CEIG Approval for a Transformer Installation: Drawings, Tests and Energisation
A transformer that steps an 11 kV or higher supply down to 415 V needs the Electrical Inspector's attention before it is energised. Under the CEA safety regulations of 2023 you file drawings, produce the manufacturer's test certificates, complete site tests, and show the earthing, oil and fire provisions. Whether the inspector visits or you self-certify depends on the voltage your state has notified.
When does a transformer need CEIG approval?
Chapter VI of the CEA (Measures relating to Safety and Electric Supply) Regulations, 2023 covers installations of voltage exceeding 650 V, and a transformer fed at 11 kV or 33 kV sits squarely inside it. Regulation 45 then splits installations at a voltage that each state notifies. Above that notified voltage, the Electrical Inspector must inspect and test the installation before supply starts, or restarts after a shutdown of six months or more. At or below it, the owner inspects, tests and self-certifies, and files the report on the Schedule II form with the inspectorate.
The notified voltage is the state's to set, so do not assume the answer from another state's practice. Ask the state inspectorate which route applies to your connection voltage, and read our wider note on CEIG approval for factories for the state-by-state guides. Two situations always reopen the question: adding a second transformer or raising the rating of an existing one (regulation 45(6) requires written approval or self-certification for additions and alterations), and restarting a plant that has been shut for six months.
What goes into the drawing submission?
The inspectorate reviews the scheme on paper before the equipment is built. A transformer file is only as good as its single-line diagram, and the diagram must agree with the DISCOM sanction and the load schedule. These are the documents a reviewer normally expects; the exact list and forms are the state's.
| Document | What the reviewer reads it for | The usual gap |
|---|---|---|
| Single-line diagram | Incomer, metering, breakers, transformer, LT side, DG interface | Rating differs from the DISCOM sanction or the machinery list |
| Transformer data sheet | kVA, voltage ratio, vector group, oil or dry type, cooling, protection fitted | Type chosen after layout, so oil volume and room do not match |
| Substation layout | Clearances, access, ventilation, fencing or room walls, cable routes | Equipment pushed against walls, no space to operate or maintain |
| Earthing design | Grid, neutral connections, pit locations, touch and step potential basis | One neutral connection drawn where two separate ones are required |
| Protection and interlock scheme | Relays, trip logic, isolator and earth-switch interlocks | Transformer protection missing for the rating |
| Oil containment and fire provisions | Soak pit, barrier walls, extinguishers, detection | Added late, after the civil work is set |
| Manufacturer's test certificates | Type, routine and acceptance test evidence | Certificates arrive after inspection is requested |
What do the regulations require of the transformer itself?
Several rules in regulations 46 to 48 turn directly into design decisions, and they are cheaper to meet on paper than in a finished substation.
- Earthing of the neutral. Regulation 50(2) requires the neutral point of every transformer in a star-connected system with earthed neutral to be earthed through not less than two separate and distinct connections to the earthing system. The earthing system must keep touch and step potential within tolerable values (regulation 50(1)).
- Protection by rating. Regulation 47(2) requires a Buchholz relay, a pressure relief device, and winding and oil temperature protection, with alarm and trip contacts, on transformers of 1000 kVA and above. Differential protection is required from 10 MVA.
- Switching either side. Regulation 37(3) requires a linked switch with fuse, an air-break switch with fuse or a circuit breaker on the primary side of every transformer, with a circuit breaker required from 1000 kVA, and a circuit breaker of adequate rating on the secondary side (a linked switch with fuse is allowed there for supplier transformers below 1000 kVA).
- Interlocks. Isolators and their breakers are interlocked, isolators and earthing switches are interlocked, and where transformers run in parallel the secondary breaker of a transformer must trip when its primary breaker trips (regulation 47(1)).
- Clearances. Safety clearances follow the relevant standards, and the minimum working clearances in Schedule V apply to bare live parts in outdoor substations (regulation 46(2)).
- Outdoor fencing. An outdoor substation is fenced at not less than 1.8 metres, and the fence is earthed (regulation 51).
Oil-filled or dry-type: what changes at inspection?
The choice drives the civil work, the fire provisions and the questions the inspector asks. Regulation 46(2) is explicit on both types.
| Point | Oil-filled transformer | Dry-type transformer |
|---|---|---|
| Where regulation 46(2) allows it | Indoors in a factory on the ground floor or not below the first basement | The only type permitted inside residential and commercial buildings |
| Oil containment | Soak pit; for apparatus with more than 2000 litres of oil, fire barrier walls or a 4-hour rated adjacent wall; draining arrangements where an oil tank holds more than 9000 litres | Not applicable |
| Basement | Not with more than 2000 litres of oil unless oil can be drained away; basement rooms need direct outside access, 4-hour rated walls, 2-hour rated doors, a curb and sealed cable openings | Basement rules on cable sealing and low-smoke cable still apply |
| Fire arrangements | Fire detection and protection suited to the apparatus; automatic fire fighting from 10 MVA | Detection and extinguishers per the fire scheme |
| What it costs you in design | Larger plot or room, drainage, fire barrier, more civil work | Higher equipment price per kVA, simpler civil work |
Spare oil may not be stored near oil-filled equipment (regulation 46(2)(vii)(c)), and cable trenches inside the substation must be filled with sand or similar non-inflammable material or covered with non-inflammable slabs. Decide the type before the layout is frozen, because the layout follows from it.
What tests come before energisation?
Regulation 48 sets the order. Before the Electrical Inspector approves, the manufacturer's test certificates for type, acceptance and routine tests are produced if required. New apparatus above 650 V cannot be commissioned until it has passed site tests under the relevant standards. Under regulation 45(5) the owner tests every circuit, other than an overhead line, to the testing voltage in regulation 48 and records the results for the inspector. The inspector may accept the manufacturer's certified tests for a particular item, and may ask for further tests before or after charging.
The supplier may energise the apparatus for those tests (the proviso to regulation 45(4)), but supply to the plant waits for written approval. In practice the site file holds insulation resistance, ratio and vector group checks, oil tests where relevant, relay secondary injection, interlock trials, and earth resistance for every pit and for the grid. Every earthing system, whether the supplier's or the consumer's, is tested for resistance on a dry day in the dry season at least once a year, with records kept for the inspector (regulation 50(8)).
How does this connect to the DISCOM?
The DISCOM will not connect an installation that needs inspector approval without it, and the DISCOM's metering arrangement must match the approved diagram. File the CEIG drawings in parallel with the DISCOM load sanction so neither department waits on the other. Our guide to HT connection and substation approval covers the DISCOM side, and the transformer sizing calculator gives a first kVA from connected load and demand factor before you commit to a rating.
How Secured Engineers helps
We design the substation in-house, so the single-line diagram, layout, earthing and protection scheme are drawn once and agree with each other. Fire NOC, CEIG and DISCOM net-metering filings are handled in-house by the same team, and MEPF and solar can sit under one contract. We work from our Noida (Delhi NCR) and Ludhiana offices, across 535+ projects in 18+ states, with 89.77% repeat clients. For a transformer file we review the drawings against regulations 45 to 51 before they go to the inspectorate, and we rectify gaps found in an existing installation.
If you have a transformer file ready or half built, send it to our CEIG approval team for a review of your file, message us on WhatsApp, call +91 70099 85817, or ask for a free proposal.
Frequently asked
Does every transformer need Electrical Inspector approval?
Every installation above 650 V falls under Chapter VI of the 2023 regulations. Regulation 45 then depends on the voltage your state has notified: above it the Electrical Inspector inspects and approves, at or below it the owner self-certifies on the Schedule II form. Adding a transformer or raising its rating reopens the process. Ask your state inspectorate which route applies.
What is the difference between self-certification and inspector approval?
Under regulation 45(1) the owner inspects, tests and self-certifies installations at or below the notified voltage, and the report is deemed received if not acknowledged within three working days. Above the notified voltage the Electrical Inspector inspects and tests before supply starts. An owner who self-certifies may still choose to have the Electrical Inspector inspect the installation.
Which test certificates does the inspector ask for?
Regulation 48(1) provides that the manufacturer's certificates for type, acceptance and routine tests are produced before approval, if required. The inspector may accept certified manufacturer tests for particular apparatus in place of site repeats, and may still require other tests before or after charging. Keep the certificates with the serial number of the transformer delivered to site.
Can I use an oil-filled transformer inside a building?
Regulation 46(2) allows oil-filled transformers indoors in buildings other than residential or commercial ones, on the ground floor or not below the first basement. Only dry-type transformers may be used inside residential and commercial buildings. Basement rooms need extra provisions such as outside access, rated walls and doors, and a curb. Confirm your building's classification with the authority.
How is the transformer neutral earthed?
In a star-connected system with an earthed neutral, regulation 50(2) requires the neutral point of every transformer to be connected to the earthing system by not less than two separate and distinct connections. The whole earthing system must also keep touch and step potentials tolerable, and earth resistance is recorded and retested at least once a year (regulation 50(8)).
Can the DISCOM energise the transformer before approval?
For installations that need inspector approval, supply cannot commence until the written approval is obtained. Regulation 45(4) lets the supplier energise the apparatus only for the tests listed in regulation 48. Plan the sequence so the CEIG file and the DISCOM sanction move together.
Related services
Related guides
- Addressable Lighting Control Pays in Some Buildings and Not in Others.
- The Thresholds Moved. Your Factory May Have Changed Category Without Doing Anything.
- Your Shopfloor Is Probably Lit Wrong in Both Directions at Once
- The MSME Act Just Changed. Here Is What It Means for a Factory Owner.
- DG Expansion and Synchronisation: Set the Backup Boundary First
- The Building Isn't Open Yet. The EV Mandate Already Applies.
Related on this site
- termPower Factor Correction
- termTransformer Sizing (kVA)
- termContract Demand
- serviceEarthing & Lightning Protection (Electrical)
- serviceLighting & Small Power (Electrical)
- calculatorFactory Electrical Capacity Calculator
- calculatorEV Charging Load Calculator
- buyer's guideHow to Select an MEP Contractor
- guidePESO licence for diesel storage
- guideFactory licence and DISH approval
More on Electrical & Power · all insights