities in the BOQ |
On interlocks the rule is statutory. The CEA Safety Regulations, 2023, regulation 47, require isolators and their controlling breakers to be interlocked so the isolator cannot operate with the breaker closed, earthing switches to be interlocked so they cannot close unless the isolator is open, and access doors to live parts to be interlocked so they cannot open until the parts are dead, discharged and earthed.
How do you specify relays, current transformers and metering?
The same MSEDCL specification requires numerical relays with three over-current elements and one earth-fault element, with high-set, draw-out construction with automatic shorting of the CT circuit when the relay is removed, and a standard communication protocol for remote monitoring. Current transformers carry a 0.2 class metering core and a protection core, a short-time rating equal to the panel's, and an instrument security factor of not more than 5 for the metering core. These are good clauses to ask a bidder to meet or to state a deviation from.
The regulations add protection that the panel and its feeders must provide. Regulation 47 requires over-current and earth-fault protection on all circuits, Buchholz, pressure-relief and winding and oil temperature protection on transformers of 1,000 kVA and above, earth-fault protection on generators of 100 kVA and above, and restricted earth-fault or differential protection on generators of 1,000 kVA and above.
Billing metering is a DISCOM matter. Ask the DISCOM for its metering cubicle drawing, the CT and PT ratios and the sealing arrangement before you finalise the incomer. Metering accuracy is set under the CEA metering regulations; Odisha's supply code, restating them, puts meters above 650 V and up to 33 kV at class 0.5S or better, with CTs and PTs no worse than the meter, but confirm the class and ratios in force with your DISCOM.
What does protection coordination mean for the buyer?
Relays are only as good as their settings. The incomer's settings must grade with the DISCOM's upstream protection, and each feeder must grade with the incomer, so a transformer fault trips its own breaker and not the whole plant. Make the settings study a deliverable: a coordination study with time-current curves, the fault levels used, and a settings schedule for every relay. Require secondary-injection testing of every relay at commissioning with the results in the handover file, and ask for the settings to be recorded so a replacement relay can be set identically. For the hazard side, our note on arc flash studies explains why the incident energy at the panel depends on the clearing time you set.
What type tests and site tests do you ask for?
MSEDCL's specification asks for type tests at an accredited laboratory within the last five years, on the offered design: lightning impulse, power-frequency withstand, short-time and peak withstand, short-circuit duties, single-phase breaking, cable-charging breaking, temperature rise and the internal arc test on the panel; a mechanical endurance test on the breaker; and tests on CTs and PTs including partial discharge and accuracy. If the reports are older than five years, it requires the tests to be repeated before supply. Ask for the same, with routine tests witnessed at the works.
At site, specify insulation resistance and contact resistance, breaker timing, interlock operation, relay secondary injection, CT ratio and polarity, and a functional trip test from the relay to the breaker. Then the Electrical Inspector inspects before energisation; our guide to CEIG approval for factories lists the file. Our guide to electrical testing and commissioning covers the site tests in detail.
How Secured Engineers helps
We design HT and LT distribution and write the equipment specifications in-house, file Fire NOC, CEIG and DISCOM applications in-house, and deliver MEPF and solar under one contract, so the HT room, the transformer yard and the solar interconnection are specified together. We work from offices in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients.
Send your single-line diagram, the DISCOM's fault level and the specification or quotation you are comparing, and we will review it line by line and tell you what is missing or under-rated. See our electrical infrastructure page, message us on WhatsApp, call +91 70099 85817, or ask for a free proposal.
Frequently asked
What short-circuit rating should an 11 kV factory panel have?
It must exceed the prospective fault level at your point of supply, with margin for growth. Ask the DISCOM for the figure in writing and choose the standard rating above it. Ratings seen in utility specifications, such as 25 kA for 3 seconds at 11 kV, are for those utilities' substations, not a default for a consumer plant.
Vacuum or SF6 breaker for a factory HT panel?
Vacuum breakers are the common choice at 11 kV and 33 kV for indoor factory panels, with long maintenance intervals and no gas handling. SF6 is used in some compact designs and at higher voltages, and adds gas-handling rules. Whichever you choose, ask for the breaker type-test reports and the mechanical endurance class, not the technology name alone.
Do I need an internal arc classified panel?
It is a risk decision, not a statutory default. Internal arc classification limits the harm to people in front of the panel if an arc occurs inside. Where operators stand in front of the panel during switching, specify it and ask for the type-test report, with the arc duration and accessibility class stated. Pair it with an arc flash study.
Who supplies the HT metering CTs and PTs?
It depends on the DISCOM. Many DISCOMs require a sealed metering cubicle to their own drawing, with CT and PT ratios and accuracy classes they set, supplied by the consumer and tested and sealed by the utility. Ask for the DISCOM's metering specification before you finalise the incomer panel, because changing it after delivery is costly.
What do I get from a protection coordination study?
A set of time-current curves showing every relay grades with the upstream and downstream devices, the fault levels used, and a settings schedule for each relay. It lets a transformer fault clear at its own breaker rather than the incomer. Ask for it before commissioning, test the relays by secondary injection, and keep the settings in the handover file.
Related services
Related guides
- Your Shopfloor Is Probably Lit Wrong in Both Directions at Once
- MEPF Cost per Sq Ft in India: How to Build a Budget You Can Defend
- One Bill, Six Tenants, and No Way to Prove Who Used What.
- A Digital Twin Is Not a 3D Model. It Is a Live Data Obligation.
- The Most Dangerous Electrical Installation You Will Ever Own Is the Temporary One
- How Long a 500 kW Solar Plant Really Takes: Approvals, Procurement and Site Work
Related on this site
- termTurnkey EPC
- termDG Set Sizing
- termOpen Access (Solar)
- serviceWater Supply & Distribution (Plumbing)
- serviceEPABX & Intercom (Low Voltage / ELV)
- calculatorMEP Quotation Comparison Calculator
- calculatorSolar Capex vs Opex Calculator
- buyer's guideHow to Compare MEPF Quotations
- guideNBC 2016 fire and life safety for factories
- guideFire NOC for factories
More on Electrical & Power · all insights