Skip to content
Secured Engineers Pvt. Ltd. logo
Home
Company Insights Resources Locations & project coverage About Founder — Er. Ankur Kaplesh
Services Mechanical / HVACElectricalPlumbingFire ProtectionLow Voltage / ELVSolar EPCMEP Consultancy & ApprovalsAMC / MaintenanceTurnkey EPCFire NOC AssistanceCEIG Liaison & EnergisationTesting & Commissioning AI Video Analytics
Industries Manufacturing & IndustrialHealthcare & HospitalsHospitality & HotelsWarehousing & LogisticsGovernment & DefenceEducation & InstitutionsData CentrePharmaceutical & CleanroomCold StorageTextile & ApparelAutomobile & Auto-ComponentsFood Processing & FMCGChemical & Process Industries
Free Tools ★ Architect & Design Resource Hub All 56 calculators Solar Financial Calculator Fire Water Storage Checker Fire Pump Room Calculator AC Tonnage Calculator DG Load Calculator MEPF Budget Calculator
Projects Work With Us Get a Free Quote
Solar Energy

What a 5 MW Solar Plant Costs and Needs: Roof, Land, Connection and Approvals

22 October 2026 · 5 min read · by

Title card reading What a 5 MW Solar Plant Costs and Needs: Roof, Land, Connection and Approvals.
Title card. Not a photograph of a Secured Engineers site.

A 5 MW solar plant for a factory costs roughly ₹12–16 crore excluding GST if scaled from the Secured Engineers C&I band of ₹24,000–32,000 per kW, with a plant this size nearer the lower end. It needs about five lakh sq ft of roof or around 20 acres of ground, an 11 kV or 33 kV connection, and a captive or open access approval, not net metering.

What 5 MW costs, and what the figure leaves out

The company publishes a C&I solar band of ₹24,000–32,000 per kW excluding GST on its solar EPC page. The 1 MW page puts a megawatt at the lower end of that band, and a 5 MW plant buys modules, inverters and structures in larger lots. Treat the lower end as the starting point and every number below as indicative until a survey.

ItemIndicative
Plant size5,000 kW (5 MW)
Full band, ex-GST₹12–16 crore
At the 1 MW page's per-kW range of ₹24,000–26,000₹12–13 crore
Generation, north India (about 120 units per kW per month)About six lakh units a month, about 72 lakh a year
Rooftop area (about 100 sq ft per kW)About five lakh sq ft shadow-free
Ground-mount (about four acres per MW)About 20 acres; 17 to 25 in practice
Not in the bandLand, evacuation line beyond your boundary, a new bay or substation if the DISCOM asks for one, SPV set-up, GST

The band assumes a connection point already exists. At 5 MW that is the assumption most likely to fail, so settle it first. Smaller sizes are covered on the 100 kW, 250 kW and 500 kW pages. Run your own bill through the payback calculator.

Roof, ground or off-site: where does 5 MW go?

Five lakh sq ft of clean roof is rare on one site, and a roof that large is usually many sheds of different heights. The three layouts behave differently.

LayoutAreaConnectionMain risk
Rooftop across shedsAbout five lakh sq ftBehind your meter at 11 kV or 33 kVRoof strength, shading between blocks, long DC runs
Ground-mount on your landAbout 20 acresBehind your meter, dedicated feederLand title, drainage, cable routes, boundary security
Off-site plant, open access or group captiveLand elsewhere, often in the same stateGrid injection point, wheeling to your meterCharges, banking limits, delivery losses, contract term

Where the roof cannot take the full plant, a hybrid is common: roof for the daytime base load and an off-site plant for the rest. Our articles on ground-mount solar on factory land and captive versus open access cover the trade-offs. The solar calculator gives the first sizing against your load.

Why net metering stops applying

The central rules allow net metering for loads up to 500 kW, raised from 10 kW by a 2021 amendment to the Electricity (Rights of Consumers) Rules, 2020 (Ministry of Power review, via PIB). State regulations can be lower. A 5 MW plant therefore sits in a different regime, and you choose between three routes.

  • Own captive plant. Rule 3 of the Electricity Rules, 2005: the users together own at least 26% of the plant and consume at least 51% of its annual generation. An amendment notified in March 2026 clarified ownership through subsidiaries and holding companies, and provided for captive status to be verified by a state nodal agency (or NLDC for inter-state) from 1 April 2026, with cross-subsidy and additional surcharge not levied pending verification if a declaration is filed.
  • Group captive through an SPV. Several consumers hold equity in a special purpose company that owns the plant. The equity and consumption tests apply to the group, and a single factory that is the sole owner does not need an SPV.
  • Green energy open access. The 2022 Green Energy Open Access Rules lowered the open access limit for green energy from 1 MW to 100 kW, with approval in 15 days or deemed granted. Wheeling, cross-subsidy, additional surcharge and banking rules are set by your state commission, so compare them on your bill. See our open access solar page.

Module sourcing also matters. For open access and net-metering projects commissioned after 1 June 2026, MNRE requires cells from ALMM List-II unless it grants a case-specific extension (PIB, May 2026); an MNRE notice also refers to a limited window until 31 December 2026, which we could not read in full. Check how the order treats your structure, and confirm the current window on the MNRE site, before you place a module order; our note on ALMM List-II and commissioning explains the dates.

Interconnection and inverter architecture

At 5 MW the plant normally connects at 11 kV or 33 kV, depending on the DISCOM's feasibility study and your existing supply. That means a breaker bay, CT and PT metering, protection relays with reverse-power and frequency settings, and drawings approved by the state Electrical Inspector before energisation. Our article on connecting at 11 kV sets out the works, and the CEIG approval page covers the inspection.

A 5 MW plant is normally built in blocks, each with its own inverters and transformer, so a fault removes a block rather than the whole plant. String inverters give finer fault isolation; central inverters reduce the number of units. The choice depends on layout and service access; see string versus central inverters. Before design, check that the existing transformer and feeder can take the plant without tripping at low load, as in our transformer headroom note.

The order of work

  1. Bill analysis and daytime load profile, to decide how much of 5 MW you can actually absorb.
  2. Route decision: captive, group captive or open access, with the state charges checked.
  3. Site: roof survey or land title, soil and drainage, shadow study.
  4. Connectivity application and DISCOM or transmission feasibility letter.
  5. Design, single-line diagram, protection study and inspector drawing approval.
  6. Procurement with ALMM compliance, then civil, structure, electrical and HT works.
  7. Inspection, energisation, meter and open access or captive registration, then commissioning.

The connection letter and the inspector approval, not the installation, usually set the date. Insist on a programme that shows them as separate lines.

How Secured Engineers helps

Secured Engineers designs solar plants in-house and files the CEIG and DISCOM net-metering or registration applications in-house, with MEPF and solar under one contract where a site needs both. The company works from offices in Noida (Delhi NCR) and Ludhiana, with 535+ projects across 18+ states and 89.77% repeat clients. It can assess whether your load supports 5 MW before any money is committed.

To size the plant against your bill, start with the solar calculator, then send your last twelve bills and site details on WhatsApp, call +91 70099 85817, or ask for a free proposal.

Frequently asked

How much does a 5 MW solar plant cost in India?

Scaling the published Secured Engineers C&I band of ₹24,000–32,000 per kW excluding GST gives ₹12–16 crore for 5,000 kW. Larger plants sit at the lower end of the band, so the working range is nearer ₹12–13 crore for a plant with a ready connection point. Land, evacuation outside your premises, SPV costs and GST are extra. This is indicative, not a quotation.

How much land does a 5 MW solar plant need?

A planning figure is about four acres per MW for ground-mount, so roughly 20 acres for 5 MW, and 17 to 25 acres in practice depending on the layout, row spacing and terrain. Roof-mounted, it needs about 100 sq ft per kW, or around five lakh sq ft of shadow-free roof, which few single sites can offer.

Can a 5 MW plant use net metering?

Usually not. The central net-metering limit is 500 kW, after the 2021 amendment to the Electricity (Rights of Consumers) Rules, and state regulations can be tighter. A 5 MW plant normally supplies a factory as a captive plant or through open access, each with its own conditions on ownership, charges and banking.

What is a captive solar plant under the Electricity Rules?

Rule 3 of the Electricity Rules, 2005 treats a plant as captive if its users together own at least 26% of it and consume at least 51% of its annual generation. A March 2026 amendment clarified ownership through group companies and provided for verification of captive status by a state nodal agency or NLDC. Check your state's procedure.

How long does a 5 MW solar project take?

Installation is measured in months, not weeks, and approvals and the DISCOM or transmission connection usually decide the schedule. Ask for a programme that separates approvals, procurement, civil and electrical works, inspection and commissioning, and insist on the connection feasibility letter before you fix a date.

Related services

Send last month's electricity bill with your enquiry — sanctioned load, tariff and consumption are all on it, and they decide the answer.

Want to know what solar would actually do on your roof?

Tell us about your project — our engineers respond within one business day.

  • ★ 4.7 (230 Google reviews)
  • 535+ projects
  • Reply in 1 business day
Add details (optional — company, email, scope and site address)

🔒 Your details go straight to our team. No spam, ever.

Ready to start your project?

Get a free consultation and quote. We design, prepare and file your approvals, and execute — you deal with one team.

ONE PARTNER. END TO END. You focus on your business — we handle the rest.
Quality Safety Commitment
Send your bill An engineer reviews it